Progressive Bros. Construction Co. v. United States

35 Cont. Cas. Fed. 75,643, 16 Cl. Ct. 549, 1989 U.S. Claims LEXIS 57, 1989 WL 31907
CourtUnited States Court of Claims
DecidedApril 7, 1989
DocketNo. 50-88C
StatusPublished
Cited by7 cases

This text of 35 Cont. Cas. Fed. 75,643 (Progressive Bros. Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Progressive Bros. Construction Co. v. United States, 35 Cont. Cas. Fed. 75,643, 16 Cl. Ct. 549, 1989 U.S. Claims LEXIS 57, 1989 WL 31907 (cc 1989).

Opinion

OPINION

MARGOLIS, Judge.

This contract case is before the court on defendant’s motion for summary judgment. The defendant asserts that plaintiff signed a valid release of claims under the disputes clause of the contract and that this release bars any subsequent action against the government. Plaintiff contends that the release was signed under duress and requests the opportunity to prove that it did not intend to waive any claims by accepting a final progress payment. The court has determined that the plaintiff has failed to establish that a genuine issue of material fact exists, and that the defendant is entitled to judgment as a matter of law. Accordingly, the defendant’s motion for summary judgment is granted.

FACTS

The plaintiff, Progressive Brothers Construction Company, brings this claim against the United States Veterans Administration (VA), for damages under Contract No. V541C-426. The contract was for the construction of a warehouse addition at the VA Medical Center in Brecksville, Ohio. After work on the project was substantially complete, plaintiff, by letter dated November 14, 1986, submitted a claim to the contracting officer seeking an equitable adjustment in the contract price for work done outside the scope of work outlined in the contract due to alleged design defects, change orders and delays. The plaintiff, requested $16,629 in additional compensation. The contracting officer denied plaintiff’s claim in a final decision on January 23, 1987.

A proposed settlement agreement, signed by the contracting officer, was sent to the plaintiff on May 28, 1987. On June 1, 1987, the contracting officer sent to the plaintiff a statement for the fourteenth and final payment to be paid under the contract in the amount of $6,919. Along with the statement, the contracting officer sent a final settlement memorandum that contained a release of claims to be executed by the plaintiff and returned prior to the final payment. The release of claims provision provided:

For and in consideration of the payments heretofore made, and payment of the above recited sum now due by reason of performance of the above contract, the undersigned contractor hereby releases and discharges the United States of America of and from all liabilities, obligations and claims whatsoever under or arising out of said contract, except the following:
Specific Claims:

(Emphasis added). The release form thus provided a specific procedure for the preservation of claims outside the scope of a settlement.

On June 16, 1987, plaintiff wrote a letter to the contracting officer proposing to reduce the final payment from $6,919 to $5,919, and to leave a balance due of $1000 [551]*551“plus claims that have not been settled.” The contracting officer rejected plaintiff’s proposed changes by letter dated June 18, 1987. The June 18, 1987 letter stated:

By signing the settlement does not waive your right to file a claim in accordance with the Disputes Clause. This settlement may be signed, claims noted and the claim submitted as stated in the above clause. We cannot accept the changes you made.

(Emphasis added). The final payment statement and release form was executed by plaintiff, through its President, David L. Morrow, on August 3, 1987. On the release form, the plaintiff failed to specifically enumerate any claims. Following receipt of the final payment statement and the signed release of claims, payment of $6,919 was approved by the contracting officer and made to the plaintiff.

On January 22, 1988, plaintiff commenced this action under the Contract Disputes Act, 41 U.S.C. § 601 et seq., appealing the contracting officer’s denial of its claim on January 23, 1987, and seeking damages of at least $10,000. Defendant asserts that the release form executed by the plaintiff on August 3, 1987 insulates the defendant from any contractual liability. The execution of a general release, defendant argues, bars the plaintiff from asserting claims against the government arising out of the contract because no claims were specifically excepted or preserved on the release form as required. Defendant contends that no genuine issue of material fact exists, and therefore, its motion for summary judgment should be granted.

Plaintiff asserts that there is a genuine issue of material fact concerning its intent to waive future claims when it signed the release document on August 3, 1987. Plaintiff argues that David L. Morrow, plaintiff’s President, signed the release under economic duress resulting from statements made in the letter dated June 18, 1987 and conversations with the contracting officer, and that plaintiff had “no intention to waive any disputes that existed between Progressive Brothers, Inc. and the Veterans Administration.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cygnus Corp. v. United States
63 Fed. Cl. 150 (Federal Claims, 2004)
W & F Building Maintenance Co. v. United States
56 Fed. Cl. 62 (Federal Claims, 2003)
Metric Constructors, Inc. v. United States
44 Fed. Cl. 513 (Federal Claims, 1999)
Safeco Credit & Fraley Associates, Inc. v. United States
44 Fed. Cl. 406 (Federal Claims, 1999)
Ed. Zueblin, A.G. v. United States
44 Fed. Cl. 228 (Federal Claims, 1999)
Coastal Industries, Inc. v. United States
39 Cont. Cas. Fed. 76,722 (Federal Claims, 1994)
McLain Plumbing & Electrical Service, Inc. v. United States
39 Cont. Cas. Fed. 76,593 (Federal Claims, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
35 Cont. Cas. Fed. 75,643, 16 Cl. Ct. 549, 1989 U.S. Claims LEXIS 57, 1989 WL 31907, Counsel Stack Legal Research, https://law.counselstack.com/opinion/progressive-bros-construction-co-v-united-states-cc-1989.