PG&E Corporation v. AECOM Technical Services, Inc..

District Court, N.D. California·Decided May 20, 2022·No. 4:20-cv-05381·Unknown

Opinion

1 2 3 6 7 JH KELLY, LLC, Case No. 20-cv-05381-HSG

8 Plaintiff, ORDER GRANTING IN PART AND DENYING IN PART AECOM’S 9 v. MOTION FOR SUMMARY JUDGMENT Re: Dkt. No. 205 11 Defendant.

12 13 Before the Court is Defendant and Counter-Claimant AECOM Technical Services, Inc.’s 14 (“AECOM”) motion for partial summary judgment against JH Kelly LLC (“JH Kelly”). Dkt. No. 15 205 (“Mot.”). The motion is fully briefed. See Dkt. Nos. 225 (“Opp.”) and 227 (“Reply”). The 16 Court finds this matter appropriate for disposition without oral argument and the matter is deemed 17 submitted. See Civil L.R. 7-1(b). For the following reasons, the motion is GRANTED IN PART 18 and DENIED IN PART. 20 This construction dispute arises out of the Burney K2 Replacement Project (“Project”), 21 which involved the replacement of a natural gas compressor unit and various upgrades at a 22 compressor station near Burney, California. Dkt. No. 102 (JH Kelly’s Second Amended 23 Complaint or “SAC”) ¶ 1. The Burney Compressor Station is part of Pacific Gas & Electric 24 Company’s (“PG&E”) natural gas distribution system. Id. ¶ 11. That system supplies natural gas 25 to the surrounding area and allows compressed gas to travel through pipelines from Oregon to 26 consumers in California. Id. In all, PG&E’s natural gas distribution system provides service to 27 around 4.2 million customers from Bakersfield, California to the Oregon border. Id. 1 PG&E for the Project. Id. ¶ 19. Under the EPC Agreement, AECOM agreed to act as the design- 2 builder and prime contractor for the Project. Id. On October 21, 2016, AECOM and Kelly 3 entered into an agreement (the “Subcontract”) for the construction portion of the work. Id. ¶¶ 25- 4 27. 5 Various issues on the Project led to disputes between JH Kelly, AECOM and PG&E. 6 Relevant here, JH Kelly contends that the Project was changed from what it bid and agreed to 7 perform, and that these changes imposed significant additional work and more difficult working 8 conditions. See Dkt. No. 162. JH Kelly also asserts that AECOM repeatedly ignored the 9 Subcontract’s change-order requirements to pay JH Kelly for the changed work. Id. AECOM 10 denies each of those claims and counterclaims that JH Kelly breached the Subcontract. Id. 11 JH Kelly filed the First Amended Complaint in January 2021. Dkt. No. 18. AECOM and 12 PG&E reached a settlement in October 2021 and ultimately agreed to dismiss their claims against 13 one another with prejudice. See Dkt. Nos. 93, 127. JH Kelly then filed the operative complaint, 14 which AECOM moved to dismiss in part. Dkt. No. 102. AECOM’s motion was granted in part 15 and denied in part. Dkt. No. 179. AECOM now moves for partial summary judgment. 17 Summary judgment is proper when a “movant shows that there is no genuine dispute as to 18 any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). 19 A fact is “material” if it “might affect the outcome of the suit under the governing law.” Anderson 20 v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). And a dispute is “genuine” if there is evidence 21 in the record sufficient for a reasonable trier of fact to decide in favor of the nonmoving party. Id. 22 The Court views the inferences reasonably drawn from the materials in the record in the light most 23 favorable to the nonmoving party, Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 24 574, 587–88 (1986), and “may not weigh the evidence or make credibility determinations,” 25 Freeman v. Arpaio, 125 F.3d 732, 735 (9th Cir. 1997), overruled on other grounds by Shakur v. 26 Schriro, 514 F.3d 878, 884–85 (9th Cir. 2008). 27 The moving party bears both the ultimate burden of persuasion and the initial burden of 1 genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986). Where the 2 moving party will not bear the burden of proof on an issue at trial, it “must either produce 3 evidence negating an essential element of the nonmoving party's claim or defense or show that the 4 nonmoving party does not have enough evidence of an essential element to carry its ultimate 5 burden of persuasion at trial.” Nissan Fire & Marine Ins. Co. v. Fritz Cos., 210 F.3d 1099, 1102 6 (9th Cir. 2000). Where the moving party will bear the burden of proof on an issue at trial, it must 7 also show that no reasonable trier of fact could not find in its favor. Celotex Corp., 477 U.S. at 8 325. In either case, the movant “may not require the nonmoving party to produce evidence 9 supporting its claim or defense simply by saying that the nonmoving party has no such evidence.” 10 Nissan Fire & Marine Ins. Co., 210 F.3d at 1105. “If a moving party fails to carry its initial 11 burden of production, the nonmoving party has no obligation to produce anything, even if the 12 nonmoving party would have the ultimate burden of persuasion at trial.” Id. at 1102–03. 13 “If, however, a moving party carries its burden of production, the nonmoving party must 14 produce evidence to support its claim or defense.” Id. at 1103. In doing so, the nonmoving party 15 “must do more than simply show that there is some metaphysical doubt as to the material facts.” 16 Matsushita Elec. Indus. Co., 475 U.S. at 586. A nonmoving party must also “identify with 17 reasonable particularity the evidence that precludes summary judgment.” Keenan v. Allan, 91 18 F.3d 1275, 1279 (9th Cir. 1996). If a nonmoving party fails to produce evidence that supports its 19 claim or defense, courts enter summary judgment in favor of the movant. Celotex Corp., 477 U.S. 20 at 323. 22 AECOM contends that it is entitled to partial summary judgment on three different 23 components of JH Kelly’s damages claim. It first argues that JH Kelly’s consequential damages— 24 consisting of loss of financing, lost profits, costs paid to third party experts, and costs for 25 preparing claims against AECOM—are barred as a matter of law because the parties’ Subcontract 26 includes an express waiver of consequential damages. Mot. at 1. It then argues that JH Kelly also 27 waived any right to recover the bulk of its costs for labor performed and materials furnished 1 “total cost” method for quantifying its delay and disruption damages because JH Kelly cannot 2 satisfy the required four-factor test for a total cost claim. Id. 3 A. JH Kelly’s Consequential Damages 4 The contract between JH Kelly and AECOM contains the following provision: 5 6 13.7 CONSEQUENTIAL DAMAGES. 7 13.7.1 NOTWITHSTANDING ANYTHING HEREIN TO THE CONTRARY, NEITHER DESIGN- BUILDER NOR SUBCONTRACTOR SHALL BE LIABLE TO THE OTHER FOR ANY 8 WARRANTY, TORT (INCLUDING. NEGLIGENCE), STRICT LIABILITY OR OTHERWISE INCLUDING BUT NOT LIMITED TO LOSSES OF USE, PROFITS, BUSINESS, REPUTATION 10 || Dkt. No. 205-1, Declaration of Marion T. Hack in support of AECOM’s Motion for Partial 11 Summary Judgment (“Hack Decl.”), Ex. 2 (“Subcontract”) § 13.7.1. Under that provision, JH 12 || Kelly unambiguously waived any claims it may have for “consequential losses or damages.” Jd. 13 Broadly speaking, AECOM contends that this waiver bars several categories of JH Kelly’s 14 || damages claims, and JH Kelly argues that its respective claims are not “consequential” damages. 15 When one party breaches a contract, the injured party is generally entitled to damages that 16 || would put it in as good a position as it would have occupied if the breach had not occurred. Lewis 3 17 || Jorge Constr. Memt., Inc. v. Pomona Unified Sch. Dist., 34 Cal.

Free access — add to your briefcase to read the full text and ask questions with AI

PG&E Corporation v. AECOM Technical Services, Inc.., (N.D. Cal. 2022).

PG&E Corporation v. AECOM Technical Services, Inc.. (PG&E Corporation v. AECOM Technical Services, Inc..) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
First American Bank v. J.S.C. Concrete Construction, Inc.
523 S.E.2d 496 (Supreme Court of Virginia, 2000)
Addicks Services, Inc. v. GGP-BRIDGELAND, LP
596 F.3d 286 (Fifth Circuit, 2010)
Shakur v. Schriro
514 F.3d 878 (Ninth Circuit, 2008)
Pacific Coast Engineering Co. v. St. Paul Fire & Marine Insurance
9 Cal. App. 3d 270 (California Court of Appeal, 1970)
People v. Cogar
202 Cal. App. 2d 509 (California Court of Appeal, 1962)
Newton v. Clemons
1 Cal. Rptr. 3d 90 (California Court of Appeal, 2003)
Realmuto v. Gagnard
1 Cal. Rptr. 3d 569 (California Court of Appeal, 2003)
Tesco Controls, Inc. v. Monterey Mechanical Co.
21 Cal. Rptr. 3d 751 (California Court of Appeal, 2004)
Dillingham-Ray Wilson v. City of Los Angeles
182 Cal. App. 4th 1396 (California Court of Appeal, 2010)
Halbert's Lumber, Inc. v. Lucky Stores, Inc.
6 Cal. App. 4th 1233 (California Court of Appeal, 1992)
Amelco Electric v. City of Thousand Oaks
38 P.3d 1120 (California Supreme Court, 2002)
Freeman v. Arpaio
125 F.3d 732 (Ninth Circuit, 1997)