United Water & Sanitation District v. Geo-Con, Inc.

CourtDistrict Court, D. Colorado
DecidedSeptember 21, 2020
Docket1:18-cv-03241
StatusUnknown

This text of United Water & Sanitation District v. Geo-Con, Inc. (United Water & Sanitation District v. Geo-Con, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Water & Sanitation District v. Geo-Con, Inc., (D. Colo. 2020).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLORADO Chief Judge Philip A. Brimmer Civil Action No. 18-cv-03241-PAB-SKC UNITED WATER AND SANITATION DISTRICT, Plaintiff, v. GEO-CON, INC., Defendant.

ORDER This matter is before the Court on defendant Geo-Con, Inc’s [Re-filed] Motion to Dismiss Complaint [Docket No. 79]. The Court has jurisdiction pursuant to 28 U.S.C. § 1332.

I. BACKGROUND This case arises out of the construction of a “slurry wall” for a water impoundment in Adams County, Colorado. A slurry wall is “a civil engineering technique used to build concrete walls in areas of soft earth close to open water, or with a high groundwater table.” Docket No. 3 at 5, ¶ 7. Because slurry walls can act as a water barrier, they are used in the construction of water reservoirs. Id., ¶¶ 8-9. A slurry wall must be “key[ed]” or “tie[d]” into the bedrock in order to be an effective water barrier. Id., ¶ 8. Accordingly, a slurry wall that will be used as a water barrier must be designed and constructed deep enough to key into the bedrock. Id. On or about December 11, 2002, Silver Peaks Metropolitan District No. 1, an entity that owned Brannan Pit #28 (the “pit”) in Adams County, entered into a contract with defendant Geo-Con, Inc. to construct a slurry wall at the pit Id., ¶ 9. The purpose of the slurry wall was to create a water reservoir at the pit. Id. The slurry wall contract

initially included certain specifications for how deep the slurry wall would need to be constructed to properly key into the pit’s bedrock. Id., ¶ 10. During construction, the parties realized that a deeper slurry wall would be required. Id. at 6, ¶ 11. The parties executed change orders to the contract to add “extra key depth” to the slurry wall. Id., ¶ 13. “Sometime thereafter,” Geo-Con “ostensibly” completed the slurry wall to contract specifications, including the deeper key depth. Id. at 6, ¶ 14. Silver Peaks subsequently assigned its interests in, among other things, the slurry wall project to plaintiff United Water and Sanitation District. Id., ¶ 15. In mid- 2017, United Water discovered that the slurry wall was leaking. Id., ¶ 16. On or about November 1, 2017, United Water received an engineering report indicating that the

slurry wall had been incompletely constructed. Id., ¶ 18. United Water’s investigation revealed that the slurry wall was inadequately keyed into bedrock in certain places. Id. at 7, ¶ 20. On November 14, 2018, United Water filed this lawsuit against Geo-Con and Geo-Solutions, Inc. in the District Court for Adams County, Colorado. Docket No. 3 at 10. Geo-Solutions, Inc. subsequently removed the case to this Court. Docket No. 1.1 United Water alleges that Geo-Con failed to complete construction of the slurry wall as

1 The parties subsequently dismissed all claims against Geo-Solutions with prejudice. Docket No. 73, 80. 2 called for in the contract. Docket No. 3 at 7, ¶ 20. United Water further alleges that Geo-Con’s failure to key the slurry wall into bedrock means that the slurry wall project “never reached substantial completion.” Id., ¶ 27. United Water brings claims for relief against Geo-Con for (1) breach of contract, (2) promissory estoppel, and (3) unjust enrichment. Id. at 8-10, ¶¶ 32-53.

On October 3, 2019, Geo-Con filed this motion to dismiss. Docket No. 79. Geo- Con argues that United Water’s claims are barred by Colorado’s statute of repose. Id. at 12-13. Geo-Con also argues that the promissory estoppel and unjust enrichment claims fail because the subject matter of those claims is covered by the slurry wall contract. Id. at 13-15. United Water filed a response, Docket No. 86, and Geo-Con filed a reply. Docket No. 88. II. LEGAL STANDARD To survive a motion to dismiss under Rule 12(b)(6) of the Federal Rules of Civil Procedure, a complaint must allege enough factual matter that, taken as true, makes

the plaintiff’s “claim to relief . . . plausible on its face.” Khalik v. United Air Lines, 671 F.3d 1188, 1190 (10th Cir. 2012) (citing Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007)). “[W]here the well-pleaded facts do not permit the court to infer more than the mere possibility of misconduct, the complaint has alleged–but it has not shown–that the pleader is entitled to relief.” Ashcroft v. Iqbal, 556 U.S. 662, 679 (2009) (internal quotation marks and alteration marks omitted); see also Khalik, 671 F.3d at 1190 (“A plaintiff must nudge [his] claims across the line from conceivable to plausible in order to survive a motion to dismiss.” (quoting Twombly, 550 U.S. at 570)). If a complaint’s

3 allegations are “so general that they encompass a wide swath of conduct, much of it innocent,” then plaintiff has not stated a plausible claim. Khalik, 671 F.3d at 1191 (quotations omitted). Thus, even though modern rules of pleading are somewhat forgiving, “a complaint still must contain either direct or inferential allegations respecting all the material elements necessary to sustain a recovery under some viable legal

theory.” Bryson v. Gonzales, 534 F.3d 1282, 1286 (10th Cir. 2008) (alteration marks omitted ). III. ANALYSIS A. Statute of Repose Geo-Con moves to dismiss all of United Water’s claims as barred by the statute of repose in the Colorado Construction Defect Action Reform Act (“CDARA”), Colo. Rev. Stat. § 13-80-104(1)(a). Docket No. 79 at 12-13. “A statute of repose . . . puts an outer limit on the right to bring a civil action,” which is measured “from the date of the last culpable act or omission of the defendant.”

CTS Corp. v. Waldburger, 573 U.S. 1, 8 (2014). In this way, statutes of repose differ from statutes of limitations, which are based on the date when the claim accrued. Id. at 7. “Statutes of repose effect a legislative judgment that a defendant should be free from liability after the legislatively determined period of time.” Id. at 9 (quotation omitted). CDARA applies to “all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of construction of any improvement

4 to real property.” Colo. Rev. Stat. § 13-80-104(1)(a). CDARA contains both a statute of limitations and a statute of repose. The statute of limitations requires any action to be brought “within the time provided in [§ 13-80-102]” – generally speaking, two years – “after the claim for relief arises.” Id. A claim “arises” when a claimant “discovers or in the exercise of reasonable diligence should have discovered the physical

manifestations of a defect in the improvement which ultimately causes the injury.” Id. § 13-80-104(1)(b)(I). This is paired with a statute of repose, which states that “in no case shall such an action be brought more than six years after the substantial completion of the improvement to the real property.” Id. § 13-80-104(1)(a); see, e.g., Bush v. Roche Constructors, Inc., 817 P.2d 608, 610 (Colo. App. 1991) (describing this portion of CDARA as “the six-year statute of repose for actions against contractors”). If six years have passed from “substantial completion”2 of an improvement to real property, any claim that “arises” after that date relating to that improvement is barred under the statute of repose.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chickasaw Nation v. United States
534 U.S. 84 (Supreme Court, 2001)
Tellabs, Inc. v. Makor Issues & Rights, Ltd.
551 U.S. 308 (Supreme Court, 2007)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Utah Gospel Mission v. Salt Lake City Corp.
425 F.3d 1249 (Tenth Circuit, 2005)
Tal v. Hogan
453 F.3d 1244 (Tenth Circuit, 2006)
Bryson v. Gonzales
534 F.3d 1282 (Tenth Circuit, 2008)
Khalik v. United Air Lines
671 F.3d 1188 (Tenth Circuit, 2012)
Nelson v. Elway
908 P.2d 102 (Supreme Court of Colorado, 1995)
Bush v. Roche Constructors, Inc.
817 P.2d 608 (Colorado Court of Appeals, 1991)
Von Saher v. Norton Simon Museum of Art at Pasadena
592 F.3d 954 (Ninth Circuit, 2010)
CoMentis, Inc. v. Purdue Research Foundation
765 F. Supp. 2d 1092 (N.D. Indiana, 2011)
Robinson v. Colorado State Lottery Division
179 P.3d 998 (Supreme Court of Colorado, 2008)
Sierra Club v. Oklahoma Gas & Electric Co.
816 F.3d 666 (Tenth Circuit, 2016)
Sierra Pacific Industries, Inc. v. Bradbury
2016 COA 132 (Colorado Court of Appeals, 2016)
In re Goodman v. Heritage Builders
2017 CO 13 (Supreme Court of Colorado, 2017)
Wheat Ridge Urban Renewal Authority v. Cornerstone Group XXII, L.L.C.
176 P.3d 737 (Supreme Court of Colorado, 2007)
Clark v. Green Tree Servicing LLC
69 F. Supp. 3d 1203 (D. Colorado, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
United Water & Sanitation District v. Geo-Con, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-water-sanitation-district-v-geo-con-inc-cod-2020.