Maxwell v. County of Freeborn

386 N.W.2d 358, 1986 Minn. App. LEXIS 4296
CourtCourt of Appeals of Minnesota
DecidedMay 6, 1986
DocketNo. CX-85-1109
StatusPublished
Cited by1 cases

This text of 386 N.W.2d 358 (Maxwell v. County of Freeborn) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maxwell v. County of Freeborn, 386 N.W.2d 358, 1986 Minn. App. LEXIS 4296 (Mich. Ct. App. 1986).

Opinion

OPINION

FOLEY, Judge.

Freeborn County Board of Commissioners appeals from a May 7, 1985 judgment dismissing its petition for improvement of an existing drainage system under Minn. Stat. § 106.501 (1984). We affirm.

FACTS

Judicial Ditch No. 9 was originally established in 1923 and lies entirely in Freeborn County. The system is composed of a main tile line which empties into an open ditch; the open ditch then empties into a larger tile line which proceeds arpproximately two miles to the point of outlet into Pickerel Lake. Branches enter the main tile line and open ditch segments at various points along the length of the main tile/ditch line.

A petition for repair and improvement was originally filed on September 16, 1980 and later modified to a petition for improvement only based on the recommendations of the project engineer. Viewer’s reports were subsequently filed and numerous hearings were held. On July 19, 1983, the board approved the petition. Its order contemplated replacement of broken tile and installation of an auxiliary pumping system designed to outlet surplus waters into Upper Twin Lake, two miles upstream from Pickerel Lake. The proposed pumping station was to be located near the point where the open ditch enters the large main tile line. The purpose of the new pumping system would be to relieve pressure upon the existing large tile which has been in [360]*360place for approximately 60 years. Upper Twin Lake is not within the existing watershed of Judicial Ditch No. 9. When the water reaches a certain elevation as determined by the setting on the pump, the pump would operate to divert the surplus water to Upper Twin Lake. This surplus water would be pumped under a county road and then would be routed through a new lateral ditch called Branch A.

Following appeal by objecting landowners, the July 19, 1983 order was remanded by the district court when the viewer’s report failed to consider benefits paid by the landowners at the time the ditch was originally established. After remand, a new viewer’s report was issued which clarified procedures but made no significant engineering changes. On September 18, 1984, the board adopted the viewer’s report by resolution.

The landowners again appealed the decision, and a trial de novo was held. At trial, project engineer Harold Zenk testified that the drainage system was of “marginal” effectiveness when constructed in 1923 and that it was “essential to replace the entire system * * *.” Zenk explained that a number of alternatives were considered, including installation of a parallel tile, but that the estimated cost ($1 million) was not economically feasible.

Zenk agreed that Upper Twin Lake, the proposed outlet, was not part of the original watershed:

Q. So what they did in 1923 was to establish a watershed that drained everything into Pickerel Lake?
A. [Zenk] Yes.
>jc ⅜ ⅛ ⅝< ‡ ⅜
Q. So all the watershed as shown on that original map took all of that water north?
A. Yes.
Q. None was taken into Upper Twin Lake?
A. Not as the ditch was constructed.

Landowners testifying at the trial generally agreed that the current system was in need of modification, but disputed that improvement rather than repair was desirable.

The trial court found that initial filing of the petition was proper under Minn.Stat. § 106.501 (1984), but that the proposed improvement violated subdivision 3 of the statute. In dismissing the petition, the trial court found that the proposal:

[C]reates a new outlet and pumping station located approximately two miles upstream from the outlet into Pickerel Lake. The new outlet and pumping station will outlet water outside the watershed and into Upper Twin Lake. This is a violation of Minnesota Statutes 106.-501, Subd. 3. It also changes the watershed as established by the Order of 1923 which established this ditch.

ISSUE

Is the County’s proposal for a pumping station that mechanically redirects surplus water flow and forces it through a new lateral branch into an outlet beyond the original watershed that is two miles upstream from the existing outlet, an improvement as contemplated under Minn. Stat. § 106.501, subd. 3 (1984)?

ANALYSIS

We note from the outset that appeal is taken solely from the judgment; no post-trial motions were made. Accordingly, our review is limited to whether the evidence supports the trial court’s findings and whether the findings sustain the conclusions of law. Johnsrud v. Tri-State Sales, Inc., 353 N.W.2d 255, 257 (Minn.Ct.App.1984).

Drainage proceedings in Minnesota “are purely statutory and their validity depends upon a strict compliance with the provisions of the statute by which they are regulated or controlled.” In re County Ditch No. 11, Martin County, 253 Minn. 367, 370, 91 N.W.2d 657, 660 (1958).

“A statutory petition is a jurisdictional prerequisite to the authority of the court or county board to proceed in the matter of establishing a ditch.” In re Judicial Ditch [361]*361No. 12, 227 Minn. 482, 492, 36 N.W.2d 336, 341 (1949). Minn.Stat. ch. 106 details five distinct types of drainage proceedings, each commenced by petition and carried on in accordance with due process standards. In re County Ditch No. 1, Faribault County, 237 Minn. 358, 360-61, 55 N.W.2d 308, 310-11 (1952). The five proceedings are as follows:

[1] The original proceedings (§ 106.031, et seq.) for establishment of a drainage system, either by way of a county ditch, or by a judicial ditch where more than one county is involved; (2) a proceeding (§ 106.471) to repair an established drainage system * * *; (3) a proceeding (§ 106.501) for the improvement of an existing system; (4) a proceeding (§ 106.-511) to improve an outlet for an established ditch; and (5) a proceeding (§§ 106.521 and 106.531) to establish laterals to drainage systems already established under (1).

Id. at 361, 55 N.W.2d at 310-11.1 Each proceeding contains its own statutory prerequisites for obtaining jurisdiction. In re County Ditch No. 31 & Judicial Ditch No. 13, Faribault County, 244 Minn. 543, 552, 70 N.W.2d 853, 860 (1955).

Respondents assert that the proper petition for appellant’s contemplated action is found in Minn.Stat. § 106.031 which requires signatures representing a majority of affected land. The trial court rejected this argument, finding Minn.Stat. § 106.-501 the proper avenue for appellant’s proposal. We agree with the trial court. Minn.Stat. § 106.031 deals specifically with establishment of a drainage system, not modification thereof. As such, it is inapplicable to the facts before us.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pestka v. County of Blue Earth
654 N.W.2d 153 (Court of Appeals of Minnesota, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
386 N.W.2d 358, 1986 Minn. App. LEXIS 4296, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maxwell-v-county-of-freeborn-minnctapp-1986.