Arkansas Power & Light Co. v. Federal Power Commission

125 F.2d 982, 1942 U.S. App. LEXIS 4842
CourtCourt of Appeals for the Eighth Circuit
DecidedMarch 2, 1942
DocketNo. 12065
StatusPublished
Cited by5 cases

This text of 125 F.2d 982 (Arkansas Power & Light Co. v. Federal Power Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arkansas Power & Light Co. v. Federal Power Commission, 125 F.2d 982, 1942 U.S. App. LEXIS 4842 (8th Cir. 1942).

Opinion

THOMAS, Circuit Judge.

This is a proceeding under § 313(b) of the Federal Power Act, 49 Stat. 860, 16 U.S.C.A. § 825Z(b), to review two orders of the Federal Power Commission, one dated March 21, 1941, and the other one May 3, 1941, as amended May 27, 1941.

The petitioner, an Arkansas corporation engaged in generating, transporting, and selling electric power and energy, is the holder of a license issued by the Commission February 7, 1923, for the construction and operation of a hydroelectric project on the Ouachita river in Arkansas. The “project”, under the provisions of the [983]*983license, consisted of three “separable parts”, each part consisting of a dam and power house and the ultimate installation of hydroelectric units. Two dams had been completed and put in operation prior to the commencement of this proceeding. The original license provided that the third dam, known as the Blakely dam (the only one involved in this proceeding) should be begun on or before July 1, 1933, and completed on or before July 1, 1936. The license has twice been amended. The last amendment made on July 1, 1935, changed the commencement date for the Blakely development to December 31, 1936, and the completion date for the first installation to December 31, 1939.

The order of March 21, 1941, was entered upon an amended application by the petitioner filed November 14, 1939, for an order to postpone indefinitely the construction and completion of the Blakely development. The application was denied. The denial was based upon findings that the license requirements for construction had not been satisfied; that the licensee had not shown when, if ever, it proposed to construct or complete the Blakely development; and that it would be inconsistent with the public interest and contrary to the provisions of the Act to grant the request for indefinite postponement of the construction and completion of the Blakely development.

On April 17, 1941, the petitioner filed an application (1) for rehearing, (2) for further postponement of-the construction and completion of the Blakely development, and (3) for permission to construct'a steam electric plant. By its order of May 3, 1941, as amended by its order of May 27, 1941, the Commission (1) denied the application for rehearing, (2) terminated petitioner’s license effective September 1, 1941, and (3) dismissed the applications for further postponement and for permission to construct a steam electric plant.

In its brief in this court the petitioner contends that:

1. The order terminating the Blakely license is not supported by the evidence and is contrary to law, in that the record shows that (a) construction work on the project was commenced within the time prescribed; (,b) petitioner could not have proceeded further with construction work without violating the license until a definite plan was approved by the Commission; (c) by the Flood Control Act of 1938, 52 Stat. 1215, 33 U.S.C.A. § 701b et seq., Congress in effect ratified petitioner’s license; and (d) the Commission is barred by law and by equity from terminating the license.

2. The denial and dismissal of the application for the postponement of the time for construction was arbitrary, opposed to the public interest, and in disregard of the duty of the Commission.

3. Petitioner is the proper party to construct the Blakely development.

The first and important point for decision is whether the Commission was legally justified in terminating the license. If it were so justified, the complaint that the Commission erred in .refusing to grant an extension of the time for commencement and completion of the development is moot. Section 13 of the Federal Power Act, 16 U.S.C.A. § 806, among other provisions, reads:

“In case the licensee shall not commence actual construction of the project works, or of any specified part thereof, within the time prescribed in the license or as extended by the commission, then, after due notice given, the license shall, as to such project works or part thereof, be terminated upon written order of the commission.”

The question for consideration is whether the petitioner had commenced “actual construction of the project works, or any specified part thereof, within the time prescribed in the license” as extended, within the meaning of the statute. The contention of petitioner is that it had done so.

The Act furnishes its own glossary. Subsection (12) of section 3, 16 U.S.C.A. § 796(12), reads, “(12) ‘project works’ means the physical structures of a project” ; and subsection (11) of said section 3 reads :

“(11) ‘project’ means complete unit of improvement or development, consisting of a power house, all water conduits, all dams and appurtenant works and structures (including navigation structures) which are a part of said unit, and all storage, diverting, or forebay reservoirs directly connected therewith, the primary line or lines transmitting power therefrom to the point of junction with the distribution system or with the interconnected primary transmission system, all miscellaneous structures used and useful in connection with said unit or any part thereof, and all water-rights, rights-of-way, ditches, dams, reservoirs, lands, or interest in lands the [984]*984use and occupancy of which are necessary or appropriate in the maintenance and operation of such unit.”

The Commission found that “The applicant [petitioner] has performed certain preliminary work on the Blakely development incidental to initiation of actual construction as provided in the license but has not commenced construction of the Blakely development.” This is a fact the finding of which is committed to the Commission and not to the court. Section 313(b) of the Act, 16 U.S.C.A. § 8251(b), provides that upon review by the court, “The finding of the Commission as to the facts, if supported by substantial evidence, shall be conclusive.”

The amount and character of the work done is not in dispute.

C. S. Lynch, chief engineer and a director of the petitioner, testified upon the hearing:

“Q. You said you had spent something like $10,000 on clearing the dam site. Is that correct? A. About $10,000 on excavation and other stuff, and clearing and surveys, and on grading work on the proposed road to the site.

“Q. That is all included in the $10,000? A. Yes, sir.

“Q. Now what actual excavation work on the site itself has been carried on. A. We have excavated several thousand yards down there, probably 10,000 or 12,000 yards at the base of the dam.”

In answer to another question the witness testified, “We have made a thorough examination of the foundation conditions with necessary core drillings and exploration trenches. * * * We have cleared the site on both sides of the river. * * * We have arranged for the necessary roads. In addition we have laid out a railroad spur to the site and have excavated a small portion of the foundation. We have worked out arrangements with a large sawmill for transportation of material to the neighborhood of the dam site and thus avoided the necessity of building several miles of railroad.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Free v. Sample
324 F. Supp. 1362 (W.D. Arkansas, 1971)
People's Counsel v. Public Service Commission
270 A.2d 105 (Court of Appeals of Maryland, 1970)
Madole v. Johnson
241 F. Supp. 379 (W.D. Louisiana, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
125 F.2d 982, 1942 U.S. App. LEXIS 4842, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arkansas-power-light-co-v-federal-power-commission-ca8-1942.