Ocean Winds Corp. v. Lane

556 S.E.2d 377, 347 S.C. 416, 2001 S.C. LEXIS 189
CourtSupreme Court of South Carolina
DecidedNovember 26, 2001
DocketNo. 25380
StatusPublished
Cited by8 cases

This text of 556 S.E.2d 377 (Ocean Winds Corp. v. Lane) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ocean Winds Corp. v. Lane, 556 S.E.2d 377, 347 S.C. 416, 2001 S.C. LEXIS 189 (S.C. 2001).

Opinion

Justice PLEICONES.

We accepted this certified question from the United States District Court to determine whether certain events trigger the running of the statute of repose codified at S.C.Code Ann. § 15-3-640 (Supp.2000).

FACTS

The district court made the following findings of fact: Plaintiff Ocean Winds Corporation of Johns Island (“Ocean Winds”) developed, built, and owned a condominium project on Sea-brook Island. In April 1997, Ocean Winds Council of Co-Owners sued Ocean Winds in its capacity as owner/developer/builder for water damage and other structural problems with the property. Ocean Winds thereafter filed suit against the defendants, including Andersen Windows (“Andersen”), seeking recovery for any damages Council of Co-Owners might recover from Ocean Winds. Andersen manufactured and supplied the windows used in the condominium project. The windows were installed no later than December 2, 1986. This case was not commenced against Andersen until February 2000, more than thirteen years after the installation of the windows. Certificates of Occupancy were issued for the various units between June 9,1987, and May 6,1991.

[418]*418CERTIFIED QUESTION

Where the owner/developer/builder of a building brings a lawsuit against a window manufacturer/supplier for allegedly defective windows, installed as an improvement during the construction of that building, for purposes of the statute of repose, S.C.Code Ann. § 15-3-640 (Supp.2000), does the “substantial completion of such improvement” occur upon substantial completion of the installation of the windows or upon substantial completion of the building as a whole?

DISCUSSION

Section 15-3-640 provides, in part:

No actions to recover damages based upon or arising out of the defective or unsafe condition of an improvement to real property may be brought more than thirteen years after substantial completion of such an improvement. For purposes of this section, an action based upon or arising out of the defective or unsafe condition of an improvement to real property includes:
(6) an action for contribution or indemnification for damages sustained on account of an action described in this subdivision; ...
(9) an action against owners or manufacturers of components, or against any person furnishing materials, or against any person who develops real property, or who performs or furnishes the design, plans, specifications, surveying, planning, supervision, testing, or observation of construction, or construction of an improvement to real property, or a repair to an improvement to real property....

“Substantial completion” is defined in S.C.Code Ann. § 15-3-630 (1976) as “that degree of completion of a project, improvement, or a specified area or portion thereof ... upon attainment of which the owner can use the same for the purpose for which it was intended____”

The cardinal rule of statutory construction is that legislative intent prevails. Statutory provisions should be given a reasonable and practical construction consistent with [419]*419the purpose and policy expressed in the statute. Folk v. Thomas, 344 S.C. 77, 81, 543 S.E.2d 556, 558 (2001).

Ocean Winds argues the thirteen year period set forth in § 15-3-640 did hot begin to run until certificates of occupancy were issued for the various units. Conversely, Andersen argues the period should run from the date installation of the windows was completed, despite the fact that certificates of occupancy were not issued until some time later.

We hold that the thirteen year period prescribed in the statute of repose began running when installation of the windows was complete. The definition of “substantial completion” contained in § 15-3-630 requires this result. The legislature defines “substantial completion” as “that degree of completion of a project, improvement, or a specified area or portion thereof ... upon attainment of which the owner can use the same for the purpose for which it was intended .... ” (Emphasis suppled).

Here the windows were “a specified area or portion” of the larger condominium project. Upon their incorporation into the larger project, which occurred no later than December 2, 1986, the owner, Ocean Winds Corporation, could use the windows “for the purpose for which [they were] intended.” Andersen should have been able to assume with confidence that it would not be amenable to suit as of December 3, 1999, thirteen years and one day after its windows were installed, and its portion of the project was substantially complete.

We find additional support for this conclusion in the preamble to § 15-3-640.1 The preamble provides

Whereas, the General Assembly finds that persons involved in improvements to real property are subject to the economic and emotional burdens of litigation and liability for an indefinite period of time upon allegations of defective or unsafe conditions; and. [sic]
Whereas, the General Assembly finds it in the public interest to provide a measure of protection against claims and litigation arising years after substantial completion of an improvement to real property; and. [sic]
[420]*420Whereas, the General Assembly finds that substantial differences exist between improvements to real property and other activities for which liability may be alleged, including the fact that improvements to real property have lengthy useful lives and are utilized, changed, and affected by many people, forces, and things after completion; and. [sic] Whereas, the General Assembly finds it reasonable and necessary to distinguish between a person in actual possession or control of an improvement to real property and those otherwise involved in an improvement to real property, for the following reasons: because acceptance of some future responsibility for the condition of the premises is implied in the acceptance of an improvement to real property; because possession or control of the premises is a reasonable and fair basis for imposing some additional liability; because after the date of acceptance of the work by the owner, there exists the possibility of neglect, abuse, poor maintenance, mishandling, improper modification, or unskilled repair of an improvement; because owners and persons in control have the opportunity to avoid liability by taking care of the improvement and by regulating its use____

Thus, the preamble indicates that the legislature sought to address those instances where “persons involved in improvements to real property are subject to the economic and emotional burdens of litigation and liability for an indefinite period of time upon allegations of defective or unsafe conditions.”

Adopting Ocean Winds’ interpretation would frustrate the legislature’s intent in enacting the statute of repose. In the instant case, for example, installation of the windows was unquestionably completed by December 2,1986. The windows first became subject to the forces of nature and the “possibility of neglect, abuse, poor maintenance, mishandling, improper modification, or unskilled repair” on that date. However, certificates of occupancy were not issued on all units until May 6, 1991, nearly four and a half years later.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lane v. New Gencoat Inc
D. South Carolina, 2022
Lawrence ex rel. Situated v. Gen. Panel Corp.
822 S.E.2d 800 (Supreme Court of South Carolina, 2019)
Sierra Pacific Industries, Inc. v. Bradbury
2016 COA 132 (Colorado Court of Appeals, 2016)
Horning v. Penrose Plumbing & Heating Inc.
2014 WY 133 (Wyoming Supreme Court, 2014)
Silva v. Warden, NH State Prison
2010 DNH 049 (D. New Hampshire, 2010)
Ervin v. CONTINENTAL CONVEYOR & EQUIPMENT CO.
674 F. Supp. 2d 709 (D. South Carolina, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
556 S.E.2d 377, 347 S.C. 416, 2001 S.C. LEXIS 189, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ocean-winds-corp-v-lane-sc-2001.