Nuclear Information Resource Service v. Nuclear Regulatory Commission

969 F.2d 1169, 22 Envtl. L. Rep. (Envtl. Law Inst.) 21252, 297 U.S. App. D.C. 169, 1992 U.S. App. LEXIS 16068
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 17, 1992
Docket89-1381
StatusPublished
Cited by2 cases

This text of 969 F.2d 1169 (Nuclear Information Resource Service v. Nuclear Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nuclear Information Resource Service v. Nuclear Regulatory Commission, 969 F.2d 1169, 22 Envtl. L. Rep. (Envtl. Law Inst.) 21252, 297 U.S. App. D.C. 169, 1992 U.S. App. LEXIS 16068 (D.C. Cir. 1992).

Opinion

969 F.2d 1169

Nuclear Reg. Rep. P 20,556, 297 U.S.App.D.C. 169,
22 Envtl. L. Rep. 21,252

NUCLEAR INFORMATION RESOURCE SERVICE, et al., Petitioners,
v.
NUCLEAR REGULATORY COMMISSION and United States of America,
Respondents,
Nuclear Management and Resources Council, Inc., Intervenor.

No. 89-1381.

United States Court of Appeals,
District of Columbia Circuit.

Argued Nov. 20, 1991.
Decided July 17, 1992.

Eric R. Glitzenstein, with whom Katherine A. Meyer was on the brief, for petitioners. William B. Schultz, Alan B. Morrison, Dean R. Tousley, Diane Curran, and James M. Shannon also entered appearances for petitioners.

John F. Cordes, Jr., Solicitor, Nuclear Regulatory Com'n, with whom Barry M. Hartman, Acting Asst. Atty. Gen., Ellen J. Durkee, Atty., Dept. of Justice, William C. Parler, Gen. Counsel, E. Leo Slaggie, Deputy Sol., and Carole F. Kagan, Senior Atty., Nuclear Regulatory Com'n, were on the brief, for respondents. Richard B. Stewart, Asst. Atty. Gen., John A. Bryson, Atty., Dept. of Justice, Martin G. Malsch, and Steven F. Crockett also entered appearances for respondents.

Marcus A. Rowden, with whom P. David Richardson, Barton Z. Cowan, Joseph M. Ramirez, and Robert W. Bishop were on the brief, for intervenor. Arthur Lazarus, Jr., also entered an appearance for intervenor.

Dorothy Thompson and Robert Guild entered appearances for amici curiae.

Before MIKVA, Chief Judge; WALD, EDWARDS, SILBERMAN, BUCKLEY, WILLIAMS, D.H. GINSBURG, SENTELLE, HENDERSON, and RANDOLPH, Circuit Judges.*

Opinion for the Court filed by Circuit Judge SENTELLE.

Dissenting opinion on the denial of a pre-operational hearing on new safety information filed by Circuit Judge WALD, with whom Chief Judge MIKVA and Circuit Judge HARRY T. EDWARDS join.

Opinion concurring in part and dissenting in part filed by Circuit Judge BUCKLEY.

SENTELLE, Circuit Judge:

We today review en banc a Nuclear Regulatory Commission ("NRC" or "Commission") rule aimed at substantially revamping the licensing process for nuclear power plants. 10 C.F.R. Part 52. This matter was previously heard by a panel of this Court in Nuclear Information and Resource Service v. United States NRC, 918 F.2d 189 (D.C.Cir.1990) ("NIRS ").

The panel concluded that the Commission's decision in Part 52 to authorize issuance of a single, "combined license" in lieu of separate construction and operating permits was acceptable under the Atomic Energy Act ("Act" or "AEA"). It likewise upheld the Commission's reliance on a pre-approval process for assessing reactor designs and sites. The panel did, however, declare facially invalid Part 52's regulations regarding the Commission's duties in making findings and holding hearings after construction is completed and before operation begins.

After rehearing, we continue to affirm the Commission's combined license procedures and its reliance on the pre-approval process; however, we now also hold that the post-construction procedures embodied in Part 52 are based on a permissible reading of the AEA.1

I.

Before conducting the rulemaking now before us, the NRC licensed nuclear reactors in two regulatory steps. See 10 C.F.R. Part 50. At the first step, the Commission was required to find the proposed site and preliminary design plans acceptable, and conduct a public hearing on these matters; thereafter, the Commission issued a construction permit. Upon completion of construction, the licensee then sought an operating license, which could be granted only after the Commission approved the reactor's final design, made several other findings, and conducted another public hearing.

Because Part 50 allowed the NRC to issue a construction permit on incomplete design information, it often became necessary for the Commission to impose new regulatory requirements as construction continued and plans changed. A "design-as-you-go" approach on the part of licensees was mirrored by a "regulate-as-you-go" tack on the part of the Commission. The result of this regimen was, as the Office of Technology Assessment has stated, that

[e]ssentially every reactor ... has been custom-designed and custom-built. The fact that almost every reactor is "one of a kind" has led to excessive difficulty in verifying the safety of individual plants and identifying particular problems in transferring the safety lessons from one reactor to another.

Congress of the United States, Office of Technology Assessment, Nuclear Power Plant Standardization at 3 (1981).

After a number of unsuccessful attempts to persuade Congress to restructure the licensing process through new legislation, in 1987 the Commission moved to reform reactor licensing regulations under existing legislation. It did so with two announced objectives: to standardize nuclear power plant design, and to establish a procedural framework for resolving with some finality as many safety and environmental issues as possible before--rather than after--construction begins. See 52 Fed.Reg. 34,884 (1987). In 1989, the Commission announced its final product, known collectively as Part 52. 54 Fed.Reg. 15,372 (1989) (codified at 10 C.F.R. Part 52).

Pre-Approval of Designs and Sites. One major feature of Part 52 is the NRC's new regulatory scheme for pre-approval of standardized power plant designs by rulemaking. 10 C.F.R. Part 52, Subpart B. Under Subpart B, an applicant files with the Commission a proposed design; if, after a period of notice and comment and a possible hearing, the Commission concludes that the design is safe, it issues a design certification. 10 C.F.R. §§ 52.41-.63. This certification remains effective for 15 years, and is renewable in successive rulemakings. 10 C.F.R. §§ 52.57-.61. Thus, the procedure allows applicants to register a "generic" design with the Commission that may be utilized any number of times during the life of the certification.

Related to the pre-approval process for plant designs is one for the early determination of plant sites. 10 C.F.R. Part 52, Subpart A. Under the "early site permit" process, the Commission may, after conducting a hearing and making necessary findings, approve a site permit. 10 C.F.R. §§ 52.11-.39. While a site permit does not authorize construction, it does establish design criteria for plant construction on the proposed site. Moreover, it retains validity for up to 20 years, though the NRC may extend this period after another examination. 10 C.F.R. §§ 52.29-.33.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kelley v. Selin
42 F.3d 1501 (Sixth Circuit, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
969 F.2d 1169, 22 Envtl. L. Rep. (Envtl. Law Inst.) 21252, 297 U.S. App. D.C. 169, 1992 U.S. App. LEXIS 16068, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nuclear-information-resource-service-v-nuclear-regulatory-commission-cadc-1992.