R.W. Dunteman Co. v. Village of Lombard

666 N.E.2d 762, 281 Ill. App. 3d 929, 217 Ill. Dec. 93, 1996 Ill. App. LEXIS 375
CourtAppellate Court of Illinois
DecidedMay 24, 1996
Docket2-95-0328
StatusPublished
Cited by8 cases

This text of 666 N.E.2d 762 (R.W. Dunteman Co. v. Village of Lombard) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.W. Dunteman Co. v. Village of Lombard, 666 N.E.2d 762, 281 Ill. App. 3d 929, 217 Ill. Dec. 93, 1996 Ill. App. LEXIS 375 (Ill. Ct. App. 1996).

Opinion

JUSTICE RATHJE

delivered the opinion of the court:

Defendant, the Village of Lombard (Village), appeals from a judgment entered by the circuit court of Du Page County awarding $111,845 to plaintiff, R.W. Dunteman Co. (Dunteman). Dunteman cross-appeals from the denial of its request for prejudgment interest. We affirm in part and reverse in part and remand.

By way of background, the parties had entered into a construction contract, the terms of which provided that Dunteman would remove and replace a section of roadway located within the Village. A dispute arose as to whether certain work performed by Dunteman was to be compensated at the "pavement removal” rate provided in the contract or at the "special excavation” rate, which was the lower of the two rates. The engineer in charge of the work determined that the "special excavation” rate applied, which decision prompted the instant suit.

Dunteman filed a single-count complaint for declaratory judgment. After the Village answered the complaint, Dunteman moved for summary judgment. Judge S. Keith Lewis granted the motion and made the following findings:

"A. A valid and binding contract existed between the parties which is certain in its terms and unambiguous with respect to the work required by [Dunteman],
B. All work in the nature of — removing and disposing of all existing structures, base, and stabilized sub-base, including resurfaced pavement by this Declaratory Judgment order is classified as 'Pavement Removal’ and not 'Special Excavation.’
C. [Dunteman] performed certain work, in an undetermined quantity, in the nature of Pavement Removal and shall be paid according to the contract at the unit price set forth therein for that amount of material removal classified as 'Pavement Removal.’ ”

The order further provided that Dunteman was to submit a statement to the Village setting forth the quantity of material it removed that was classified as "pavement removal” under the terms of Judge Lewis’ order. The Village was to respond with any objection to the said quantity and the basis for the objection.

Dunteman then served upon the Village a request to admit facts. Dunteman also filed an amended complaint. Count I sought a declaratory judgment as to classification of the work performed. Count II alleged a breach of contract and sought damages based upon the Village’s failure to pay Dunteman for the removal of the "pavement structures.”

In its response to the request to admit facts, the Village admitted that Dunteman removed the entire surface area of the "Work Area.” The Village admitted that there may have been as much as 16,930 square yards of surface area. The Village further admitted that Dunteman removed pavement structures, base, and stabilized sub-base, including resurfaced pavement.

A bench trial was held before Judge Bonnie M. Wheaton. Following the trial, Judge Wheaton made the following findings: that the determination of the engineer as to the payment rate was not binding upon the parties; that the contract price for pavement removal was $10 per square yard; that 16,525 square yards of pavement were removed from the work area; and that Dunteman was entitled to be paid for the removal of the specified surface area, that being 16,525 square yards, at the rate of $10 per square yard.

After subtracting the amounts previously paid by the Village, judgment was entered for Dunteman in the amount of $111,845. Judge Wheaton denied Dunteman’s request for prejudgment interest.

This appeal and cross-appeal followed.

The Village contends, first, that Judge Wheaton erred in determining that the engineer’s decision as to the payment rate was not binding on the parties in this case. Dunteman responds that engineering decisions made pursuant to contract provisions similar to the one at issue in the present case are always subject to judicial review and scrutiny.

It is not disputed that article 105.01 of the Standard Specifications for Road and Bridge Construction, Illinois Department of Transportation, adopted July 1, 1988 (Standard Specifications), was incorporated into the contract at issue in the present case. Article 105.01 provides as follows:

"Authority of Engineer. All work shall be done under the supervision of the Engineer and to the Engineer’s satisfaction. The Engineer shall decide all questions which arise as to the quality and acceptability of materials furnished, work performed, manner of performance, rate of progress of the work, interpretation of the plans and Specifications, acceptable fulfillment of the contract, compensation, and disputes and mutual rights between Contractors under the Specifications. The Engineer shall determine the amount and quality of work performed and materials furnished. The Engineer’s decision shall be final and shall be a condition precedent to the right of the Contractor to receive money due the Contractor under the contract.” Standard Specifications, art. 105.01 (1988).

Illinois courts have consistently enforced similar contract provisions making decisions of the engineers or architects final on matters that were so intended by the parties to the contract. See Weld v. First National Bank, 255 Ill. 43 (1912); Arnold v. Bournique, 144 Ill. 132 (1893); Herlihy Mid-Continent Co. v. City of Chicago, 331 Ill. App. 78 (1947); Jobst v. City of Danville, 212 Ill. App. 571 (1918). However, Illinois courts do not recognize the engineer’s decision as binding in all circumstances. Rather, the engineer’s decisions or determinations are considered final and legally binding except where his actions or failure to act were fraudulent, collusive, unreasonable, made in bad faith, or contained evident mistake. See Mellon Stuart Construction, Inc. v. Metropolitan Water Reclamation District of Greater Chicago, No. 93 — C—6241 (N.D. Ill. April 21, 1995) (and the cases cited therein).

We believe that the record in this case demonstrates a clear mistake by the engineer when he determined that the "special excavation” rate and not the "pavement removal” rate applied to Dunteman’s removal work.

The contract at issue here provides that special excavation "shall be performed in accordance with the requirements of Section 205 of the Standard Specifications.” Section 205 provides in pertinent part as follows:

"205.01 Description. Special excavation shall consist of the removal of all existing structures defined herein; earth excavation and borrow excavation; the placement of all suitable excavated materials in the subgrade, or embankment, or as replacement.
* * *
205.02 Definition of Structures.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Marriage of Landgren
2022 IL App (2d) 210408-U (Appellate Court of Illinois, 2023)
In re Marriage of Mulligan-Ehrie
2022 IL App (1st) 210493-U (Appellate Court of Illinois, 2022)
Blitz Telecom Consulting, LLC v. Peerless Network, Inc.
212 F. Supp. 3d 1232 (M.D. Florida, 2016)
R. W. Dunteman Co. v. State
52 Ill. Ct. Cl. 33 (Court of Claims of Illinois, 1999)
Countryman v. Industrial Commission
686 N.E.2d 61 (Appellate Court of Illinois, 1997)
Countryman v. Industrial Comm'n
Appellate Court of Illinois, 1997

Cite This Page — Counsel Stack

Bluebook (online)
666 N.E.2d 762, 281 Ill. App. 3d 929, 217 Ill. Dec. 93, 1996 Ill. App. LEXIS 375, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rw-dunteman-co-v-village-of-lombard-illappct-1996.