In Re Improvement of Murray County Ditch No. 34

615 N.W.2d 40, 2000 Minn. LEXIS 409, 2000 WL 1030344
CourtSupreme Court of Minnesota
DecidedJuly 27, 2000
DocketCX-98-2194
StatusPublished
Cited by11 cases

This text of 615 N.W.2d 40 (In Re Improvement of Murray County Ditch No. 34) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Improvement of Murray County Ditch No. 34, 615 N.W.2d 40, 2000 Minn. LEXIS 409, 2000 WL 1030344 (Mich. 2000).

Opinions

OPINION

STRINGER, Justice.

Murray County Ditch 34 was originally constructed between 1914 and 1916 and runs for several miles through Skandia and Ellsborough Townships in Murray County, Minnesota. Its condition has substantially deteriorated since its construction. On September 14, 1993, respondents filed a petition for improvement of the ditch with the county drainage authority, requesting an improvement to the buried main tile system. After conducting a cost-benefit analysis required by Minn.Stat. § 103E.341 (1998), the drainage authority concluded that the benefits of the project exceeded its costs and ordered the improvement. In its cost-benefit analysis the drainage authority applied Minn.Stat. § 103E.215, subd. 6 (1998), providing that where an existing ditch needs repair and a petition for improvement pertains to a “separable” portion of the ditch, the cost of the repair is assessed against all property benefited by the entire drainage system, but the cost of the improvement is assessed only to those properties benefited by the improvement. See Minn.Stat. § 103E.215, subd. 6. Objecting property owners appealed the order to the district court, arguing that the cost of the project exceeded its benefits and the drainage authority incorrectly applied the statute because the section of the ditch designated for improvement was not separable from the entirety of the ditch, and therefore the costs of the project were unlawfully assessed against them. The district court and the court of appeals affirmed the drainage authority’s order of improvement. On review here, we affirm.

Murray County Ditch 34 was constructed as a buried main tile system with 32 tile branches containing several miles of tile lines and approximately 600 feet of open ditch at the outlet. On September 14, 1993, respondents, the owners of land through which the ditch passes, filed a petition for the improvement1 of the ditch with the Murray County Board of Commissioners stating that “over 200 acres of prime farmland is still underwater,” and requesting authority to dig an open ditch replacing the buried main tile line “beginning [at] the main tile line and commencing to the outlet of the main tile line only.” The County Board, acting as the drainage authority,2 evaluated the petition3 pursuant to Minn.Stat. § 103E.215, subd. 4 (1998),4 and pursuant to Minn.Stat. [43]*43§ 103E.215, subd. 5 (1998), appointed Sioux Engineering, Inc. (Sioux) to determine the costs of the improvement and to make a recommendation as to whether the ditch should be improved by construction of the open ditch or merely repaired to its original capacity. Sioux reported: “it is our opinion that the only method of reestablishing the drainage system’s originally installed capacities is to replace the drain the in its entirety * * * * with the construction of an open ditch.” The report also stated:

The existing drainage system is in need of repair, and the Petition for Improvement is for a separable part of the existing drainage system, consisting of the main branch. In this plan, the main branch ⅜ * ⅜ will be eliminated as a result of the improvement, and therefore, will not need to be repaired.

The report thus concluded that the existing drainage tile should be improved by the construction of an open ditch and that the portion of the ditch needing improvement was separable from the remainder of the drainage system.

Sioux’s report also determined the total cost of the project, then broke the total into two components: the cost of repairing the ditch back to its original condition when construction was completed in 1916, and the cost of improving the efficiency of the ditch over and above its originally constructed capacity.5 The re-port estimated the cost of repairing6 the separable part of the ditch to its originally constructed condition as $290,279.01 and the total cost of the entire improvement project as $593,565.43. The difference between the two calculations of $303,286.42 was the additional cost of improving the ditch beyond its originally constructed capacity.

The drainage authority also appointed three “viewers” to perform other statutorily mandated duties relating to the ditch project. For example, if the drainage authority determines that the original assessment of benefits to landowners as a result of the ditch do not reflect reasonable present day values, the viewers must redetermine the benefits and report the present day benefits7 and damages8 of the ditch. See Minn.Stat. § 103E.351, subd. 1 (1998). The present day estimated benefits are referred to as “redetermination” benefits and pursuant to Minn.Stat. § 103E.351, subd. 3 (1998), redetermination benefits are to be used in place of the original benefits “in all subsequent proceedings relating to the drainage system.” Minn.Stat. § 103E.351, subd. 3.

The original assessment of benefits when the ditch was completed in 1916 was $49,942.75; the viewers’ report estimated the redetermination benefits as $458,584.03 “based upon a comparison of the conditions which will exist with the drainage system repairs to the depth, grades and [44]*44tile sizes as shown on the original plans with the conditions which would have. existed before the construction began.” Thus, $458,584.03 reflects the present day benefit of the ditch if repaired to an “as new” condition when constructed.

The viewers’ report also estimated the benefits of the portion of the project that represented an improvement over the ditch as originally constructed to be $508,766.72 “based upon a comparison of the conditions which would exist with the existing drainage systems in a reasonable state of repair and the conditions which will exist upon completion of the improvement.” The report concluded: “It is our opinion that the proposed improvement will replace a portion of the existing drainage system and that the costs of the improvement should be prorated between repair and improvement.”

The drainage authority determined that the petition satisfied the legal requirements of Minn.Stat. § 103E.341, subd. 2 (1998), requiring the benefits to exceed the costs as a condition of approving the project: “[t]he drainage authority shall establish, by order, a proposed drainage project if it determines that * * * the damages and benefits have been properly determined * * * [and] the estimated benefits are greater than the total estimated cost, including damages[J” Minn.Stat. § 103E.341, subd. 2. It must dismiss the petition if it determines that “the benefits of the proposed drainage project are less than the total cost, including damages awarded[.]” Minn.Stat. § 103E.341, subd. 1 (1998).

The drainage authority first applied section 103E.215, subd. 6, and determined that the estimated repair cost portion of the improvement should be assessed against all property owners benefited by the entire drainage system and the cost of improving the ditch beyond the repairs should be assessed only against the property benefited by the improvement.9

The drainage authority then determined that the estimated cost of repair of $290,279.01 was less than the redetermination benefits, $458,548.03, and the total cost of the improvement project of $593,565.43 was less than the sum of the redetermination benefits plus the benefit of improving the ditch by removing the tile and opening the ditch, estimated to total $967,314.75.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re the Estate of Jotham
722 N.W.2d 447 (Supreme Court of Minnesota, 2006)
Agra Resources Coop v. Freeborn County Board of Commissioners
682 N.W.2d 681 (Court of Appeals of Minnesota, 2004)
Pestka v. County of Blue Earth
654 N.W.2d 153 (Court of Appeals of Minnesota, 2002)
Jasper v. Commissioner of Public Safety
642 N.W.2d 435 (Supreme Court of Minnesota, 2002)
Zaluckyj v. Rice Creek Watershed District
639 N.W.2d 70 (Court of Appeals of Minnesota, 2002)
Swarthout v. Mutual Service Life Insurance Co.
632 N.W.2d 741 (Court of Appeals of Minnesota, 2001)
Improvement of County Ditch No. 86, Branch 1 v. Phillips
625 N.W.2d 813 (Supreme Court of Minnesota, 2001)
In Re Improvement of Murray County Ditch No. 34
615 N.W.2d 40 (Supreme Court of Minnesota, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
615 N.W.2d 40, 2000 Minn. LEXIS 409, 2000 WL 1030344, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-improvement-of-murray-county-ditch-no-34-minn-2000.