42 U.S.C. § 2235.
Text
(a)All applicants for licenses to construct or modify production or utilization facilities shall, if the application is otherwise acceptable to the Commission, be initially granted a construction permit. The construction permit shall state the earliest and latest dates for the completion of the construction or modification. Unless the construction or modification of the facility is completed by the completion date, the construction permit shall expire, and all rights thereunder be forfeited, unless upon good cause shown, the Commission extends the completion date. Upon the completion of the construction or modification of the facility, upon the filing of any additional information needed to bring the original application up to date, and upon finding that the facility authorized has been c
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Power Reactor Development Co. v. International Union of Electrical, Radio & MacHine Workers
367 U.S. 396 (Supreme Court, 1961)
Rockford League of Women Voters v. United States Nuclear Regulatory Commission, Commonwealth Edison Company, Intervenor-Respondent
679 F.2d 1218 (Seventh Circuit, 1982)
Union of Concerned Scientists v. Atomic Energy Commission and United States of America, Boston Edison Company, Intervenor
499 F.2d 1069 (D.C. Circuit, 1974)
Limerick Ecology Action, Inc. v. United States Nuclear Regulatory Commission
869 F.2d 719 (Third Circuit, 1989)
Public Interest Research Group of NJ, Inc. v. STATE, DEPT. OF ENVIR. PROTECTION
377 A.2d 915 (New Jersey Superior Court App Division, 1977)
Citizens for Safe Power, Inc., and Audubon Naturalist Council v. Nuclear Regulatory Commission, Maine Yankee Atomic Power Company, Intervenor
524 F.2d 1291 (D.C. Circuit, 1975)
New England Power Company v. United States Nuclear Regulatory Commission and United States of America
683 F.2d 12 (First Circuit, 1982)
Morningside Renewal Council, Inc. v. United States Atomic Energy Commission
482 F.2d 234 (Second Circuit, 1973)
Oystershell Alliance v. United States Nuclear Regulatory Commission and United States of America, Louisiana Power & Light Company, Intervenor
800 F.2d 1201 (D.C. Circuit, 1986)
United States v. City of New York
463 F. Supp. 604 (S.D. New York, 1978)
Blue Ridge Environmental Defense League v. Nuclear Regulatory Commission
668 F.3d 747 (D.C. Circuit, 2012)
People's Counsel v. Public Service Commission
270 A.2d 105 (Court of Appeals of Maryland, 1970)
Brooks v. Atomic Energy Commission
476 F.2d 924 (D.C. Circuit, 1973)
Nuclear Information Resource Service v. Nuclear Regulatory Commission
969 F.2d 1169 (D.C. Circuit, 1992)
International Union of Electrical, Radio & Machine Workers v. United States
280 F.2d 645 (D.C. Circuit, 1960)
Citizens Association for Sound Energy v. U.S. Nuclear Regulatory Commission and United States of America, Texas Utilities Electric Co., Intervenors
821 F.2d 725 (D.C. Circuit, 1987)
Eddleman v. Nuclear Regulatory Commission
825 F.2d 46 (Fourth Circuit, 1987)
Coalition for the Environment v. Nuclear Regulatory Commission
795 F.2d 168 (D.C. Circuit, 1986)
Nuclear Information & Resource Service v. United States Nuclear Regulatory
918 F.2d 189 (D.C. Circuit, 1990)
International Union of Electrical, Radio and Machine Workers, Afl-Cio v. United States
280 F.2d 645 (D.C. Circuit, 1960)
Source Credit
History
(Aug. 1, 1946, ch. 724, title I, §185, as added Aug. 30, 1954, ch. 1073, §1, 68 Stat. 955; renumbered title I and amended Pub. L. 102–486, title IX, §902(a)(8), title XXVIII, §2801, Oct. 24, 1992, 106 Stat. 2944, 3120; Pub. L. 118–67, div. B, title V, §505(c), July 9, 2024, 138 Stat. 1478.)
Editorial Notes
Editorial Notes
References in Text
This chapter, referred to in subsecs. (a) and (b), was in the original "this Act", meaning act Aug. 1, 1946, ch. 724, as added by act Aug. 30, 1954, ch. 1073, §1, 68 Stat. 919, known as the Atomic Energy Act of 1954, which is classified principally to this chapter. For complete classification of this Act to the Code, see Short Title note set out under section 2011 of this title and Tables.
Amendments
2024—Subsec. (c). Pub. L. 118–67 added subsec. (c).
1992—Pub. L. 102–486, §2801, inserted "and operating licenses" after "permits" in section catchline, designated existing text as subsec. (a), and added subsec. (b).
Statutory Notes and Related Subsidiaries
Effective Date of 1992 Amendment
Pub. L. 102–486, title XXVIII, §2806, Oct, 24, 1992, 106 Stat. 3121, provided that: "Sections 185 b. and 189 a. (1)(B) of the Atomic Energy Act of 1954 [subsec. (b) of this section and section 2239(a)(1)(B) of this title], as added by sections 2801 and 2802 of this Act, shall apply to all proceedings involving a combined license for which an application was filed after May 8, 1991, under such sections."
Combined License Review Procedure
Pub. L. 118–67, div. B, title II, §207, July 9, 2024, 138 Stat. 1463, provided that:
"(a) In General.—In accordance with this section, the [Nuclear Regulatory] Commission shall establish and carry out an expedited procedure for issuing a combined license pursuant to section 185 b. of the Atomic Energy Act of 1954 (42 U.S.C. 2235(b)).
"(b) Qualifications.—To qualify for the expedited procedure under subsection (a), an applicant—
"(1) shall submit a combined license application for a new nuclear reactor that—
"(A) references a design for which the Commission has issued a design certification (as defined in section 52.1 of title 10, Code of Federal Regulations (or any successor regulation)); or
"(B) has a design that is substantially similar to a design of a nuclear reactor for which the Commission has issued a combined license, an operating license, or a manufacturing license under the Atomic Energy Act of 1954 (42 U.S.C. 2011 et seq.);
"(2) shall propose to construct the new nuclear reactor on a site—
"(A) on which a licensed commercial nuclear reactor operates or previously operated; or
"(B) that is directly adjacent to a site on which a licensed commercial nuclear reactor operates or previously operated and has site characteristics that are substantially similar to that site; and
"(3) may not be subject to an order of the Commission to suspend or revoke a license under section 2.202 of title 10, Code of Federal Regulations (or any successor regulation).
"(c) Expedited Procedure.—With respect to a combined license for which the applicant has satisfied the requirements described in subsection (b), the Commission shall, to the maximum extent practicable—
"(1) not later than 18 months after the date on which the application is accepted for docketing—
"(A) complete the technical review process and issue a safety evaluation report; and
"(B) issue a final environmental impact statement or environmental assessment, unless the Commission finds that the proposed agency action is excluded pursuant to a categorical exclusion in accordance with the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.);
"(2) not later than 2 years after the date on which the application is accepted for docketing, complete any necessary public licensing hearings and related processes; and
"(3) not later than 25 months after the date on which the application is accepted for docketing, make a final decision on whether to issue the combined license.
"(d) Performance and Reporting.—
"(1) Delays in issuance.—Not later than 30 days after the applicable deadline, the Executive Director for Operations of the Commission shall inform the Commission of any failure to meet a deadline under subsection (c).
"(2) Delays in issuance exceeding 90 days.—If any deadline under subsection (c) is not met by the date that is 90 days after the applicable date required under that subsection, the Commission shall submit to the appropriate committees of Congress [Committee on Energy and Commerce of the House of Representatives and Committee on Environment and Public Works of the Senate] a report describing the delay, including—
"(A) a detailed explanation accounting for the delay; and
"(B) a plan for completion of the applicable action."
Executive Documents
Executive Order No. 12129
Ex. Ord. No. 12129, Apr. 5, 1979, 44 F.R. 21001, which established a Critical Energy Facility Program, was revoked by Ex. Ord. No. 12553, Feb. 25, 1986, 51 F.R. 7237.
References in Text
This chapter, referred to in subsecs. (a) and (b), was in the original "this Act", meaning act Aug. 1, 1946, ch. 724, as added by act Aug. 30, 1954, ch. 1073, §1, 68 Stat. 919, known as the Atomic Energy Act of 1954, which is classified principally to this chapter. For complete classification of this Act to the Code, see Short Title note set out under section 2011 of this title and Tables.
Amendments
2024—Subsec. (c). Pub. L. 118–67 added subsec. (c).
1992—Pub. L. 102–486, §2801, inserted "and operating licenses" after "permits" in section catchline, designated existing text as subsec. (a), and added subsec. (b).
Statutory Notes and Related Subsidiaries
Effective Date of 1992 Amendment
Pub. L. 102–486, title XXVIII, §2806, Oct, 24, 1992, 106 Stat. 3121, provided that: "Sections 185 b. and 189 a. (1)(B) of the Atomic Energy Act of 1954 [subsec. (b) of this section and section 2239(a)(1)(B) of this title], as added by sections 2801 and 2802 of this Act, shall apply to all proceedings involving a combined license for which an application was filed after May 8, 1991, under such sections."
Combined License Review Procedure
Pub. L. 118–67, div. B, title II, §207, July 9, 2024, 138 Stat. 1463, provided that:
"(a) In General.—In accordance with this section, the [Nuclear Regulatory] Commission shall establish and carry out an expedited procedure for issuing a combined license pursuant to section 185 b. of the Atomic Energy Act of 1954 (42 U.S.C. 2235(b)).
"(b) Qualifications.—To qualify for the expedited procedure under subsection (a), an applicant—
"(1) shall submit a combined license application for a new nuclear reactor that—
"(A) references a design for which the Commission has issued a design certification (as defined in section 52.1 of title 10, Code of Federal Regulations (or any successor regulation)); or
"(B) has a design that is substantially similar to a design of a nuclear reactor for which the Commission has issued a combined license, an operating license, or a manufacturing license under the Atomic Energy Act of 1954 (42 U.S.C. 2011 et seq.);
"(2) shall propose to construct the new nuclear reactor on a site—
"(A) on which a licensed commercial nuclear reactor operates or previously operated; or
"(B) that is directly adjacent to a site on which a licensed commercial nuclear reactor operates or previously operated and has site characteristics that are substantially similar to that site; and
"(3) may not be subject to an order of the Commission to suspend or revoke a license under section 2.202 of title 10, Code of Federal Regulations (or any successor regulation).
"(c) Expedited Procedure.—With respect to a combined license for which the applicant has satisfied the requirements described in subsection (b), the Commission shall, to the maximum extent practicable—
"(1) not later than 18 months after the date on which the application is accepted for docketing—
"(A) complete the technical review process and issue a safety evaluation report; and
"(B) issue a final environmental impact statement or environmental assessment, unless the Commission finds that the proposed agency action is excluded pursuant to a categorical exclusion in accordance with the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.);
"(2) not later than 2 years after the date on which the application is accepted for docketing, complete any necessary public licensing hearings and related processes; and
"(3) not later than 25 months after the date on which the application is accepted for docketing, make a final decision on whether to issue the combined license.
"(d) Performance and Reporting.—
"(1) Delays in issuance.—Not later than 30 days after the applicable deadline, the Executive Director for Operations of the Commission shall inform the Commission of any failure to meet a deadline under subsection (c).
"(2) Delays in issuance exceeding 90 days.—If any deadline under subsection (c) is not met by the date that is 90 days after the applicable date required under that subsection, the Commission shall submit to the appropriate committees of Congress [Committee on Energy and Commerce of the House of Representatives and Committee on Environment and Public Works of the Senate] a report describing the delay, including—
"(A) a detailed explanation accounting for the delay; and
"(B) a plan for completion of the applicable action."
Executive Documents
Executive Order No. 12129
Ex. Ord. No. 12129, Apr. 5, 1979, 44 F.R. 21001, which established a Critical Energy Facility Program, was revoked by Ex. Ord. No. 12553, Feb. 25, 1986, 51 F.R. 7237.