PG&E Corporation v. AECOM Technical Services, Inc..

District Court, N.D. California·Decided June 28, 2021·No. 4:20-cv-05381·Unknown

Opinion

1 2 3 6 7 JH KELLY, LLC, Case No. 20-cv-05381-HSG 8 Plaintiff, ORDER GRANTING MOTION TO DISMISS IN PART AECOM'S FIRST 9 v. AMENDED COUNTERCLAIM 10 AECOM TECHNICAL SERVICES, INC.., Re: Dkt. No. 48 et al., 11 Defendants. 12 13 Pending before the Court is PG&E’s motion to dismiss certain claims in AECOM’s First 14 Amended Counterclaim. Dkt. No. 48 (“Mot.”). AECOM has filed an opposition, Dkt. No. 60 15 (“Opp.”), and PG&E has filed a reply, Dkt. No. 63 (“Reply”). The Court finds this matter 16 appropriate for disposition without oral argument and the matter is deemed submitted. See Civil 17 L.R. 7-1(b). For the following reasons, the Court GRANTS the motion to dismiss with LEAVE 18 TO AMEND as to AECOM’s claims for negligent misrepresentation, fraudulent concealment, 19 quantum meruit, implied contractual indemnity, and contribution/apportionment. 21 This construction dispute arises out of the Burney K2 Replacement Project (“Project”), 22 which involved the replacement of a natural gas compressor unit and various upgrades at the 23 compressor station near Burnley, California. Dkt. No. 38 (AECOM’s First Amended 24 Counterclaim or “Countercl.”) ¶ 7. The Burney Compressor Station is part of PG&E’s natural gas 25 distribution system that supplies natural gas to the surrounding area and allows compressed gas to 26 continue traveling through pipelines from Oregon to consumers in California. Id. ¶ 8. PG&E’s 27 natural gas distribution system provides service to around 4.2 million customers from Bakersfield, 1 PG&E and AECOM entered into an Engineering, Procurement and Construction of 2 Natural Gas & Electric Transmission Facilities Agreement (the “EPC Agreement”). Id. ¶ 9. 3 AECOM then entered into a subcontract (the “Subcontract”) with JH Kelly, which is also a party 4 to this complex construction dispute. Id. Under the EPC Agreement, AECOM agreed to design 5 and construct the Project and to procure certain materials and equipment. Id. ¶ 10. Under the 6 Subcontract, AECOM assigned its construction obligations to JH Kelly, and JH Kelly agreed to 7 construct the Project, to supply certain materials, and be responsible for construction planning and 8 scheduling. Id. 9 The current case involves disputes between PG&E, AECOM, and JH Kelly over who is 10 responsible for various alleged delays, cost overruns, contractual violations, and tortious actions. 11 The current motion to dismiss addresses the non-contract claims in AECOM’s Counterclaim. 12 Mot. at 9. 14 Federal Rule of Civil Procedure 8(a) requires that a complaint contain “a short and plain 15 statement of the claim showing that the pleader is entitled to relief.” Fed. R. Civ. P. 8(a)(2). A 16 defendant may move to dismiss a complaint for failing to state a claim upon which relief can be 17 granted under Rule 12(b)(6). “Dismissal under Rule 12(b)(6) is appropriate only where the 18 complaint lacks a cognizable legal theory or sufficient facts to support a cognizable legal theory.” 19 Mendiondo v. Centinela Hosp. Med. Ctr., 521 F.3d 1097, 1104 (9th Cir. 2008). To survive a Rule 20 12(b)(6) motion, a plaintiff need only plead “enough facts to state a claim to relief that is plausible 21 on its face.” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007). A claim is facially plausible 22 when a plaintiff pleads “factual content that allows the court to draw the reasonable inference that 23 the defendant is liable for the misconduct alleged.” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009). 24 Rule 9(b) imposes a heightened pleading standard where fraud is an essential element of a 25 claim. See Fed. R. Civ. P. 9(b) (“In alleging fraud or mistake, a party must state with particularity 26 the circumstances constituting fraud or mistake.”); see also Vess v. Ciba–Geigy Corp. USA, 317 27 F.3d 1097, 1107 (9th Cir. 2003). A plaintiff must identify “the who, what, when, where, and how” 1 the charge. Cooper v. Pickett, 137 F.3d 616, 627 (9th Cir. 1997). 2 In reviewing the plausibility of a complaint, courts “accept factual allegations in the 3 complaint as true and construe the pleadings in the light most favorable to the nonmoving party.” 4 Manzarek v. St. Paul Fire & Marine Ins. Co., 519 F.3d 1025, 1031 (9th Cir. 2008). Nevertheless, 5 courts do not “accept as true allegations that are merely conclusory, unwarranted deductions of 6 fact, or unreasonable inferences.” In re Gilead Scis. Secs. Litig., 536 F.3d 1049, 1055 (9th Cir. 7 2008) (quoting Sprewell v. Golden State Warriors, 266 F.3d 979, 988 (9th Cir. 2001)). 8 If the court concludes that a 12(b)(6) motion should be granted, the “court should grant 9 leave to amend even if no request to amend the pleading was made, unless it determines that the 10 pleading could not possibly be cured by the allegation of other facts.” Lopez v. Smith, 203 F.3d 11 1122, 1127 (9th Cir. 2000) (en banc) (quotation omitted). 13 AECOM’s Counterclaim alleges sixteen causes of action, including contractual and tort 14 claims against both PG&E and JH Kelly. PG&E moves to dismiss AECOM’s non-contractual 15 claims against PG&E, specifically AECOM’s claims for Negligent Misrepresentation (5th), 16 Fraudulent Concealment (6th), Quantum Meruit (7th), Implied Contractual Indemnity (8th), and 17 Contribution/Apportionment (16th).1 Mot. at 9. 18 A. AECOM’s Negligent Misrepresentation and Fraudulent Concealment Claims 19 The basis for AECOM’s negligent misrepresentation and fraudulent concealment claims 20 are representations allegedly made by PG&E in the Burney project’s request for proposal (“RFP”). 21 Specifically, AECOM alleges that “[i]n the RFP, PG&E represented that: (a) it would only make 22 minimum changes to the existing pre-bid design, (b) the pre-bid design was accurate, (c) the 23 allowable means and methods for the construction of the Project were as described in the RFP, and 24 (d) the scope of the Project and the scope of the design would be frozen at the 30% (pre-bid) stage 25

26 1 The parties stipulate to the dismissal of AECOM’s claim for determination of priority and extent of AECOM’s mechanics’ lien against PG&E based on this Court’s prior ruling on JH Kelly’s 27 claim for foreclosure of mechanics’ lien. Mot. at 10; Opp. at 2; Dkt. No. 56. Given this 1 and any changes thereafter would entitle AECOM to a schedule extension and/or increase in 2 contact price.” Countercl. ¶¶ 119, 128. According to AECOM, PG&E knew, or should have 3 known, that these representations contained in the RFP were false. Id. ¶¶ 121, 130. 4 Under California law, AECOM’s negligent misrepresentation and fraudulent concealment 5 claims sound in fraud. See Daniels v. Select Portfolio Servicing, Inc., 246 Cal. App. 4th 1150, 6 1166 (Cal. Ct. App. 2016) (“Causes of action for intentional and negligent misrepresentation 7 sound in fraud and, therefore, each element must be pleaded with specificity.”).

Free access — add to your briefcase to read the full text and ask questions with AI

PG&E Corporation v. AECOM Technical Services, Inc.., (N.D. Cal. 2021).

PG&E Corporation v. AECOM Technical Services, Inc.. (PG&E Corporation v. AECOM Technical Services, Inc..) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Melder v. Morris
27 F.3d 1097 (Fifth Circuit, 1994)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Iragorri v. International Elevator, Inc.
203 F.3d 8 (First Circuit, 2000)
Manzarek v. St. Paul Fire & Marine Insurance
519 F.3d 1025 (Ninth Circuit, 2008)
Mendiondo v. Centinela Hospital Medical Center
521 F.3d 1097 (Ninth Circuit, 2008)
In Re Gilead Sciences Securities Litigation
536 F.3d 1049 (Ninth Circuit, 2008)
C. Norman Peterson Co. v. Container Corp. of America
172 Cal. App. 3d 628 (California Court of Appeal, 1985)
Sehulster Tunnels/Pre-Con v. Traylor Brothers, Inc./Obayashi Corp.
4 Cal. Rptr. 3d 655 (California Court of Appeal, 2003)
Ben-Zvi v. Edmar Co.
40 Cal. App. 4th 468 (California Court of Appeal, 1995)
Amelco Electric v. City of Thousand Oaks
38 P.3d 1120 (California Supreme Court, 2002)
Robinson Helicopter Co., Inc. v. Dana Corp.
102 P.3d 268 (California Supreme Court, 2004)
Daniels v. Select Portfolio Servicing, Inc.
246 Cal. App. 4th 1150 (California Court of Appeal, 2016)
Karim Khoja v. Orexigen Therapeutics, Inc.
899 F.3d 988 (Ninth Circuit, 2018)
Prince v. Pacific Gas & Electric Co.
202 P.3d 1115 (California Supreme Court, 2009)
Cooper v. Pickett
137 F.3d 616 (Ninth Circuit, 1997)
Sprewell v. Golden State Warriors
266 F.3d 979 (Ninth Circuit, 2001)
JMP Securities LLP V. Altair Nanotechnologies Inc.
880 F. Supp. 2d 1029 (N.D. California, 2012)