Minnesota Center for Environmental Advocacy v. Big Stone County Board of Commissioners

638 N.W.2d 198, 2002 Minn. App. LEXIS 76, 2002 WL 47021
CourtCourt of Appeals of Minnesota
DecidedJanuary 15, 2002
DocketC7-01-1161
StatusPublished
Cited by4 cases

This text of 638 N.W.2d 198 (Minnesota Center for Environmental Advocacy v. Big Stone County Board of Commissioners) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Minnesota Center for Environmental Advocacy v. Big Stone County Board of Commissioners, 638 N.W.2d 198, 2002 Minn. App. LEXIS 76, 2002 WL 47021 (Mich. Ct. App. 2002).

Opinion

OPINION

STONEBURNER, Judge.

Respondents Minnesota Center for Environmental Advocacy, the Coalition for a Clean Minnesota River and the New Ulm Area Sportfishermen sought a declaratory judgment that a proposed repair to Big Stone County Ditch No. 2/2A (County Ditch 2) requires (1) permission of the Commissioner of the Department of Natural Resources (DNR) pursuant to Minn. Stat. § 103E.011, subd. 3; (2) a public waters work permit from the DNR pursuant to Minn.Stat. § 103G.245; (3) an Environmental Impact Statement (EIS); and (4) a wetland-replacement plan approved pursuant to Minn.Stat. §§ 103G.222 and 103G.2242.

The district court granted partial summary judgment to respondents, declaring that the project requires a public waters work permit and permission from the Commissioner of the DNR. After trial, the district court concluded that the project does not require an EIS but does require either an approved wetland-replacement plan or an exemption from the requirement by the appropriate government agency. The district court also concluded that the Environmental Assessment Worksheet (EAW) used by appellants was fatally flawed, and ordered a new EAW and review before the project could proceed.

Appellants, the drainage authority for Big Stone County, appeal the district court’s determination that the EAW is fatally flawed and that the project requires a work permit, permission from the commissioner, and a wetland-replacement plan. Respondents seek review of the district court’s determination that the project does not require an EIS. Because we conclude that the project requires either permission from the commissioner or a public waters work permit, requires an approved wetland-replacement plan or exemption from the appropriate agency, and is subject to a mandatory EIS, we affirm in part and reverse in part.

FACTS

County Ditch 2 was built in 1907 through a pre-existing natural watercourse to drain adjacent areas for agricultural use. County Ditch 2 passes through DNR-protected wetland 6-11W. Wetland 6-11W is an approximately 60-acre public water, Type-5 wetland, defined as

[ijnland open fresh water, shallow ponds, and reservoirs in which water is usually less than ten feet deep and * * * fringed by a border of emergent vegetation similar to open areas of type 4 wetland.

Minn. Stat. § 103G.005, subd. 17b (5) (2000). Bottom elevations in wetland 6-11W range from 1005.7 to 1007.5 feet above sea level.

In 1915, landowners petitioned appellants to widen and enlarge the ditch. The width of the ditch as it currently exists is consistent with the 1915 “as-improved” width. The depth of the portion of County Ditch 2 located below wetland 6-11W was 1004.48 feet, mean sea level, “as improved” in 1915, but accumulated sediment has raised bottom elevations. In 1994, landowners petitioned appellants to comprehensively repair County Ditch 2, including *201 removal of sediment from the ditch below wetland 6-11W to reestablish the as-improved 1915 depth. The district court found that this work would constitute a “repair” as defined by Minn.Stat. § 103E.701 (2000).

In response to the 1994 petition, appellants commissioned a report from Sioux Engineering on the impact of the project. The report indicated that removing sediment from the ditch below wetland 6-11W would affect water levels in the wetland, triggering environmental review. Sioux Engineering recommended that appellants install a weir to eliminate any effect on the wetland, and the additional expense of environmental review. The weir solution is acceptable to respondents and the DNR but not to appellants. Appellants proceeded in 1995 and 1996 with major repairs to County Ditch 2, but did not remove sediment downstream of wetland 6-11W.

In July 1998, appellants received a new petition for removal of the sediment downstream of wetland 6-11W. Initially, appellants unanimously approved a resolution finding that “the repair * * * does not have the potential for significant environmental effects” and that an EIS was not required. Appellants rescinded this resolution on advice of counsel and retained Sioux Engineering to prepare an EAW to identify whether there would be significant environmental effects from the project and to allow for public comment and a hearing. 1

The EAW incorrectly identifies wetland 6-11W as a Type-3 wetland consisting of 20 acres. Type-3 wetlands are defined as “inland shallow fresh marshes in which soil is usually waterlogged early during a growing season and often covered with as much as six inches or more of water.” Minn.Stat. § 103G.005, subd. 17b (3). The EAW summary states:

The main issue considering wetland 6-11W and Big Stone County Ditch No. 2 is the impact of a repair of ditch 2 to original constructed depth and the current water level in 6-11W. Past records indicate that water depths in wetland 6-11W were adequate to maintain type 3 conditions with the ditch in a reasonable state of repair. Current data indicates that with the repair of Ditch No. 2 water depths may not support the same wetlands type.

It is undisputed that the project will transform wetland 6-11W from a Type-5 protected wetland to an unprotected Type-2 wetland, defined as

[ijnland fresh meadows in which soil is usually without standing water during most of the growing season but is waterlogged within at least a few inches of the surface.

Minn.Stat. § 103G.005, subd. 17b(2).

Appellants received comments based on the flawed EAW, and a response to the comments from the county engineer. The Minnesota Board of Water and Soil Resources 2 commented that a replacement plan for the loss of wetlands would be required. The board noted that, pursuant to Minn. R. 8420.0210 (1999), a Technical Evaluation Panel (TEP) and local government unit would be responsible for determining if appellant is exempt from the *202 replacement plan requirement. A TEP was convened and issued a report that stated that a “mitigation or replacement plan would certainly be needed if plans were made to lower the control point of Protected Waters Wetland 6-11W.”

After a public hearing, appellants concluded that the cumulative potential effects of the project “would not be so significant as to warrant an EIS.” Appellants assert that the project is exempt from the requirement of a wetland-replacement plan but have not sought an exemption from the local government unit.

Respondents brought this declaratory judgment action. The district court granted partial summary judgment declaring that appellants are required to obtain permission from the commissioner of the DNR to undertake this project because it substantially affects public waters, and that appellants are required to have a public waters work permit. After trial, the district court concluded that appellants are also required to have an approved wetland-replacement plan or exemption from the requirement by the appropriate government agency but are not required to have an EIS.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pestka v. County of Blue Earth
654 N.W.2d 153 (Court of Appeals of Minnesota, 2002)
In Re Silicone Implant Insurance Coverage Litigation
652 N.W.2d 46 (Court of Appeals of Minnesota, 2002)
McKissic v. BOR-SON CONSTRUCTION
638 N.W.2d 198 (Supreme Court of Minnesota, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
638 N.W.2d 198, 2002 Minn. App. LEXIS 76, 2002 WL 47021, Counsel Stack Legal Research, https://law.counselstack.com/opinion/minnesota-center-for-environmental-advocacy-v-big-stone-county-board-of-minnctapp-2002.