Industrial Risk Insurers v. the Rust Engineering Co.

232 Cal. App. 3d 1038, 283 Cal. Rptr. 873, 91 Cal. Daily Op. Serv. 6004, 91 Daily Journal DAR 9256, 1991 Cal. App. LEXIS 872
CourtCalifornia Court of Appeal
DecidedJuly 29, 1991
DocketA051674
StatusPublished
Cited by17 cases

This text of 232 Cal. App. 3d 1038 (Industrial Risk Insurers v. the Rust Engineering Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Industrial Risk Insurers v. the Rust Engineering Co., 232 Cal. App. 3d 1038, 283 Cal. Rptr. 873, 91 Cal. Daily Op. Serv. 6004, 91 Daily Journal DAR 9256, 1991 Cal. App. LEXIS 872 (Cal. Ct. App. 1991).

Opinion

Opinion

PERLEY, J.

—In this case we hold that the 10-year time limit Code of Civil Procedure section 337.15 places on suits for latent defects in improvements to real property commences when the defendant’s work on the improvement is substantially completed, rather than when the improvement itself is substantially completed. The trial court here granted the motion of respondent, The Rust Engineering Company, for summary judgment under section 337.15, finding that the $20 million damage claim of appellant, Industrial Risk Insurers, was time barred and that there was no triable issue of fact to the contrary. We affirm the judgment entered in favor of respondent.

I.

A 400-ton boiler at Louisiana Pacific Fiberboard Corporation’s paper mill in Antioch, California, exploded on July 5, 1987, killing 3 people, wounding several others and causing extensive property damage. Appellant, Fiberboard’s property and business interruption insurer, filed suit against respondent on December 24, 1987, to recover amounts paid under its policy on account of the explosion. The complaint alleged that the explosion was caused by failure of the rapid drain system respondent designed for the boiler, and that respondent was liable for the resulting damages under theories of strict liability, negligence or breach of warranty. Judgment was entered for respondent on the ground that it had substantially completed its *1041 services in connection with the rapid drain system by December 24,1977, 10 years before the filing of the complaint.

There is no dispute on appeal that the rapid drain system was an “improvement” to real property within the meaning of Code of Civil Procedure section 337.15. 1 The issue is whether this statute’s 10-year time frame for suits for latent defects commenced when the system itself was substantially completed, or earlier, when respondent’s work on the system was substantially completed. In the published portion of our discussion, we will explain why we conclude that the limitations period began with the substantial completion of respondent’s services. In the unpublished portion, we will address the evidence presented in connection with the motion for summary judgment, which established that virtually all of respondent’s services with respect to the rapid drain system were furnished more than 10 years prior to the filing of the complaint.

II.

We are called upon to construe subdivisions (a) and (g) of Code of Civil procedure section 337.15, which read as follows: “(a) No action may be brought to recover damages from any person, or the surety of a person, who develops real property or performs or furnishes the design, specifications, surveying, planning, supervision, testing, or observation of construction or construction of an improvement to real property more than 10 years after the substantial completion of the development or improvement for any of the following: [ft (1) Any latent deficiency in the design, specification, surveying, planning, supervision, or observation of construction or construction of an improvement to, or survey of, real property, [ft (2) Injury to property, real or personal, arising out of any such latent deficiency. . . . [ft (g) The 10-year period specified in subdivision (a) shall commence upon substantial completion of the improvement, but not later than the date of one of the following, whichever first occurs: [ft (1) The date of final inspection by the applicable public agency, [ft (2) The date of recordation of a valid notice of completion, [ft (3) The date of use or occupation of the improvement, [ft (4) One year after termination or cessation of work on the improvement, [ft The date of substantial completion shall relate specifically to the performance or furnishing [sic] design, specifications, surveying, planning, supervision, testing, observation of construction or construction services by each profession *1042 or trade, rendering services to the improvement.” (§ 337.15, subds. (a), (g) [italics added].)

A statute should be interpreted so as to effectuate its apparent purpose. (Delaney v. Superior Court (1990) 50 Cal.3d 785, 798 [268 Cal.Rptr. 753, 789 P.2d 934]; Moyer v. Workmen’s Comp. Appeals Bd. (1973) 10 Cal.3d 222, 252 [110 Cal.Rptr. 144, 514 P.2d 1224].) The legislative purpose is determined in the first instance by the language used in the statute. (Brown v. Kelly Broadcasting Co. (1989) 48 Cal.3d 711, 724 [257 Cal.Rptr. 708, 771 P.2d 406].) “If the language is clear and unambiguous there is no need for construction, nor is it necessary to resort to indicia of the intent of the Legislature.” (Lungren v. Deukmejian (1988) 45 Cal.3d 727, 735 [248 Cal.Rptr. 115, 755 P.2d 299] [describing the “plain meaning” rule].) The language we have highlighted in the last sentence of Code of Civil Procedure section 337.15, subdivision (g) “relates” the concept of substantial completion to services rendered to an improvement, and it relates this concept “specifically” to the services rendered by “each” profession. It is somewhat imprecise to say that things are related without saying how they are related. But the reasonably plain meaning of this sentence is that the limitations period commences as to each profession on the date its services to the improvement are substantially complete.

Appellant offers no alternative construction of the words used in the last sentence of Code of Civil Procedure section 337.15, subdivision (g). Appellant maintains, however, that the sentence “cannot be read to eliminate” the references to “substantial completion of the improvement” in the first sentences of Code of Civil Procedure section 337.15, subdivisions (a) and (g). Appellant also suggests that our interpretation of the last sentence of subdivision (g) effectively negates subdivision (g)(4), which states that the limitations period cannot commence any later than one year “after termination or cessation of work on the improvement.” Appellant reasons that subdivision (g)(4) will never come into play if the limitations period is triggered by the substantial completion of services.

“[Statutory sections relating to the same subject must be harmonized, both internally and with each other, to the extent possible.” (Dyna- Med, Inc. v. Fair Employment & Housing Com. (1987) 43 Cal.3d 1379, 1387 [241 Cal.Rptr. 57, 743 P.2d 1323].) The last sentence of Code of Civil Procedure section 337.15, subdivision (g) is not necessarily inconsistent with subdivision (g)(4). The latter provision ensures that the limitations period will begin to run at some fixed point after work on an improvement stops, even if some portion of the work is not substantially complete.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hensel Phelps Construction Co. v. Super. Ct.
California Court of Appeal, 2020
People v. McGowan
242 Cal. App. 4th 377 (California Court of Appeal, 2015)
Horning v. Penrose Plumbing & Heating Inc.
2014 WY 133 (Wyoming Supreme Court, 2014)
JHP LLC v. Japp CA1/5
California Court of Appeal, 2013
Du v. Hawkins CA2/3
California Court of Appeal, 2013
Mussetter Distributing, Inc. v. Dbi Beverage Inc.
685 F. Supp. 2d 1028 (N.D. California, 2010)
Maita Distributors, Inc. of San Mateo v. DBI Beverage Inc.
667 F. Supp. 2d 1140 (N.D. California, 2009)
Mills v. Forestex Co.
134 Cal. Rptr. 2d 273 (California Court of Appeal, 2003)
Ocean Winds Corp. v. Lane
556 S.E.2d 377 (Supreme Court of South Carolina, 2001)
FNB Mortgage Corp. v. Pacific General Group
90 Cal. Rptr. 2d 841 (California Court of Appeal, 1999)
CYBERMEDIA, INC. v. Superior Court
82 Cal. Rptr. 2d 126 (California Court of Appeal, 1999)
Kotler v. Alma Lodge
63 Cal. App. 4th 1381 (California Court of Appeal, 1998)
Nelson v. Gorian & Associates, Inc.
61 Cal. App. 4th 93 (California Court of Appeal, 1998)
Gordon v. Western Steel Co.
950 S.W.2d 743 (Court of Appeals of Texas, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
232 Cal. App. 3d 1038, 283 Cal. Rptr. 873, 91 Cal. Daily Op. Serv. 6004, 91 Daily Journal DAR 9256, 1991 Cal. App. LEXIS 872, Counsel Stack Legal Research, https://law.counselstack.com/opinion/industrial-risk-insurers-v-the-rust-engineering-co-calctapp-1991.