Sierra Pacific Industries, Inc. v. Bradbury

2016 COA 132, 409 P.3d 551
CourtColorado Court of Appeals
DecidedSeptember 8, 2016
DocketCourt of Appeals 15CA1652
StatusPublished
Cited by4 cases

This text of 2016 COA 132 (Sierra Pacific Industries, Inc. v. Bradbury) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sierra Pacific Industries, Inc. v. Bradbury, 2016 COA 132, 409 P.3d 551 (Colo. Ct. App. 2016).

Opinion

Opinion by

JUDGE DAILEY

¶ 1 In this construction defect dispute, plaintiff, Sierra Pacific Industries, Inc. (Sierra Pacific), appeals the .district court’s entry of summary judgment in favor of defendant, Jason Bradbury, d/b/a ‘Bradbury Construction, Inc. (Bradbury). We affirm.

I. Background

¶ 2 Sierra Pacific was hired by a contractor, the Weitz Company I, Inc. (Weitz), to supply windows and doors for the construction of condominiums for the Ajax Lofts Condominium Association, Inc. (Ajax). Sierra Pacific, in turn, hired' Bradbury to install the windows and doors; Bradbury began and completed its work in 2002.

¶ 3 On June 11, 2004, the City and County of Denver issued a certificate of occupancy for all units. Subsequently, however, the condominiums’ residents began complaining to Ajax about water infiltration. At Ajax’s direction, Weitz and Sierra Pacific attended to the reported leaks and water damage between 2004 and 2011, including two substantial retrofit repairs in January 2005 and March 2011; Bradbury participated in some repair efforts in 2004, but none thereafter.

¶ 4 In November 2011, Ajax filed suit against Weitz for the alleged defective construction. Weitz, in turn, filed suit against Sierra Pacific for damages, costs, and ex.penses related to Ajax’s claims.. Following the district court’s consolidation of the two cases (hereinafter, the underlying case), Ajax, Weitz, and Sierra Pacific reached a settlement on July 31, 2014.

¶ 5 On October 20, 2014, Sierra Pacific filed the present indemnification action against-Bradbury to recover losses incurred in the settlement and damages for related contractual breaches. Bradbury filed a motion, for summary judgment under C.R.C.P. 56(b), .asserting that Sierra Pacific’s claims, brought nearly ten- years after Bradbury ceased repair efforts .on the project, were time barred by the six-year statute of repose in Colorado’s Construction Defect Action Reform Act (CDARA), § 13-8Ó-104, C.R.S. 2015.

¶ 6 Sierra Pacific responded that its claims were not barred by the statute of repose because (1) under section 13 — 80—104(l)(b)(II), its claims against Bradbury did not' “arise’-’ until after the underlying case was settled in 2014, after which Sierra Pacific had ninety days to file its complaint (which it did); and (2) even if the statute of repose was not tolled by the settlement, the period of repose did not commence until 2011, when the improvements to the property in connection with Bradbury’s defective work were substantially completed.

¶ 7 Bradbury replied that (1) there is no settlement exception to the statute of repose; and (2) the statute of repose commenced, at the latest, upon its completion of work in 2004.

¶ 8 The district court concluded that

• both the 2005 and 2011 repairs constituted “improvement[s] to the real property,” § 13-80-104(1);
• “[s]ince Bradbury conducted repairs in 2004, [it] may have contributed to the 2005 retrofit,” but the 2011 retrofit constituted a “separate effort”;
• “[t]herefore, the effective date of -substantial completion in regard[ ] to . Bradbury’s work is January 2005”;
*554 • to toll the statute of repose that commenced in January 2005, Sierra Pacific would have had to notify Bradbury of its claims within the requisite six-year period;
• “[i]t is undisputed that Bradbury did not have notice of [Sierra Pacific’s] claims within the requisite time period”; and
• consequently, Sierra Pacific’s claims against Bradbury are barred by the six-year statute of repose.

¶ 9 Accordingly, the district court granted Bradbury’s motion for summary judgment.

II. Analysis

¶ 10 Sierra Pacific contends that the district court erred in finding that its claims were barred by the six-year statute of repose. We disagree.

¶ 11 We review de novo a district court’s order granting summary judgment. Mountain States Adjustment v. Cooke, 2016 COA 80, ¶ 11, 412 P.3d 819. Summary judgment is proper when there is no genuine issue as to any material fact and the moving party is entitled to judgment as a matter of law. Geiger v. Am. Standard Ins. Co. of Wis., 192 P.3d 480, 482 (Colo.App.2008).

¶ 12 A district court’s ruling may be affirmed based on any grounds that are supported by the record. Rush Creek Sols., Inc. v. Ute Mountain Ute Tribe, 107 P.3d 402, 406 (Colo.App.2004).

A The Statute of Repose Was Not Tolled Until the Settlement in the Underlying Case

¶ 13 A statute of limitations creates a time limit for a plaintiff to file suit in a civil case and is based on when a claim accrued; in contrast, a statute of repose bars any suit filed after a specific time, thereby acting as a “‘cutoff or absolute bar on a defendant’s liability, and it reflects a legislative judgment that a defendant should be free from liability after the legislatively prescribed period of time.” Lewis v. Taylor, 2016 CO 48, ¶ 43, 375 P.3d 1205 (Gabriel, J., dissenting) (citing CTS Carp. v. Waldburger, 573 U.S. -, -, 134 S.Ct. 2175, 2183, 189 L.Ed.2d 62 (2014)); see also Gleason v. Becker-Johnson Assocs., Inc., 916 P.2d 662, 664 (Colo.App.1996) (“Unlike a statute of limitations, a statute of repose imposes an absolute bar to bringing suit after a set period of time, regardless of whether the claim has accrued or an injury has resulted. Thus, even though a statute of limitations may not bar an action, a statute of repose operates independently.”) (citation omitted). 1

¶ 14 “Section 13-80-104 ... contains both a statute of limitations and a statute of repose that are applicable to suits against architects, contractors, builders or builder vendors, engineers, inspectors, and others involved in real property construction or improvements.” Thermo Dev., Inc. v. Cent. Masonry Corp., 195 P.3d 1166, 1167 (Colo.App.2008). Section 13-80-104(l)(a) incorporates the two-year statute of limitations contained in section 13-80-102(1), C.R.S. 2015; and, subsections (l)(a) and (2) of section 13-80-104 provide a statute of repose which expires six years “after the substantial completion of the improvement to, the real property,” unless it is extended two years because the underlying cause of action arose “during the fifth or sixth year after substantial completion of the improvement to real property.” 2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Goodman v. Heritage Builders
2017 CO 13 (Supreme Court of Colorado, 2017)
Medved v. State
434 P.3d 674 (Colorado Court of Appeals, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
2016 COA 132, 409 P.3d 551, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sierra-pacific-industries-inc-v-bradbury-coloctapp-2016.