Thermo Development, Inc. v. Central Masonry Corp.

195 P.3d 1166, 2008 Colo. App. LEXIS 1414, 2008 WL 4330275
CourtColorado Court of Appeals
DecidedSeptember 18, 2008
Docket07CA1190
StatusPublished
Cited by15 cases

This text of 195 P.3d 1166 (Thermo Development, Inc. v. Central Masonry Corp.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thermo Development, Inc. v. Central Masonry Corp., 195 P.3d 1166, 2008 Colo. App. LEXIS 1414, 2008 WL 4330275 (Colo. Ct. App. 2008).

Opinion

*1167 Opinion by

Judge NIETO * .

Plaintiffs, Thermo Development, Inc., and Thermo Development Two, Inc., appeal the trial court's judgment in favor of defendants, Central Masonry Corporation and High Country Plastering, Inc. We affirm.

Plaintiffs were developers of a condominium complex in Denver. As a result of water intrusion, a condominium owner and the condominium association brought suit against plaintiffs. Plaintiffs settled that action and less than ninety days later brought this action against defendants seeking contribution and indemnity.

Defendants moved to dismiss this action as barred by the six-year statute of repose set forth in section 18-80-104(1)(a), C.R.S.2007. In response, plaintiffs argued that section 13-80-104(1)(b)(II)(B), C.R.$.2007, permitted them to file an action against defendants within ninety days of settling the underlying action regardless of the six-year statute of repose. Defendants countered by arguing that the ninety-day provision applied only to the statute of limitations, not to the statute of repose.

The trial court found that the ninety-day provision in section 13-80-104(1)(b)(II)(B) did not apply to the six-year statute of repose. Accordingly, it determined that plaintiffs' claims against defendants were barred. The trial court certified its order as final pursuant to C.R.C.P. 54(b) and plaintiffs then brought this appeal.

Plaintiffs contend that the trial court erred in finding that their claims were barred by the six-year statute of repose. We disagree.

The proper construction of section 13-80-104(1)(b)(I1), C.R.8.2007, is a question of law we review de novo. In construing a statute, our duty is to effectuate the intent and purpose of the General Assembly. We read the statute as a whole, giving sensible effect to all of its parts whenever possible. CLPF-Parkridge One, L.P. v. Harwell Invs., Inc., 105 P.3d 658, 660 (Colo.2005).

Section 18-80-104, C.R.S.2007, contains both a statute of limitations and a statute of repose that are applicable to suits against architects, contractors, builders or builder vendors, engineers, inspectors, and others involved in real property construction or improvements. See CLPF-Parkridge One, 105 P.3d at 661; Two Denver Highlands Ltd. Liab. Ltd. P'ship v. Stanley Structures, Inc., 12 P.3d 819, 821 (Colo.App.2000). It incorporates the two-year statute of limitations contained in section 18-80-102(1), C.R.S.2007, and provides a six-year statute of repose that may be extended by up to two years if the claim arises in the fifth or sixth year after substantial completion of the improvement. See § 18-80-104(1)(a), (1)(b)(D), (2), C.R.S. 2007.

Section 18-80-104(1) (a) provides:

Notwithstanding any statutory provision to the contrary, all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property shall be brought within the time provided in section 18-80-10% after the claim for relief arises, and not thereafter, but in mo case shall such an action be brought more than six years after the substantial completion of the improvement to the real property, except as provided in subsection (2) of this section.

(Emphasis added.)

Section 18-80-104 (1)(b), C.R.S.2007, in turn, provides in relevant part:

(I) Except as otherwise provided in sub-paragraph (II) of this paragraph (b), a claim for relief arises under this section at the time the claimant or the claimant's predecessor in interest discovers or in the exercise of reasonable diligence should have discovered the physical manifestations of a defect in the improvement which ultimately causes the injury.
(II) Notwithstanding the provisions of paragraph (a) of this subsection (1), all claims, including, but not limited to indemnity or contribution, by a claimant against *1168 a person who is or may be liable to the claimant for all or part of the claimant's liability to a third person:
(A) Arise at the time the third person's claim against the claimant is settled or at the time final judgment is entered on the third person's claim against the claimant, whichever comes first; and
(B) Shall be brought within ninety days after the claims arise, and not thereafter.

In CLPF-Parkridge One, 105 P.3d at 660, the supreme court held that "section 18-80-104(1)(b)(II) ... does not bar cross-claims and third-party claims for indemnity or contribution in construction defect lawsuits; rather, this section also allows indemnity or contribution claims to be brought by a separate lawsuit but no later than ninety days after termination of the construction defect lawsuit." However, in reaching this conclusion, the court did not address application of the six-year statute of repose.

Plaintiffs argue that the trial court erred in holding that section 18-80-104(1)(b)(IN) does not toll the six-year statute of repose. They contend that the trial court's interpretation of section 18-80-104(1)(b)(II) eviscerates the General Assembly's intent to preclude "shotgun-style" litigation where a contractor names all of the subcontractors regardless of liability to avoid the possible expiration of the statute of limitations or the statute of repose.

To properly understand a statute, we cannot read various words or phrases in isolation but must read them in context, and in a manner that gives effect to the entire statute. If the statutory language is unclear or susceptible of different interpretations, we examine the sources of legislative intent, including the objective of the legislation and the consequences of a particular construction. Fire Ins. Exch. v. Monty's Heating & Air Conditioning, 179 P.3d 43, 45 (Colo.App.2007) (construing various subsections of section 13-80-104); Rodriquez v. Nurseries, Inc., 815 P.2d 1006, 1008 (Colo.App.1991) ("In construing a statute, words, phrases, clauses, and sentences must be interpreted in connection with, and in relation to, the rest of the paragraph.").

We conclude that section 13-80-104(1)(b)(II) does not act as a "tolling" provision for the six-year statute of repose. The purpose of section

was to streamline construction defect litigation by allowing the addition of third-party subcontractors alleged to be responsible for the complained-of defect, and to defer the running of the statute of limitations on indemnity and contribution claims that construction professionals who are defendants in construction defect lawsuits might have against another person.

Fire Ins. Exch., 179 P.3d at 46.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lansford v. Poudre River
Colorado Court of Appeals, 2026
In re Goodman v. Heritage Builders
2017 CO 13 (Supreme Court of Colorado, 2017)
Sopris Lodging, LLC v. Schofield Excavation, Inc.
2016 COA 158 (Colorado Court of Appeals, 2016)
Sierra Pacific Industries, Inc. v. Bradbury
2016 COA 132 (Colorado Court of Appeals, 2016)
Lewis v. Taylor
2016 CO 48 (Supreme Court of Colorado, 2016)
In re the Marriage of Vittetoe
2016 COA 71 (Colorado Court of Appeals, 2016)
Williams v. Department of Public Safety, Colorado State Patrol
2015 COA 180 (Colorado Court of Appeals, 2015)
Williams v. Department of Public Safety
2015 COA 180 (Colorado Court of Appeals, 2015)
Independence Institute v. Gessler
869 F. Supp. 2d 1289 (D. Colorado, 2012)
Shaw Construction, LLC v. United Builder Services, Inc.
2012 COA 24 (Colorado Court of Appeals, 2012)
United Fire Group v. Powers Electric, Inc.
240 P.3d 569 (Colorado Court of Appeals, 2010)
Smith v. Executive Custom Homes, Inc.
209 P.3d 1175 (Colorado Court of Appeals, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
195 P.3d 1166, 2008 Colo. App. LEXIS 1414, 2008 WL 4330275, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thermo-development-inc-v-central-masonry-corp-coloctapp-2008.