People's Counsel v. Public Service Commission

270 A.2d 105, 259 Md. 409
CourtCourt of Appeals of Maryland
DecidedOctober 30, 1970
Docket[No. 41, September Term, 1970.]
StatusPublished
Cited by8 cases

This text of 270 A.2d 105 (People's Counsel v. Public Service Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
People's Counsel v. Public Service Commission, 270 A.2d 105, 259 Md. 409 (Md. 1970).

Opinions

[411]*411Hammond, C. J.,

delivered the opinion of the Court. Barnes and McWilliams, JJ., dissent. Barnes, J., filed a dissenting opinion, in which McWilliams, J., concurred, at page 424 infra.

The Calvert Cliffs Nuclear Power Plant of Baltimore Gas and Electric Company (the Company) in Calvert County, Maryland, which recently has led to various differences of opinion, scientific and otherwise, is responsible for the question now before us for decision. The legislature of 1968 passed Ch. 493 of the Laws of that year, which is now codified as § 54A of Art. 78 of the Code. The statute became effective July 1, 1968, to provide in pertinent part that:

“No electric company may begin the construction in Maryland of a generating station or any overhead transmission line designed to carry a voltage in excess of 69,000 volts, or exercise the right of eminent domain in connection therewith, without having first obtained from the [Public Service] Commission a certificate of public convenience and necessity for the construction of the station or line.”

The Commission is directed to hold a public hearing on a request for a certificate in the area involved, together with the local governing bodies of the area. Final action is to be taken by the Commission only after due consideration of the recommendabions of the governing bodies, the present and future needs for service, “effect on system stability and reliability, economics, esthetics, historic sites, and, when applicable, the effect on air and water pollution.”

It is agreed that the statute is prospective in operation, Amereihn v. Kotras, 194 Md. 591, 601, and the question presented is whether the Company began construction of the generating station prior to July 1, 1968. After a hearing necessitated by a petition filed with it by the People’s Counsel asking the Commission to require the [412]*412Company to apply for the certificate required by § 54A, the Commission decided that construction had begun before July 1,1968, and therefore the Company did not need a certificate in order to complete the generating station at Calvert Cliffs. In the appeal to the Circuit Court for Anne Arundel County Judge Melvin, using a test of judicial review of a Commission order established by Code (1969 Repl. Vol.), Art. 78, § 97, Scope of Review, held that whether construction had begun before July 1, 1968, within the meaning of § 54A, was a mixed question of law and fact and that “this court is unable to say that the Commission’s decision * * * is ‘unsupported by substantial evidence on the record considered as a whole.’ ”

The appellants, the People’s Counsel, Anne Arundel County, individuals in the area involved, and the Chesapeake Environmental Protection Association, Inc. (its standing is not now challenged) contend that the question presented is solely one of law, rather than the mixed question of fact and law that Judge Melvin saw. The case was decided in the Circuit Court on the record before the Commission, and the evidence before the Commission was the testimony of an engineer of the Company and an employee of the supplier of the nuclear steam supply system and several exhibits, such as the Calvert County Code. There is no dispute as to the facts and we think that the question presented to us is, on the record before us, essentially one of law.

The Company produced testimony that (a) in December 1966 it agreed to buy from General Electric Company a $25,000,000 turbine generator (the testimony was that due to the long time required for manufacture and the “tremendous influx of orders to the turbine generator suppliers,” it was necessary to have a “lead time” of some six years to assure delivery when needed) ; (b) in May 1967 it signed a memorandum of understanding with Combustion Engineering, Inc. for construction of the proposed plant’s nuclear steam supply system (and thereafter made substantial progress payments from time to time); (c) about a week later the deed to the site was [413]*413delivered; (d) three days later the Company made a public announcement of its intent to construct a two-unit nuclear power plant at Calvert Cliffs; (e) immediately thereafter the Company caused to be drilled core borings in the earth of the proposed site to determine the composition and utility of the ground; (f) in June 1967 the Company ordered a second generator from Westinghouse Electric Company at a price of $25,000,000; (g) on July 31, 1967 the Company hired Bechtel Corporation (Bechtel) “to provide services for engineering and construction for the Calvert Cliffs nuclear power plant” (there is nothing in the record to show whether the hiring was in writing or oral, how definitive it was as to scope and time, or what specific services were covered) ; (h) in August 1967 certain seismological studies at the site were contracted for; (i) in December 1967 Bechtel prepared a bar chart showing excavation scheduled for June 1968, and in February 1968 a master flow chart that also estimated that excavation would begin in June 1968; (j) in January 1968 the Company sought and received from Calvert County a permit to “construct a metal shed” on land adjacent to the site (later also acquired by the Company) to use in testing condensor tubes; (k) later in January 1968 the Company filed with the Atomic Energy Commission (AEC) an application for a permit to construct the nuclear generating station (such a permit is required by the Atomic Energy Act of 1954, 42 U.S.C. § 2235, before construction of a nuclear facility can lawfully be begun;1 (1) lumber companies cut marketable [414]*414timber in February 1968; (m) in April 1968 C. J. Langenfelder & Sons, Inc. (Langenfelder) began clearing and grubbing operations; (n) on June 6, 1968 Langenfelder, pursuant to oral directions from Bechtel, confirmed by letter and later by a written contract to do grading and excavation, began to move earth in order to level the site to an elevation of Plus 1. From June 6 to June 30 Langenfelder moved 104,000 cubic yards of earth, the first of the same kind of an ultimate total of 1,850,000 cubic yards, labelled as “unclassified excavation” in both the contract between Bechtel (acting for the Company) and Langenfelder, and in Langenfelder’s invoice to the Company. The Company’s engineer described “unclassified excavation” in contrast to “structural excavation” (both being called for by the contract, as were other categories such as “compacted fill”) as “the more easily removed material,” calling for a lower price than “structural excavation” which was to be “the very deep, hard to remove material,” calling for a higher price.

The record shows that the following events took place after July 1, 1968. (1)' The Commission’s regulations effective both prior to and after July 1, 1968, required that major construction projects of a utility be reported to the Commission within one month following the beginning of such construction. On July 17, 1968 the Company submitted a report showing that the construction period for the Calvert Cliffs plant would be from June 1968 to December 1974. (2) On April 17, 1970 the Commission granted the Company a certificate of Public Convenience and Necessity for the transmission lines from the plant. (3) The Calvert County Building Code requires, subject to penalty for non-compliance, all persons “before erecting or constructing any building in Calvert County” to apply for a building permit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Offen v. County Council for Prince George's County
625 A.2d 424 (Court of Special Appeals of Maryland, 1993)
Prince George's County v. Sunrise Development Ltd. Partnership
623 A.2d 1296 (Court of Appeals of Maryland, 1993)
PG COUNTY v. Sunrise Dev.
623 A.2d 1296 (Court of Appeals of Maryland, 1993)
Steuart Petroleum Co. v. Board of County Commissioners
347 A.2d 854 (Court of Appeals of Maryland, 1975)
Pemberton v. Montgomery County
340 A.2d 240 (Court of Appeals of Maryland, 1975)
County Council v. District Land Corp.
337 A.2d 712 (Court of Appeals of Maryland, 1975)
Carey v. Baltimore County
278 A.2d 6 (Court of Appeals of Maryland, 1971)
People's Counsel v. Public Service Commission
270 A.2d 105 (Court of Appeals of Maryland, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
270 A.2d 105, 259 Md. 409, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peoples-counsel-v-public-service-commission-md-1970.