Blue Ridge Environmental Defense League v. Nuclear Regulatory Commission

668 F.3d 747, 399 U.S. App. D.C. 202, 2012 WL 516498, 2012 U.S. App. LEXIS 3116
CourtCourt of Appeals for the D.C. Circuit
DecidedFebruary 17, 2012
Docket09-1112, 10-1058
StatusPublished
Cited by9 cases

This text of 668 F.3d 747 (Blue Ridge Environmental Defense League v. Nuclear Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blue Ridge Environmental Defense League v. Nuclear Regulatory Commission, 668 F.3d 747, 399 U.S. App. D.C. 202, 2012 WL 516498, 2012 U.S. App. LEXIS 3116 (D.C. Cir. 2012).

Opinion

Opinion for the court filed by Senior Circuit Judge EDWARDS.

EDWARDS, Senior Circuit Judge:

In December 1974, Tennessee Valley Authority (“TVA”) received construction permits from the Atomic Energy Commission, the predecessor to the Nuclear Regulatory Commission (“the NRC” or “the Commission”), for the Bellefonte Nuclear Plant, Units 1 and 2 (“the units”). TVA pursued construction under a series of permit extensions through the late 1980s, when, based on its projections of diminished energy demand, it decided to place the units in “deferred status” and establish a maintenance program under the NRC’s Policy Statement on Deferred Plants (“the Policy Statement”). See 52 Fed. Reg. 38,-077, 38,077-79 (Oct. 14, 1987). Under the Policy Statement, during a deferral period, a permit holder is required to undertake maintenance and preservation activities but may halt actual construction. In 2005, TVA placed the units in “terminated” status under the Policy Statement. One year later, TVA voluntarily requested that the NRC withdraw the permits. The NRC granted this request.

In 2008, TVA asked the NRC to reinstate its withdrawn construction permits. Although neither withdrawal nor reinstatement are specifically addressed in the Atomic Energy Act (“the AEA” or “the Act”), see 42 U.S.C. § 2239 (2006), the NRC granted TVA’s reinstatement request in an order issued on March 9, 2009 and published in the Federal Register on March 13, 2009.

On March 30, 2009, the Blue Ridge Environmental Defense League (“BREDL” or “Petitioner”) filed a petition with this court, purporting to challenge the NRC’s decision to reinstate the construction permits. However, in its Statement of Issues To Be Raised, in its Reply Brief, and during oral argument, BREDL insisted that it was not challenging the NRC order that was published in the Federal Register *749 on March 13, 2009. Rather, BREDL asserted that its March 30, 2009 petition for review challenges only a compilation of “Response Sheets” filed by individual Commissioners in December 2008 and January 2009.

BREDL contends that this compilation of Commissioners’ views resulted in a final order on January 27, 2009. We disagree. After the Commissioners’ “Response Sheets” were assembled, the matter was referred to the NRC staff for evaluation. However, it was not until February 18, 2009 that the NRC authorized the staff to issue an order on behalf of the agency reinstating the construction permits. That order was published in the Federal Register on March 13, 2009. Therefore, BREDL’s petition for review challenging an alleged action of the NRC taken on January 27, 2009 does not seek review of a final NRC order.

On May 8, 2009, BREDL, along with some other parties, petitioned the NRC to intervene in an agency good cause hearing on the Commission’s action reinstating the construction permits. The NRC decided to hear BREDL’s legal contentions first, before addressing technical contentions primarily regarding the safety of reinstating the construction permits. On January 7, 2010, the NRC issued an opinion rejecting BREDL’s legal claims and referring BREDL’s remaining claims to the Atomic Safety and Licensing Board (“the ASLB”) for disposition. On March 8, 2010, before the ASLB had addressed BREDL’s remaining contentions, BREDL filed its second petition for review with this court. This second petition challenges the NRC’s January 7, 2010 opinion rejecting BREDL’s legal claims. BREDL contends that the agency’s January 7 opinion qualifies as a final agency action that is subject to judicial review. We disagree. It is clear on the record here that the NRC’s January 7 opinion was merely an interlocutory action addressing BREDL’s legal challenges to the Commission’s authority. BREDL had raised numerous other claims that were referred to the ASLB, and those claims remained pending before the NRC when BREDL filed its premature petition for review on March 8, 2010.

Under the Hobbs Act, this court has jurisdiction to review only “final orders” of the NRC. 28 U.S.C. § 2342(4) (2006). The March 30, 2009 and March 8, 2010 petitions filed by BREDL with this court do not seek review of final NRC orders. Therefore, we lack jurisdiction and must dismiss.

I. Background

A. Facts

The AEA provides the general framework that governs the construction of nuclear power plants. Before a company can build a plant, it must seek a construction permit from the NRC. See 42 U.S.C. § 2235(a). All construction permits must specify the latest date by which construction must be complete, although the NRC can extend deadlines for good cause. Id. All of a permit holder’s rights and privileges are “forfeited” when a permit “expire[s]” on the designated completion date. Id. The AEA also authorizes the NRC to revoke a construction permit prior to completion in the event of wrongdoing. See id. § 2236. But the Act does not account for the possibility that a permit holder might voluntarily request that the NRC withdraw a valid construction permit, nor does it address whether the NRC may reinstate a construction permit that has been withdrawn. See id. § 2239.

TVA first applied for construction permits for the units in 1973. See In re Tenn. Valley Autk, 71 N.R.C. 113, 115 (2010), reprinted in Joint App. (“J.A.”) 14. The *750 ASLB considered interested citizens’ intervention requests, conducted an evidentiaryhearing, and issued a favorable decision in December 1974. The permits for the units were set to expire in 1979 and 1980 respectively. See id. at 115-16. But by 1979, TVA realized that it would not be able to complete construction by the deadlines due in part to labor shortages, delivery problems, and the need for new safety features following the Three Mile Island accident. See TVA, Bellefonte Nuclear Plant, Units 1 and 2; Order Extending Construction Completion Dates, 44 Fed. Reg. 76,893, 76,893 (Dec. 28, 1979). TVA thus requested, and the NRC granted, an extension of the permit deadlines. See id. But TVA found that it could not complete construction by the new deadlines, and it again submitted timely extension requests, which the NRC granted. See TVA, Bellefonte Nuclear Plant, Units 1 and 2; Order Extending Construction Completion Dates, 52 Fed. Reg. 25,676, 25,676 (July 8, 1987).

Soon after the 1987 extension, TVA decided to defer construction of the plants under the Commission’s Policy Statement. In re Tenn. Valley Autk, 71 N.R.C. at 116. At the time of deferral, Units 1 and 2 were approximately ninety and sixty percent complete, respectively. Id. Under the Policy Statement, a permit holder may resume construction of a plant only after providing at least an 120-day notice to the NRC and receiving the NRC’s approval that the plant’s systems, structures, and components are acceptable. See

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brotherhood of Locomotive Engi v. FRA
972 F.3d 83 (D.C. Circuit, 2020)
Jones v. Department of Health & Human Services
834 F.3d 1361 (Federal Circuit, 2016)
Adenariwo v. Federal Maritime Commission
808 F.3d 74 (D.C. Circuit, 2015)
Eirik Tillman v. Ohio Bell Telephone Company
545 F. App'x 340 (Sixth Circuit, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
668 F.3d 747, 399 U.S. App. D.C. 202, 2012 WL 516498, 2012 U.S. App. LEXIS 3116, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blue-ridge-environmental-defense-league-v-nuclear-regulatory-commission-cadc-2012.