Riverland Const. Co. v. Lombardo Contracting Co.
This text of 380 A.2d 1161 (Riverland Const. Co. v. Lombardo Contracting Co.) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
RIVERLAND CONSTRUCTION COMPANY, A NEW JERSEY CORPORATION, PLAINTIFF-RESPONDENT,
v.
LOMBARDO CONTRACTING CO., INC., A CORPORATION, DEFENDANT-APPELLANT, AND TOWNSHIP OF BRIDGEWATER, A MUNICIPAL BODY, DEFENDANT-RESPONDENT.
Superior Court of New Jersey, Appellate Division.
*43 Before Judges HALPERN, LARNER and KING.
Mr. Richard K. Rosenberg argued the cause for appellant Lombardo Contracting Co., Inc. (Messrs. Rosenberg & Waldman, attorneys; Mr. Michael O. Renda on the brief).
Mr. Richard M. Salsburg argued the cause for respondent Riverland Construction Company.
Mr. William W. Lanigan argued the cause for respondent Township of Bridgewater (Messrs. Lanigan, O'Connell and Hirsch, attorneys; Mr. Andrew R. Jacobs on the brief).
The opinion of the court was delivered by LARNER, J.A.D.
This appeal arises out of a controversy relating to public bids for a sewer construction contract for a project planned by the Township of Bridgewater designated as "Charlotte Drive Edgewood Terrace Area Sanitary Sewers." On August 1, 1977, after appropriate advertising, *44 the township received ten competitive bids, with Lombardo Contracting Co. (Lombardo) submitting the lowest and Riverland Construction Company (Riverland) the second lowest. Since all other proposals were higher and since the two lowest bidders were concededly responsible and qualified, the issue for determination by the municipality and the trial court focused upon the validity of these bids and the appropriateness of the remedy in the event of rejection.
Lombardo's overall bid was $324,140.98, whereas Riverland's bid amounted to $331,414. These bids compared favorably with the estimate of the township engineer in the sum of $343,163. However, the municipality rejected the two lowest bids of Lombardo and Riverland on the ground that they were "unbalanced," relying upon a reservation in the specifications that proposals may be rejected if the prices are obviously unbalanced. The other bids were also rejected for a variety of reasons and a resolution was adopted August 15, 1977 calling for readvertising for new bids.
Thereupon Riverland instituted an action in lieu of prerogative writs seeking a declaration that it was the lowest responsible bidder and an order compelling the township to award it the contract. Lombardo filed an answer denying Riverland's claim to the contract as well as a cross-claim asserting invalidity of the resolution rejecting the bids and its right to the contract as the lowest responsible bidder. The municipality took the position that the rejection of all bids was legally warranted.
The matter was considered by the trial judge at a plenary hearing on September 20 and resulted in a judgment dated October 3 setting aside the resolution rejecting Riverland's bid, directing the township to award the contract to Riverland, affirming the rejection of Lombardo's bid on the basis that it is "sham, non-responsive and contrary to statute," and enjoining the municipality from readvertising for new bids.
*45 Lombardo alone appeals from that judgment. After granting a stay of the judgment we accelerated the appellate process in order to accommodate the public interest in early completion of the project.
The issue before us focuses solely on one of 38 items in the proposal which sought a per cubic yard unit bid for select fill to cover the sewer pipe after installation. Since the exact amount of fill could not be ascertained in advance of the work, the township sought a unit price based on the engineer's estimate of a required quantity of 8,078 cubic yards.
Lombardo, in submitting its total bid, included the unit price of one cent per cubic yard for the select fill, while Riverland submitted a price of $1 a cubic yard. As extended, and based on the engineer's estimate, Lombardo's bid for this item was approximately $80, while Riverland's bid for the same item was approximately $8,000. The township engineer, on the other hand, estimated the reasonable cost for this item as $5 per cubic foot, or a total of approximately $40,000. Based on the advice of its engineer the township considered both bids for select fill so low as to be unbalanced. The trial judge agreed as to the Lombardo "penny" bid, but found that the $1 bid was not so nominal as to render it "unbalanced." It was on that basis that he proceeded to find the Lombardo bid invalid and the Riverland bid to be the lowest valid responsible bid.
We conclude that under the facts gleaned from this record the trial judge erred in its determination that the Lombardo bid was illegal.
In Stamato v. New Brunswick, 20 N.J. Super. 340 (App. Div. 1952), we held:
An unbalanced bid comprehends a bid based on nominal prices for some work and enhanced prices for other work. The mere fact that a bidder has submitted an unbalanced bid, does not automatically operate to invalidate an award of the contract to such bidder. There must be proof of collusion or of fraudulent conduct on the part of such bidder and the city or its engineer or other agent, or proof of other irregularity of such substantial nature as will operate to affect fair and competitive bidding. Phifer v. Bayonne, 105 N.J.L. *46 524 (Sup. Ct. 1929); Walter v. McClellan, 113 App. Div. 295, 99 N.Y.S. 78 (App. Div. 1906), affirmed 190 N.Y. 505, 83 N.E. 1133 (Ct. App. 1907). [at 344]
See also, the majority opinion in Armaniaco v. Cresskill, 62 N.J. Super. 476, 482-484 (App. Div. 1960).
The record herein concededly does not contain an allegation or proof of any irregularity, collusion or fraudulent conduct or intent by Lombardo or the township, its engineer or other representatives, which would operate to taint the fair and competitive bidding contemplated by the applicable statutes and judicial decisions. Nor does the record present any evidence that the prices submitted by Lombardo for other items of work in the contract were inflated in order to compensate for the nominal bid on the fill. Significantly, the total contract price was lower than the engineer's estimate for the cost of the project but not so inordinately low as to forebode default in performance.
Furthermore, the engineer's testimony dispels any inference that his estimate of 8,078 cubic feet was to any extent out of line with the quantity which would reasonably be required to comply with the work specifications. In fact, the physical reality of the determinable length and depth of the pipe in a practical sense dictated the requisite quantity of the fill.
In light of such a factual complex we are confronted with the question whether the submission of a "penny" or nominal bid, per se, for an item which is relatively minor in comparison with the total contract price of over $300,000, renders the lowest bid invalid. In our opinion, a nominal bid under such circumstances is not inherently evil or destructive of fair and competitive bidding. But see the concurring opinion of Judge Conford in Armaniaco v. Cresskill, supra. And in the absence of other factors which might undermine the salutary principles of fair and competitive bidding espoused in the leading case of Hillside Tp. v. Sternin, 25 N.J. 317 (1957), we conceive of no reason why *47
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
380 A.2d 1161, 154 N.J. Super. 42, Counsel Stack Legal Research, https://law.counselstack.com/opinion/riverland-const-co-v-lombardo-contracting-co-njsuperctappdiv-1977.