Oglala Sioux Tribe v. U.S. Nuclear Regulatory Comm'n

896 F.3d 520
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 20, 2018
Docket17-1059
StatusPublished
Cited by31 cases

This text of 896 F.3d 520 (Oglala Sioux Tribe v. U.S. Nuclear Regulatory Comm'n) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oglala Sioux Tribe v. U.S. Nuclear Regulatory Comm'n, 896 F.3d 520 (D.C. Cir. 2018).

Opinion

Opinion for the Court filed by Chief Judge GARLAND.

GARLAND, Chief Judge : Powertech (USA), Inc. applied to the Nuclear Regulatory Commission for a license to construct a uranium mining project in the Black Hills of South Dakota. The Oglala Sioux Tribe, which has historical ties to the proposed project area, intervened in opposition because it feared the destruction of its cultural, historical, and religious sites. The staff of the Commission granted the license.

On administrative appeal, the Commission decided to leave the license in effect-notwithstanding its own determination that *523 there was a significant deficiency in its compliance with the National Environmental Policy Act-pending further agency proceedings to remedy the deficiency. The Commission grounded this decision on the Tribe's inability to show that noncompliance with the Act would cause irreparable harm. In so doing, the Commission was following what appears to be the agency's settled practice to require such a showing.

The National Environmental Policy Act, however, obligates every federal agency to prepare an adequate environmental impact statement before taking any major action, which includes issuing a uranium mining license. The statute does not permit an agency to act first and comply later. Nor does it permit an agency to condition performance of its obligation on a showing of irreparable harm. There is no such exception in the statute.

In fact, such a policy puts the Tribe in a classic Catch-22. In order to require the agency to complete an adequate survey of the project site before granting a license, the Tribe must show that construction at the site would cause irreparable harm to cultural or historical resources. But without an adequate survey of the cultural and historical resources at the site, such a showing may well be impossible. Of course, if the project does go forward and such resources are damaged, the Tribe will then be able to show irreparable harm. By then, however, it will be too late.

The Commission's decision to let the mining project proceed violates the National Environmental Policy Act. Indeed, it vitiates the requirements of the Act. We therefore find the decision contrary to law and grant the petition for review in part. The Tribe also challenges other aspects of the Commission's order but, as we explain, we lack jurisdiction to consider those rulings.

I

The Atomic Energy Act, 42 U.S.C. § 2011 et seq. , authorizes the Nuclear Regulatory Commission (NRC) to issue licenses to qualified applicants to transfer, deliver, or receive source material from in-situ leach uranium mining (also known as ISL or ISR mining), a process used to recover underground uranium for subsequent use in nuclear power plants. 42 U.S.C. § 2092 ; see Va. Uranium, Inc. v. Warren , 848 F.3d 590 , 596 (4th Cir. 2017). No one can conduct such activities without an NRC license. 42 U.S.C. § 2092 . The Act also creates hearing rights. Anyone "whose interest may be affected by [a] proceeding" to grant a license has the right to intervene and present "contentions" challenging the license. Id. § 2239(a)(1)(A); 10 C.F.R. § 2.309 (a), (f).

The licensing process involves three relevant components of the NRC.

The first is the Commission Staff, which is responsible for reviewing a license application, analyzing the environmental effects and other features of the proposed project, and issuing an initial decision approving or denying the application. 10 C.F.R. §§ 2.103 , 51.80, 51.102.

The second is an Atomic Safety and Licensing Board (ASLB), a panel that can be designated to preside over a licensing hearing, at which the Board hears contentions from intervenors and then issues an initial decision on those contentions. Id. §§ 2.313(a), 2.321, 2.1210. Through the Board hearing process, intervenors can challenge the agency's compliance with the National Environmental Policy Act (NEPA), which requires federal agencies to prepare a detailed Environmental Impact Statement (EIS) for any "proposed" major federal action that "significantly affect[s] the quality of the human environment," 42 U.S.C. § 4332 (2)(C), including *524 granting the kind of license at issue here, see 10 C.F.R. § 51.20 (b)(8).

Third is the Commission itself. Once the Board issues an initial decision on the contentions before it, parties can seek review from the Commission. Id. § 2.341(b). The Commission "may adopt, modify, or set aside" the Board's decision. Id. § 2.344(b).

In 2009, Powertech applied for an NRC license authorizing it to "construct and operate" a uranium mining project, called the "Dewey-Burdock project," in the southwest corner of South Dakota. NRC, Record of Decision for the Dewey-Burdock Uranium In-Situ Recovery Project at 1 (2014) ("Record of Decision") (J.A. 738). The NRC described the project as follows:

The proposed facility will encompass approximately ... 10,580 acres[,] which consists of two contiguous mining units ....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
896 F.3d 520, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oglala-sioux-tribe-v-us-nuclear-regulatory-commn-cadc-2018.