United States v. Sargent County Water Resource District

876 F. Supp. 1090, 40 ERC (BNA) 1718, 1994 U.S. Dist. LEXIS 19745, 1994 WL 757863
CourtDistrict Court, D. North Dakota
DecidedDecember 30, 1994
DocketCiv. A3-88-175
StatusPublished
Cited by6 cases

This text of 876 F. Supp. 1090 (United States v. Sargent County Water Resource District) is published on Counsel Stack Legal Research, covering District Court, D. North Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Sargent County Water Resource District, 876 F. Supp. 1090, 40 ERC (BNA) 1718, 1994 U.S. Dist. LEXIS 19745, 1994 WL 757863 (D.N.D. 1994).

Opinion

*1091 MEMORANDUM AND ORDER

WEBB, Chief Judge.

This is a dispute between the United States of America and the Sargent County Water Resource District (hereinafter “County”) over work the County did on a drainage ditch that bisects three sloughs. The federal government brought this action seeking in-junctive relief and civil penalties for violations of the Clean Water Act (“Act”), 33 U.S.C. §§ 1251-1376. The objective of the Act is “to restore and maintain the chemical, physical, and biological integrity of the Nation’s water.” 33 U.S.C. § 1251(a). The Act prohibits the discharge of dredged or fill materials into “navigable waters” — defined as “waters of the United States” — unless authorized by a permit issued by the Army Corps of Engineers (hereinafter “Corps”) pursuant to 33 U.S.C. § 1344. See generally, 33 U.S.C. § 1311, 1344. Limited exemptions from the permit requirement are found in § 1344(f), which provides in pertinent part:

(f) Non-prohibited discharge of dredged or fill material
(1) Except as provided in paragraph (2) of this subsection, the discharge of dredged or'fill material—
(C) for the purpose of construction or maintenance of farm or stock ponds or irrigation ditches, or the maintenance of drainage ditches;
is not prohibited by or otherwise subject to regulation under this section....
(2) Any discharge of dredged or fill material into the navigable waters incidental to any activity having as its primary purpose bringing an area of the navigable waters into a use to which it was not previously subject, where the flow or circulation of navigable waters may be impaired or the *1092 reach of such waters be reduced, shall be required to have a permit under this section.

33 U.S.C. § 1344(f). The United States of America argues the work the County directed required a permit under 33 U.S.C. § 1344, while the County argues that the work was exempt as maintenance under 33 U.S.C. § 1344(f).

This court previously ruled it had jurisdiction to hear the case. A bench trial on the issue of liability concluded on November 16, 1994, and this order follows.

FACTS

Sargent County is located in southeastern North Dakota. The southern boundary borders South Dakota and the eastern boundary is relatively close to Minnesota. Bruns Slough is the northern-most of the three sloughs and is bisected by North Dakota Highway 13, which provides easy access. Meszaros Slough, the southern-most slough, is also easily accessed due to its proximity to North Dakota Highway 11 and a well maintained county road.

In 1917, Sargent County began construction of Sargent County Drain 11, the drainage ditch here in question. This drainage ditch is about twenty-five miles long and cuts through Bruns, Big, and Meszaros Sloughs, respectively, before draining into the Wild Rice River near Brampton, North Dakota. The ditch was originally constructed to provide an out-fall for surface runoff for a large portion of the western part of Sargent County. Completed in the early 1920’s, the drainage ditch was successful as Bruns, Big, and Meszaros Sloughs were entirely drained as a result of the work.

The recorded history of the drainage ditch is extensive. Mr. Samuel Denton designed the ditch and oversaw portions of its original construction. Denton was replaced by W.B. Stevenson, who conducted the first survey of the drainage ditch bottom in 1919, prior to its completion. The 1919 survey was referred to throughout trial as the “as built” profile even though the survey did not account for the last seven miles of the ditch which was not built at the time Stevenson did his survey, and it did not account for any improvements that were subsequently made based on Stevenson’s recommendation after he completed his survey. A true “as built” survey was never found. The next known survey of the ditch occurred in 1969 when the United States Bureau of Reclamation conducted a survey as part of the Garrison Diversion Project. This is known as the “USBR-1969” survey. In 1990, after the work here at issue had been completed, a final survey was conducted at the request of the government by Resource Consultants, Inc., and is known as the “RCI-1990” survey.

In the early 1980’s, Moore Engineering, Inc. (hereinafter “Moore”), was retained by the County and charged with developing a profile of the bottom of the drainage ditch as it existed upon its completion in the early 1920’s. The original design drawings, the 1919 “as built” survey, and the “USBR-1969” survey were all used by Moore to complete this work. Mr. Jeffry Volk, the project engineer with Moore who oversaw the development of the profile, testified that although the County explored different alternatives, including improving the drain, it concluded that the best option was a clean-out of the drain. The cost of improving the drain would have been prohibitive and could not be justified. Volk also testified to some of the problems he encountered in reviewing Den-ton’s design with Stevenson’s “as built” survey and recommendations to arrive at an accurate “as built” profile. Denton and Stevenson started their work at different locations, with different base elevations, so many of their profile drawing lines did not match up. Volk recalled an instance where there was a three and one-half to four foot grade elevation difference between one sheet and another. Another problem was that Stevenson recommended various improvements to the drain based on the 1919 “as built” survey, but because no survey was conducted at the conclusion of all the original work, Volk was not entirely sure of the drain’s actual as built profile. Nonetheless, based primarily on information taken from Denton’s design drawings, Stevenson’s 1919 “as built” survey, and the “USBR-1969” survey, Volk developed a profile of the drainage ditch bottom as it *1093 existed at the completion of the work in the 1920’s.

Concerned about the cost of the clean-out of the ditch, the County sought to obtain financial assistance from the state. The state provides funds for new construction, but not for maintenance. The state considered the work to be performed on the drainage ditch to be strictly maintenance, and therefore, would not assist the County in funding the project. The project proceeded without state funding.

Once Moore.had completed its profile of the drainage ditch, the County contracted with Radniecki Construction Co. (hereinafter “Radniecki”) to perform the clean-out.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peconic Baykeeper, Inc. v. Suffolk County
585 F. Supp. 2d 377 (E.D. New York, 2008)
Greenfield Mills Inc v. Macklin, Larry
361 F.3d 934 (Seventh Circuit, 2004)
Greenfield Mills, Incorporated v. Macklin
361 F.3d 934 (Seventh Circuit, 2004)
Greenfield Mills, Inc. v. O'BANNON
189 F. Supp. 2d 893 (N.D. Indiana, 2002)
Hentges v. Minnesota Board of Water & Soil Resources
638 N.W.2d 441 (Court of Appeals of Minnesota, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
876 F. Supp. 1090, 40 ERC (BNA) 1718, 1994 U.S. Dist. LEXIS 19745, 1994 WL 757863, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-sargent-county-water-resource-district-ndd-1994.