Steuart Petroleum Co. v. Board of County Commissioners

347 A.2d 854, 276 Md. 435, 1975 Md. LEXIS 737
CourtCourt of Appeals of Maryland
DecidedDecember 3, 1975
Docket[No. 41, September Term, 1975.]
StatusPublished
Cited by30 cases

This text of 347 A.2d 854 (Steuart Petroleum Co. v. Board of County Commissioners) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steuart Petroleum Co. v. Board of County Commissioners, 347 A.2d 854, 276 Md. 435, 1975 Md. LEXIS 737 (Md. 1975).

Opinion

Singley, J.,

delivered the opinion of the Court.

Steuart Investment Company and Steuart Petroleum Company (collectively referred to in this opinion as Steuart) have respectively owned and operated an oil storage terminal at Piney Point in St. Mary’s County (the County) since 1949. 1 The terminal has the capability of storing 200,000,000 gallons of fuel cil which is off-loaded from tankers and delivered to customers in the District of Columbia, Maryland and Virginia principally either by pipeline or barge, primarily for use as boiler fuel. Some aviation fuel is also stored for the Department of Defense.

Steuart appealed to the Court of Special Appeals from an order and a decree entered against it by the Circuit Court for the County in a proceeding in which three different actions had been consolidated for trial. We granted certiorari in order that the matter might be considered by us prior to argument in the Court of Special Appeals.

In 1968, Steuart had announced and later deferred plans to build a topping plant at Piney Point. 2 On 25 October 1973, Steuart made a public announcement of its intention to go forward with the construction of a refinery which would occupy four and one-half acres of its 350-acre tract; would have a capability of producing 100,000 barrels of fuel oil per day, and would cost $160,000,000.00. On 1 November 1973, Steuart’s contractor applied for, and the County granted, building permit No. 6166 which authorized the construction of a steel and concrete “Warehouse and shop storage” building to cost $200,000.00. One day later, the same contractor applied for, and was granted, building permit No. 6173 which covered the construction of a “Foundation pad *438 for processing and utility area” at a cost of $800,000.00. Neither of the applications nor the single site plan, offered in support of both applications, made any allusion to the proposed refinery. The site plan indicated a foundation pad area of 780,000 square feet, but the application described the pad as occupying 78,000 square feet.

The county, on 7 November, revoked permit No. 6173 on the ground that Steuart, by failing to disclose the purpose for which the foundation pad was to be used and the nature of the structures which were to be placed upon it, understated the cost of the project. After a conference on 12 November between County officials and representatives of Steuart, the permit was reinstated on 21 November with a caveat by the County that: “The permit can in no way be construed as pertaining to the construction of anything except the said foundation pad. Any structure to be erected thereon would necessarily require application for a separate building permit.”

On 1 November, Ordinance No. 73-25 covering the issuance of County building permits had become effective, implementing Section 217 of the Public Local Laws of St. Mary’s County as amended in 1969, which had granted to the County Commissioners broader discretionary powers than had theretofore existed. In pursuance of this grant, the new County building permit ordinance required that construction should commence within four months of the grant of a permit, a condition which applied to both permits held by Steuart. 3 While Steuart challenged the regularity of *439 the proceeding with respect to the enactment of the ordinance and the County’s power to impose the four month limitation, the court below concluded that the ordinance had been regularly adopted and that the time limitation was a valid and reasonable corollary to the power to grant the permit. We agree.

On 1 March 1974, the day before the expiration of the four month period applicable to permit No. 6173, Steuart’s employees, rather than its contractor, poured six concrete footings for a pad on which a transformer was to be located. As work proceeded on the warehouse, it was determined that the footings had been improperly sited, and they were ultimately incorporated in the foundation for the warehouse and shop storage building. In August, 1974, a concrete pad eight feet square was poured for the transformer at a location different from that shown on the application for permit No. 6173. Steuart asserts that the four month time *440 limitation in building permit No. 6173 did not begin to run until 11 February 1974, the date on which a grading permit was issued by the County. This assertion is predicated on the fact that the County Commissioners had informed Steuart in the letter of 21 November 1973 that “prior to the commencement of any construction of the foundation pad, application must be made to and approved by this office [of the County Engineerl for a grading permit. ...” Assuming, for the purposes of this opinion, that the delay in the issuance of the grading permit until February suspended the four month time limitation on the building permit, Steuart still failed to commence construction under permit No. 6173 within four months because the concrete pad was not poured until August, 1974. And, as we will develop later, the pouring of six footings for the pad in March could not, as it turned out, constitute the commencement of construction.

Meanwhile, on 28 May 1974, the County’s new zoning ordinance had become effective. An oil refinery is not a permitted use in property classified as 1-1 (General Industrial) or as PD-IP (Planned Development - Industrial Park), which allow industrial uses in the St. Mary’s County zoning scheme. These are the classifications which appear to apply to Steuart’s Piney Point tract. Storage of petroleum products, however, is a permitted use in a General Industrial District under § 9.4 B 3 of the ordinance and in a Planned Development - Industrial Park District under § 10.19 B 4.

At its 1974 session, the General Assembly had enacted Chapter 583 of the Laws of 1974, referred to by the parties as the Bailey Bill, 4 which would add a new section 4.01(c) to Maryland Code (1957, 1970 Repl. Vol., 1975 Cum. Supp.) Art. 66B, subject, however, to referendum by the voters of the County:

“In St. Mary’s County, land and buildings may not be used for chemical or catalytic manufacturing, chemical fabrication, gasoline processing, or *441 refining of petroleum or petroleum products. This prohibition does not apply to land and buildings used for these purposes on July 23,1974.”

After the Bailey Bill was approved by the voters on 23 July 1974, the County, on 15 August 1974, revoked permit No. 6173 covering the foundation pad because construction had not commenced within four months from the date the permit was issued. The County then sought, in an action in, equity, an injunction prohibiting the construction of the refinery, relying on the prohibition contained in the Bailey Bill and Steuart’s failure to commence construction of the foundation pad within four months after the issuance of a permit. Soon after, Steuart entered an appeal from the revocation of the permit in an action at law in the Circuit Court for the County.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maryland Attorney General Opinion 98 OAG 060
Maryland Attorney General Reports, 2013
Kane v. Board of Appeals
887 A.2d 1060 (Court of Appeals of Maryland, 2005)
Powell v. Calvert County
768 A.2d 750 (Court of Special Appeals of Maryland, 2001)
McKENZIE AND GREEN v. State
748 A.2d 67 (Court of Special Appeals of Maryland, 2000)
McKenzie v. State
748 A.2d 67 (Court of Special Appeals of Maryland, 2000)
Sterling Homes Corp. v. Anne Arundel County
695 A.2d 1238 (Court of Special Appeals of Maryland, 1997)
Relay Improvement Ass'n v. Sycamore Realty Co.
661 A.2d 182 (Court of Special Appeals of Maryland, 1995)
Fish Market Nominee Corp. v. G.A.A. Inc.
650 A.2d 705 (Court of Appeals of Maryland, 1994)
Offen v. County Council for Prince George's County
625 A.2d 424 (Court of Special Appeals of Maryland, 1993)
Prince George's County v. Sunrise Development Ltd. Partnership
623 A.2d 1296 (Court of Appeals of Maryland, 1993)
PG COUNTY v. Sunrise Dev.
623 A.2d 1296 (Court of Appeals of Maryland, 1993)
Levinson v. Montgomery County
620 A.2d 961 (Court of Special Appeals of Maryland, 1993)
Speyer v. Barry
588 A.2d 1147 (District of Columbia Court of Appeals, 1991)
Cade v. Montgomery County
575 A.2d 744 (Court of Special Appeals of Maryland, 1990)
Board of County Commissioners v. Pritchard
540 A.2d 1139 (Court of Appeals of Maryland, 1988)
County of Kauai v. Pacific Standard Life Insurance
653 P.2d 766 (Hawaii Supreme Court, 1982)
Mears v. Town of Oxford
449 A.2d 1165 (Court of Special Appeals of Maryland, 1982)
O'DONNELL v. Bassler
425 A.2d 1003 (Court of Appeals of Maryland, 1981)
Board of Public Works v. Baltimore County
421 A.2d 588 (Court of Appeals of Maryland, 1980)
Prince George's County v. Equitable Trust Co.
408 A.2d 737 (Court of Special Appeals of Maryland, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
347 A.2d 854, 276 Md. 435, 1975 Md. LEXIS 737, Counsel Stack Legal Research, https://law.counselstack.com/opinion/steuart-petroleum-co-v-board-of-county-commissioners-md-1975.