Public Service Co. v. Patch

221 F.3d 198, 2000 U.S. App. LEXIS 17967, 2000 WL 992247
CourtCourt of Appeals for the First Circuit
DecidedJuly 25, 2000
Docket00-1460
StatusPublished
Cited by3 cases

This text of 221 F.3d 198 (Public Service Co. v. Patch) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Public Service Co. v. Patch, 221 F.3d 198, 2000 U.S. App. LEXIS 17967, 2000 WL 992247 (1st Cir. 2000).

Opinion

BOUDIN, Circuit Judge.

This appeal is the latest installment in a series growing out of New Hampshire’s efforts to deregulate the electric utility industry and trim rates for customers. 1 Familiarity with our prior decisions is assumed. We repeat here only those facts pertinent to the present issue.

Connecticut Valley Electric Company (“Connecticut Valley”), a small New Hampshire utility, provides retail electric service to about 10,000 customers in New Hampshire. Connecticut Valley purchases about 76 percent of its power from its parent company, Central Vermont Public Service Corporation (“Central Vermont”), a Vermont utility, under a wholesale requirements contract (“the RS-2 contract”) that incorporates cost-of-service rates (“the RS-2 rate schedule”) filed with and regulated by the Federal Energy Regulatory Commission (“FERC”). Connecticut Valley and Central Vermont have had a requirements contract incorporating some form of the RS-2 rate schedule since 1982.

The RS-2 contract has a termination clause that, read literally, permits either party to terminate the contract at the end of a service year by giving written notice of termination before the beginning of that service year. See Patch V, 167 F.3d at 32. Connecticut Valley and Central Vermont contend that the termination clause was not intended to give either of them the ability to terminate unilaterally on such short notice, but the district court found it unnecessary to decide whether the one-year termination clause allows Connecticut Valley to terminate on the specified notice if and when its own interests so dictate.

*200 Central Vermont’s rates under the RS-2 contract with Connecticut Valley are higher than the current rates for wholesale electricity available elsewhere in New Hampshire, due in part to an expensive long-term contract by which Central Vermont purchases from Hydro Quebec. In February 1997, as part of its restructuring of electricity regulation in New Hampshire, the New Hampshire Public Utilities Commission (“the Commission”) found that Connecticut Valley should have given notice of termination of its RS-2 contract on or before December 31,1996. This finding was made in computing the so-called “stranded cost recovery charge” that Connecticut Valley would otherwise be allowed to recover from customers as part of the deregulation process. Re Connecticut Valley Elec. Co., Order No. 22,509 (Feb. 28, 1997) (the “Stranded Cost Recovery Order”). 2

Concerned that Connecticut" Valley would terminate the RS-2 contract and thereby leave Central Vermont alone with a long-term obligation to buy expensive power from Hydro Quebec, Central Vermont in June 1997 filed with FERC its own proposal to terminate the RS-2 contract. However, it made termination contingent on FERC allowing Central Vermont to add a “stranded cost surcharge” on power delivered over its transmission lines to customers in Connecticut Valley’s service area. FERC rejected that proposal as inconsistent with earlier FERC orders and regulations, but decided to allow Central Vermont to file a different plan that would impose an exit fee on Connecticut Valley at the contract’s termination, and thus ensure that Connecticut Valley shared in the loss to Central Vermont that would result from termination of the contract. See Central Vt. Pub. Serv. Corp., 81 F.E.R.C. ¶ 61,386, at 62,543 (1997), aff'd, 214 F.3d 1366 (D.C.Cir.2000).

In December 1997, Central Vermont notified FERC that it would seek a tariff amendment to establish an exit fee (to recover its own stranded costs). The recovery of stranded costs at the wholesale level is the subject of extensive FERC regulation, recently sustained in almost all respects by the D.C. Circuit in Transmission Access Policy Study Group v. FERC, 225 F.3d 667, 699-700 (D.C.Cir.2000). FERC accepted the proposed exit fee provision for filing in March 1998. See Central Vt. Pub. Serv. Corp., 82 F.E.R.C. ¶ 61,237, at 61,908 (1998). A hearing has now been held before an administrative law judge at FERC, but no decision on either the propriety or the amount of the fee has yet been issued.

In late December 1997, as the state’s restructuring proceedings continued, Connecticut Valley applied for a routine increase in its 1998 retail rates to incorporate increases in Central Vermont’s RS-2 rate schedule. Such adjustments to the RS-2 schedule are made periodically by Central Vermont to reflect changes in its cost of acquiring power, and, in the past, the Commission has allowed them to be passed through by Connecticut Valley to its own customers. FERC accepted Central Vermont’s increased RS-2 rates for filing on January 13, 1998. This time, instead of approving the requested increase, the state commission found Connecticut Valley imprudent for not terminating the RS-2 contract sooner because power was available for less money on the open market, and it disallowed the requested increase. Connecticut Valley Elec. Co., Order No. 22,815 (Dec. 31, 1997) (“the Disallowance Order”). This finding *201 paralleled the reasoning behind its Stranded Cost Recovery Order.

In the same period, litigation concerning New Hampshire’s plan for restructuring the electric utility industry was proceeding in this court and the district court. In December 1998, we upheld a preliminary injunction in which the district court prohibited the Commission from implementing its broad deregulation plan. Patch IV, 167 F.3d at 28-29. However, in a companion decision, Patch V, we vacated the injunction to the extent it required the Commission to allow Connecticut Valley to recover through its retail rates the full cost of wholesale power purchased under the RS-2 contract. 167 F.3d at 36. We found that Connecticut Valley had not shown a likelihood that the Disallowance Order was enjoinable by a federal court under the restrictive terms of the Johnson Act, 28 U.S.C. § 1342 (1994).

Our decision in Patch V permitted the Commission to roll back Connecticut Valley’s retail rates to the 1997 level. However, after that decision, the Commission ordered Connecticut Valley to reduce its rates temporarily below the 1997 level in order to refund to customers the higher rates they had paid while the district court’s preliminary injunction was in effect. Connecticut Valley Elec. Co., Order No. 23,168 (Mar. 22, 1999) (“the Refund Order”). Connecticut Valley and Central Vermont objected to the district court regarding this further reduction; the district court agreed; and on April 7, 1999, it enjoined the Commission from ordering the refund. The Commission again appealed to this court.

In Patch VI, decided on January 24, 2000, we found that the injunction against the Refund Order could not be sustained on the basis thus far supplied, but allowed the district court 90 days to provide a sufficient basis for such an injunction. 202 F.3d at 34-35. The district court then sought to supply that explanation and, at the same time, to dispose of the parties’ cross-motions for summary judgment as to the underlying dispute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Delmarva Power & Light Co. v. Morrison
496 F. Supp. 2d 678 (E.D. Virginia, 2007)
Pacific Gas & Electric Co. v. Lynch
216 F. Supp. 2d 1016 (N.D. California, 2002)
Farmland Industries, Inc. v. Kansas Corporation Comm'n
37 P.3d 640 (Court of Appeals of Kansas, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
221 F.3d 198, 2000 U.S. App. LEXIS 17967, 2000 WL 992247, Counsel Stack Legal Research, https://law.counselstack.com/opinion/public-service-co-v-patch-ca1-2000.