Pestka v. County of Blue Earth

654 N.W.2d 153, 2002 Minn. App. LEXIS 1385, 2002 WL 31819072
CourtCourt of Appeals of Minnesota
DecidedDecember 17, 2002
DocketC3-02-566
StatusPublished

This text of 654 N.W.2d 153 (Pestka v. County of Blue Earth) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pestka v. County of Blue Earth, 654 N.W.2d 153, 2002 Minn. App. LEXIS 1385, 2002 WL 31819072 (Mich. Ct. App. 2002).

Opinion

OPINION

HUDSON, Judge.

This is the second appeal to this court arising from the petition for a drainage improvement to County Ditch # 86, Branch 1, in Blue Earth County. On appeal from summary judgment, appellants argue that the district court (a) erred in ruling that Minn.Stat. § 103E.5I1 (2002) gives the drainage authority the ability to approve a corrected report of the viewers; (b) should have ruled that Minn.Stat. §§ 103E.341 and 103E.505 (2002) preclude the drainage authority from awarding a contract for a drainage project unless it is known that the project’s benefits exceed its cost; and (c) should have included in the cost of the project the amounts paid to avoid a challenge to the project by others. We affirm.

FACTS

On September 23, 1997, the Blue Earth County Board of Commissioners (county board), acting as the drainage authority, approved a proposed drainage improvement to County Ditch # 86, Branch 1, in *155 Blue Earth County. 1 As required by statute, the county board found that the estimated benefits were greater than the total estimated costs, including damages. See Minn.Stat. § 103E.341 (2002). 2 At the time of the hearing, the viewers 3 determined the benefits to be $339,819 and the estimated costs of the improvement, including damages, to be $315,932, causing the estimated benefits to-exceed the sum of the estimated damages and the costs by $23,886.

No appeal was taken from the order establishing the drainage improvement project. On October 28, 1997, however, appellants Wayne Pestka and Blaine Phillips (Pestka and Phillips), along with several other affected landowners, filed a benefits-and-damages appeal, contesting the amount of benefits and damages that would accrue to their lands under the drainage improvement project. At the January 11, 1999, jury trial of the consolidated appeals, the viewers indicated that they had misapplied a capitalization formula to arrive at the determination of benefits, and that their report to the county board had consequently understated the benefits that they believed accrued to the land. Nonetheless, the jury issued verdicts reducing the amount of benefits and increasing the amount of damages to most of the subject properties,‘resulting in the cost of the drainage improvement project exceeding the benefits.

In apparent anticipation that the viewers would file an amended report, on April 12, 1999, Pestka and Phillips filed a petition with the drainage authority for (1) nonap-proval and denial of an amended viewers’ report, on the basis that the viewers had made erroneous assumptions as to benefits and (2) dismissal of the proceedings on the basis that the costs, including damages, would exceed the benefits of the project. On April 30, 1999, the viewers did, in fact, file an amended viewers’ report, reporting increased benefits to the affected land based on the adjustment to the capitalization factor. Benefits under the amended report were set at $324,168.

As a result of a posttrial settlement between the parties, the district court issued amended findings of fact, order, and judgment in the first benefits appeal, incorporating many of the verdict amounts and making minor modifications to the precise area of certain lands to be reclaimed. On May 25, 1999, the project engineers then filed a revised amended final report with some project engineering changes incorporating certain changes agreed to by the parties in the posttrial settlement. Two days later, the county received new bids for the project. The lowest bid came from Krengel Brothers Construction, Inc.

On June 7, 1999, another affected landowner, Merrill Hoppe (Hoppe), who had not joined in the original proceeding, petitioned the county board to refer the initial viewers’ and engineer’s reports back to the viewers and the engineer for amendment to conform to the reports. The petition stated that because of excessive litigation costs, it appeared that unless the viewers’ *156 and engineer’s reports were amended, the improvement project could not be constructed because the costs would be in excess of the reported benefits. On August 9, 1999, the county board found that with the corrections or modifications proposed in the petition, a contract could be awarded for construction of the project and ordered that the engineer and the viewers amend their initial reports to conform to Hoppe’s petition. As amended, the reports were adopted; the benefits were determined to be $824,186, and the cost of construction plus damages found to be $313,577.

As a result of this order, Pestka and Phillips appealed a second time to the district court, challenging the benefits and damages determinations on lands affected by the order. Because their benefits had been determined in their first appeal, Pest-ka and Phillips’ benefits were unchanged by this order. Included in the new appeal was land owned by Duane Truebenbach and other affected landowners. Pestka and Phillips also filed a complaint in district court requesting a temporary injunction and a declaratory judgment that the county board had exceeded its authority in approving the amended viewers’ report, and that the sum of $12,000, which had been paid into the trust account of an attorney for the county in order to secure the promise of Duane Truebenbach not to appeal the benefits and damages determination, be considered additional costs of the project. While these actions were pending, the county board issued an order on October 19, 1999, awarding the construction contract to Krengel Brothers Construction, Inc.

The district court dismissed the second benefits-and-damages appeal as well as the declaratory judgment/injunction action, noting that it had become moot as a result of the dismissal of the benefits-and-damages appeal. Pestka and Phillips then appealed to this court, which concluded that they lacked standing to appeal because there was no “injury in fact” to them. In re Improvement of County Ditch No. 86 v. Phillips, 614 N.W.2d 756, 763 (Minn.App.2000) (Ph illips I). On appeal, the Minnesota Supreme Court reversed, holding that appellants, who would be directly affected by the proposed project, had standing pursuant to Minn.Stat. § 103E.091 to appeal the benefits and damages determinations, even when they were not appealing those determinations as to their own land. In re Improvement of County Ditch No. 86 v. Phillips, 625 N.W.2d 813, 814 (Minn.2001) (Phillips II). The supreme court also held that the appellants’ declaratory judgment and injunctive actions could proceed. Id. at 821. During the pendency of this litigation, the drainage improvement was constructed. On February 27, 2001, the county board accepted the drainage project and approved final payment to the contractor.

On remand, the district court granted summary judgment for Pestka and Phillips as to the county board’s jurisdictional challenge.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brookfield Trade Center, Inc. v. County of Ramsey
584 N.W.2d 390 (Supreme Court of Minnesota, 1998)
Titrud v. Achterkirch
213 N.W.2d 408 (Supreme Court of Minnesota, 1973)
Improvement of County Ditch No. 86, Branch 1 v. Phillips
625 N.W.2d 813 (Supreme Court of Minnesota, 2001)
In Re the Establishment of County Ditch No. 11 (Bevens Creek)
511 N.W.2d 54 (Court of Appeals of Minnesota, 1994)
In Re Improvement of Murray County Ditch No. 34
615 N.W.2d 40 (Supreme Court of Minnesota, 2000)
In Re Improvement of County Ditch No. 11, Martin County
91 N.W.2d 657 (Supreme Court of Minnesota, 1958)
In Re Lateral 2-A of Judicial Ditch No. 36
185 N.W.2d 701 (Supreme Court of Minnesota, 1971)
State Ex Rel. Cooper v. French
460 N.W.2d 2 (Supreme Court of Minnesota, 1990)
Improvement of County Ditch No. 86, Branch 1, County of Blue Earth v. Phillips
614 N.W.2d 756 (Court of Appeals of Minnesota, 2000)
Maxwell v. County of Freeborn
386 N.W.2d 358 (Court of Appeals of Minnesota, 1986)
Wold v. Bankers Surety Co.
157 N.W. 998 (Supreme Court of Minnesota, 1916)
Bauer v. Redwood County
185 N.W.2d 701 (Supreme Court of Minnesota, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
654 N.W.2d 153, 2002 Minn. App. LEXIS 1385, 2002 WL 31819072, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pestka-v-county-of-blue-earth-minnctapp-2002.