The Selmer Company v. Blakeslee-Midwest Company, Westinghouse Electric Corporation, and Federal Insurance Company

704 F.2d 924, 1983 U.S. App. LEXIS 29284
CourtCourt of Appeals for the Seventh Circuit
DecidedMarch 29, 1983
Docket82-2493
StatusPublished
Cited by22 cases

This text of 704 F.2d 924 (The Selmer Company v. Blakeslee-Midwest Company, Westinghouse Electric Corporation, and Federal Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Selmer Company v. Blakeslee-Midwest Company, Westinghouse Electric Corporation, and Federal Insurance Company, 704 F.2d 924, 1983 U.S. App. LEXIS 29284 (7th Cir. 1983).

Opinion

POSNER, Circuit Judge.

This appeal by the plaintiff from summary judgment for the defendants in a diversity case requires us to consider the meaning, under Wisconsin contract law, of “economic duress” as a defense to a settlement of a contract dispute.

On this appeal, we must take as true the following facts. The plaintiff, Selmer, agreed to act as a subcontractor on a construction project for which the defendant Blakeslee-Midwest Prestressed Concrete Company was the general contractor. Under the contract between Blakeslee-Midwest and Selmer, Selmer was to receive $210,000 for erecting prestressed concrete materials supplied to it by Blakeslee-Midwest. Blakeslee-Midwest failed to fulfill its contractual obligations; among other things, it was tardy in supplying Selmer with the prestressed concrete materials. Selmer could have terminated the contract without penalty but instead agreed orally with Blakeslee-Midwest to complete its work, provided Blakeslee-Midwest would pay Selmer for the extra costs of completion due to Blakeslee-Midwest’s defaults. When the job was completed, Selmer demanded payment of $120,000. BlakesleeMidwest offered $67,000 and refused to budge from this offer. Selmer, because it was in desperate financial straits, accepted the offer.

Two and a half years later Selmer brought this suit against Blakeslee-Midwest (the other defendants’ liability, being derivative from Blakeslee-Midwest’s, does not require separate consideration), claiming that its extra costs had amounted to $150,-000 ($120,000 being merely a settlement offer), and asking for that amount minus the $67,000 it had received, plus consequential and punitive damages. Although Selmer, presumably in order to be able to claim such damages, describes this as a tort rather than a contract action, it seems really to be a suit on Blakeslee-Midwest’s alleged oral promise to reimburse Selmer in full for the extra costs of completing the original contract after Blakeslee-Midwest defaulted. But the characterization is unimportant. Selmer concedes that, whatever its suit is, it is barred by the settlement agreement if, as the district court held, that agreement is valid. The only question is whether there is a triable issue as to whether the settlement agreement is invalid because procured by “economic duress.”

If you extract a promise by means of a threat, the promise is unenforceable. This is not, as so often stated, see, e.g., Totem Marine Tug & Barge, Inc. v. Alyeska Pipeline Serv. Co., 584 P.2d 15, 22 (Alaska 1978), because such a promise is involun *927 tary, unless “involuntary” is a conclusion rather than the description of a mental state. If the threat is ferocious (“your money or your life”) and believed, the victim may be desperately eager to fend it off with a promise. Such promises are made unenforceable in order to discourage threats by making them less profitable. The fundamental issue in a duress case is therefore not the victim’s state of mind but whether the statement that induced the promise is the kind of offer to deal that we want to discourage, and hence that we call a “threat.” Selmer argues that BlakesleeMidwest said to it in effect, “give up $53,-000 of your claim for extras [$120,000 minus $67,000], or you will get nothing.” This has the verbal form of a threat but is easily recast as a promise innocuous on its face— “I promise to pay you $67,000 for a release of your claim.” There is a practical argument against treating such a statement as a threat: it will make an inference of duress inescapable in any negotiation where one party makes an offer from which it refuses to budge, for the other party will always be able to argue that he settled only because there was a (figurative) gun at his head. It would not matter whether the party refusing to budge was the payor like Blakeslee-Midwest or the promisor like Selmer. If Selmer had refused to complete the job without being paid exorbitantly for the extras and Blakeslee-Midwest had complied with this demand because financial catastrophe would have loomed if Selmer had walked' off the job, we would have the same case. A vast number of contract settlements would be subject to being ripped open upon an allegation of duress if Selmer’s argument were accepted.

Sensitive — maybe oversensitive — to this danger, the older cases held that a threat not to honor a contract could not be considered duress. See, e.g., Sistrom v. Anderson, 51 Cal.App.2d 213, 124 P.2d 372, 376 (Cal.App.1942); cf. Batavian Bank v. North, 114 Wis. 637, 645-46, 90 N.W. 1016, 1019 (1902). But the principle was not absolute, as is shown by Alaska Packers’ Ass’n v. Domenico, 117 Fed. 99 (9th Cir.1902). Sailors and fishermen (the libelants) “agreed in writing, for a certain stated compensation, to render their services to the appellant in remote waters where the season for conducting fishing operations is extremely short, and in which enterprise the appellant had a large amount of money invested; and, after having entered upon the discharge of their contract, and at a time when it was impossible for the appellant to secure other men in their places, the libel-ants, without any valid cause, absolutely refused to continue the services they were under contract to perform unless the appellant would consent to pay them more money.” Id. at 102. The appellant agreed, but later reneged, and the libelants sued. They lost; the court refused to enforce the new agreement. Although the technical ground of decision was the absence of fresh consideration for the modified agreement, it seems apparent both from the quoted language and from a reference on the same page to coercion that the court’s underlying concern was that the modified agreement had been procured by duress in the form of the threat to break the original contract. Cf. Farnsworth, Contracts 271 (1982).

Alaska Packers’ Ass’n shows that because the legal remedies for breach of contract are not always adequate, a refusal to honor a contract may force the other party to the contract to surrender his rights — in Alaska Packers’ Ass’n, the appellant’s right to the libelants’ labor at the agreed wage. It undermines the institution of contract to allow a contract party to use the threat of breach to get the contract modified in his favor not because anything has happened to require modification in the mutual interest of the parties but simply because the other party, unless he knuckles under to the threat, will incur costs for which he will have no adequate legal remedy. If contractual protections are illusory, people will be reluctant to make contracts. Allowing contract modifications. to be voided in circumstances such as those in Alaska Packers’ Ass’n assures prospective contract parties that signing a contract is not stepping into a trap, and by thus encouraging people to make contracts promotes the efficient allocation of resources.

*928 Capps v. Georgia Pac. Corp., 253 Or. 248, 453 P.2d 935 (1969), illustrates the principle of Alaska Packers’ Ass’n in the context of settling contract disputes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rochester Ford Sales, Inc. v. Ford Motor Co.
287 F.3d 32 (First Circuit, 2002)
Resolution Trust Corp. v. Ruggiero
977 F.2d 309 (Seventh Circuit, 1992)
Resolution Trust Corporation v. Angelo Ruggiero
977 F.2d 309 (Seventh Circuit, 1992)
R.S. & V. Co. v. Atlas Van Lines, Inc.
917 F.2d 348 (Seventh Circuit, 1990)
Progressive Bros. Construction Co. v. United States
35 Cont. Cas. Fed. 75,643 (Court of Claims, 1989)
Wisconsin Knife Works v. National Metal Crafters
781 F.2d 1280 (Seventh Circuit, 1986)
Pope v. Ziegler
377 N.W.2d 201 (Court of Appeals of Wisconsin, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
704 F.2d 924, 1983 U.S. App. LEXIS 29284, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-selmer-company-v-blakeslee-midwest-company-westinghouse-electric-ca7-1983.