Sopris Lodging, LLC v. Schofield Excavation, Inc.

2016 COA 158, 409 P.3d 597, 2016 Colo. App. LEXIS 1490
CourtColorado Court of Appeals
DecidedOctober 20, 2016
DocketCourt of Appeals 15CA1959
StatusPublished
Cited by2 cases

This text of 2016 COA 158 (Sopris Lodging, LLC v. Schofield Excavation, Inc.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sopris Lodging, LLC v. Schofield Excavation, Inc., 2016 COA 158, 409 P.3d 597, 2016 Colo. App. LEXIS 1490 (Colo. Ct. App. 2016).

Opinion

Opinion by

JUDGE RICHMAN

¶ 1 In this construction defect case, Sopris Lodging, LLC, assignee of the claims of third-party plaintiffs TDC/BEI Joint Venture, LLC (TDC), Charles R. Lakin, and Tyler Casebier, appeals the district court’s entry of summary judgment in favor of third-party defendants, Schofield Excavation, Inc. (Schofield), and Colorado Engineering Contractors, Inc. (CEC). Because we conclude that the third-party claims at issue are time barred, we affirm.

*599 I. Background

¶ 2 TDC was the general contractor for the construction of a hotel owned by Sopris Lodging. On March 11, 2011, Sopris Lodging sent TDC a notice of claim regarding alleged construction defects at the hotel. On May 24, 2013, Sopris Lodging filed a complaint in district court asserting construction defect claims against one of the subcontractors of the hotel, and against the TDC’s individual principals, Latón and Casebier, who had guaranteed TDC’s performance. On the same date, however, Sopris Lodging and TDC entered into an agreement to toll the statute of limitations for Sopris Lodging’s claims against TDC. Sopris Lodging later amended its complaint in August of 2013 to add claims against TDC. 1

¶ 3 In 2014, while those claims were pending, TDC filed third-party claims against several subcontractors, including Schofield and CEC, for breach of contract, negligence, contribution, and indemnification. CEC and Schofield moved for summary judgment, asserting that TDC’s third-party claims were barred by the two-year statute of limitations set forth in section 13-80-102, C.R.S. 2016, and made applicable to TDC’s claims through section 13-80-104(l)(a), C.R.S. 2016. CEC and Schofield argued that those claims accrued on or before March 11, 2011, when Sopris Lodging sent the notice of claim to TDC. Because TDC did not file its third-party claims until 2014, CEC and Schofield asserted that the claims were time barred.

¶ 4 In its response, TDC did not dispute the date of accrual. However, it asserted that section 13 — 80—104(l)(b)(II) tolled the statute of limitations for a defendant’s third-party claims until ninety days after a settlement or final judgment on the plaintiffs’ claims against the defendant.

¶ 6 After briefing, the district court entered a detailed written order ruling that the third-party claims were time barred. Relying on CLPF-Parkridge One, L.P. v. Harwell Investments, Inc., 106 P.3d 658 (Colo. 2006), the court concluded that section 13-80-104(1)(b)(II) did not apply to TDC’s third-party claims and that those claims were barred by the limitations period in section 13-80-104(1)(a). Accordingly, the court entered summary judgment in favor of CEC and Schofield.

¶ 6 Thereafter, Sopris Lodging and TDC reached a settlement agreement. TDC assigned its third-party claims to Sopris Lodging, and Sopris Lodging, standing in the shoes of TDC, filed this appeal.

II. Discussion

¶ 7 Sopris Lodging contends that the court misapplied section 13-80-104 in ruling that the third-party claims of TDC were time barred. We disagree.

A. Standard of Review

¶ 8 We review a trial court’s order on a summary judgment motion de novo. Gibbons v. Ludlow, 2013 CO 49, ¶ 11, 304 P.3d 239. Summary judgment is appropriate when the pleadings and supporting documents establish that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law. Id.

¶ 9 Statutory interpretation is a question of law that we review de novo. Klinger v. Adams Cty. Sch. Dist. No. 50, 130 P.3d 1027, 1031 (Colo. 2006). Our task is to give effect to the intent of the General Assembly. Id. To do so, we look first to the language of the statute. Id. We construe words and phrases according to their commonly accepted and understood meanings. A.S. v. People, 2013 CO 63, ¶ 10, 312 P.3d 168. Where the language is clear and unambiguous, we do not resort to other rules of statutory construction. Klinger, 130 P.3d at 1031.

B. Applicable Law

¶ 10 Section 13-80-104(l)(a) provides that the two-year statute of limitations set forth in section 13-80-102(1) applies to construction defect claims:

Notwithstanding any statutory provision to the contrary, all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, *600 inspection, construction, or observation of construction of any improvement to real property shall be brought within the time provided in section 13-80-102 after the claim for relief arises, and not thereafter, but in no case shall süch. an action be brought more than six years after the substantial completion of the improvement to the real property, except as provided in subsection (2) of this section.

¶ 11 Section 13 — 80—104(l)(b) provides:

(I) Except as otherwise provided in sub-paragraph (II) of this paragraph (b), a claim for relief arises under this section at the time the claimant or the claimant’s predecessor in interest discovers or in the exercise of reasonable diligence should have discovered the physical manifestations of a defect in the improvement which ultimately causes the injury.
(II) Notwithstanding the provisions of paragraph (a) of this subsection (1),- all claims, including, but not limited to indemnity or contribution, by a claimant against a person who is or may be liable to the claimant for all or part of the claimant’s liability to a third person:
(A) Alise at the time the third person’s claim against the claimant is settled or at the time final judgment is entered on the third person’s claim against the claimant, whichever comes first; and
(B) Shall be brought within ninety days, after the claims arise, and not thereafter.

¶ 12 In CLPF-Parkridge One, the supreme court held that section 13-80-104(1)(b)(II) does not bar a defendant contractor from asserting third-party claims for indemnity or contribution against subcontractors before the resolution of the underlying construction defect claims. 105 P.3d at 663-65. The court concluded that section 13-80-104(1)(b)(II) is not a ripeness provision but instead “toll[s] the otherwise applicable statute of limitations in order to allow indemnity or contribution claims to be brought in a separate lawsuit ... within ninety days after settlement of or judgment in the construction defect lawsuit.” Id. at'665. Thus, a defendant in a construction defect lawsuit may either (1)-bring appropriate cross-claims or third-party claims in the same lawsuit or (2) wait to file a separate suit within the ninety-day period after a settlement or judgment in the construction defect lawsuit in accordance with section 13-80~104(l)(b)(II). Id. at 664-65,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

v. Zag Built LLC —
2018 COA 66 (Colorado Court of Appeals, 2018)
T.D. v. Wiseman
2017 COA 111 (Colorado Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2016 COA 158, 409 P.3d 597, 2016 Colo. App. LEXIS 1490, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sopris-lodging-llc-v-schofield-excavation-inc-coloctapp-2016.