Public Service Co. of New Hampshire v. Patch

87 F. Supp. 2d 57, 2000 U.S. Dist. LEXIS 2632, 2000 WL 263708
District Court, D. New Hampshire·Decided March 6, 2000·No. 97-97-JD, 97-121-L·Published·Cited by 1 cases

Opinion

DECISION AND ORDER

LAGUEUX, District Judge. *

This matter is the latest installment in the extensive litigation resulting from New Hampshire’s attempt to deregulate its electric utility industry. 1 However, for the reasons set forth below, the particular issue decided today is distinct from the many issues surrounding the implementation of that deregulation effort. Specifically, the question before the Court at present is whether Connecticut Valley Electric Company (“plaintiff’) is entitled to a permanent injunction mandating the New Hampshire Public Utility Commission (“defendant”) to pass through in plaintiffs retail rates the wholesale energy price paid by plaintiff to Central Vermont Public Service Corporation (“Central Vermont”) while plaintiff is purchasing power from Central Vermont pursuant to a federally-approved contract and tariff. This Court concludes that plaintiff is entitled to such relief and a permanent injunction shall issue.

I. Background

Plaintiff, a New Hampshire corporation, distributes and sells electric service to approximately 10,000 customers in western New Hampshire. Plaintiff purchases seventy-six percent (76%) of its power from its parent Central Vermont, a Vermont corporation, pursuant to an interstate cost-of-service-based wholesale requirements rate schedule (“RS-2 Rate Schedule”) approved by the Federal Energy Regulatory Commission (“FERC”). This purchasing arrangement has been in place since 1950 and some form of the RS-2 Rate Schedule has been in existence since 1982. The RS-2 Rate Schedule contains the following clause (“Section E”):

E. Termination Service under this rate schedule may be terminated at any time if both [Central Vermont] and [plaintiff] agree to the termination. If there is no agreement, service may be terminated at the end of a service year if the party seeking termination has given written notice of termination prior to the beginning of that service year.

As discussed below, the parties vigorously dispute the ramifications of this clause.

Plaintiff purchases the remainder of its power from other sources not relevant to the case at bar. Plaintiffs retail rates are set forth in a retail tariff which is subject to approval by defendant.

Approximately ninety percent (90%) of the power Central Vermont supplies to plaintiff is purchased from other sources, *59 pursuant to several long-term contracts. One of those contracts is with Hydro Quebec. That arrangement was made on a long-term basis in 1990 so that Central Vermont and plaintiff would have a firm and rehable source of power to service their customers. That arrangement and the rates to be paid were approved by FERC, the Vermont Public Service Board and defendant as it was then constituted.

At all times relevant to this matter (because of the passage of time and change of power supply circumstances) these long-term contract prices have exceeded wholesale electricity prices in New England. Because Central Vermont essentially passes these prices through to plaintiff under the RS-2 Rate Schedule, plaintiff has been buying power from Central Vermont at higher-than-market wholesale rates. 2

In 1996, with the purpose of reducing the state’s retail electric rates, the New Hampshire legislature adopted the Electric Utility Restructuring Act, N.H.Rev. StatAnn. §§ 374-F:l et seq. (1999) (“the Act”), providing for the introduction of competition into the New Hampshire electric utility industry. Pursuant to the power vested in it by this statute, defendant issued a restructuring plan (the “Final Plan”) and implementing orders on February 28, 1997. See Order No. 22,514; Order Nos. 22,509-22,513 (specific utilities’ interim stranded cost rulings). Familiarity with the Final Plan’s details is assumed as it is described at length in Patch I and Patch IV. See Patch, 962 F.Supp. at 226-228; Patch, 167 F.3d at 18-19. Of importance here is defendant’s February 28, 1997 order which denies plaintiff a stranded cost recovery charge for power purchased from Central Vermont to the extent that the cost of that power exceeds wholesale prices generally available in the New Hampshire market. See Order No. 22,509. (“Stranded Cost Recovery Order”). Defendant’s rationale for this determination was that plaintiff should, pursuant to Section E, terminate the RS-2 Rate Schedule and avail itself of current market prices, thus avoiding any stranded costs upon the implementation of restructuring. See id.

On March 3, 1997, Public Service Company of New Hampshire (“PSCNH”), the largest electric utility in New Hampshire, brought suit in this Court, seeking to enjoin implementation of the Final Plan on a number of federal constitutional grounds. This Court granted a temporary restraining order (“TRO”) against implementation of the Final Plan on March 10, 1997. On March 21, 1997, after an evidentiary hearing, this Court renewed the TRO and requested briefing on the issues of ripeness and abstention. In Patch I, issued April 28,1997, this Court rejected those grounds for dismissal of this case, rejected defendant’s claim that the Court lacked jurisdiction under the Johnson Act, 28 U.S.C. § 1342, and concluded that the TRO should remain in place until further order of the Court. See Patch, 962 F.Supp. at 244.

In Patch II, issued June 12, 1997, this Court allowed several other New Hampshire electric utilities to intervene in the litigation as of right. See Patch, 173 F.R.D. at 28. Shortly thereafter, on June 18, 1997, plaintiff and Central Vermont were permitted to intervene.

Free access — add to your briefcase to read the full text and ask questions with AI

Public Service Co. of New Hampshire v. Patch, 87 F. Supp. 2d 57, 2000 U.S. Dist. LEXIS 2632, 2000 WL 263708 (D.N.H. 2000).

87 F. Supp. 2d 57 (Public Service Co. of New Hampshire v. Patch) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Public Service Co. v. Patch
221 F.3d 198 (First Circuit, 2000)