Nova group/tutor-saliba v. United States

127 Fed. Cl. 591, 2016 U.S. Claims LEXIS 1007, 2016 WL 4009886
United States Court of Federal Claims·Decided July 22, 2016·No. 15-885C·Published·Cited by 1 cases

Opinion

Contract Disputes Act, 41 U.S.C. § 7101 et seq; Transfer; Time Limit for Appealing Contracting Officer’s Decision; Time-Barred Appeal; Waiver of Sovereign Immunity.

OPINION AND ORDER DENYING PLAINTIFF’S MOTION TO TRANSFER

WILLIAMS, Judge.

On May 31, 2016, Plaintiff filed an unopposed motion to transfer the above-captioned case to the Armed Services Board of Contract Appeals (“ASBCA”) pursuant to 41 U.S.C. § 7107(d). Plaintiff represents that it presently has an appeal pending before the ASBCA arising under the same contract at issue in this action. Because the claim pending in this Court would be time-barred at the ASBCA and the claim pending in this Court involves wholly different facts than the ASBCA claim, Plaintiffs motion to transfer is denied.

Background

On May 2, 2008, the Naval Facilities Engineering Command (“NAVFAC”), awarded Contract No. N44255-08-CT6000 for the design and construction of a ship repair wharf (“Pier B”) at the Puget Sound Navy Shipyard in Bremerton, Washington to Plaintiff, Nova Group/Tutor-Saliba. Nova Group/Tutor-Saliba v. United States, 125 Fed.Cl. 469, 470 (2016). Although NAVFAC approved Plaintiffs design submissions on November 12, 2009, the project’s construction manager later questioned Plaintiffs design on March 8, 2010. Id. In response to the construction manager’s letter raising this design issue, Plaintiff stopped construction and began a re-evaluation of the design, which lasted from March 8 until May 27, 2010. Id. at 471. As part of this re-evaluation, Plaintiffs architect-engineer and designer of record, KPFF Consulting (“KPFF”), hired an independent third-party designer, Ben C. Gerwick, Inc. (“Gerwick”), to analyze KPFF’s original design. Id. Gerwick concluded that KPFF’s design complied with the requirements of the contract and that KPFF had chosen an appropriate design method. Id. Plaintiff resumed construction on May 27, 2010. Id. Upon resuming construction, Plaintiff accelerated the remaining work, increasing manpower, equipment, and overtime. Id. •

Two Requests for Equitable Adjustment (“REA”) are implicated in the instant motion — REAs 9 and 14. In REA 14, the subject of the suit in this Court, Plaintiff seeks compensation for the work stoppage and acceleration stemming from the design re-evaluation in 2010. Plaintiff stated:

The Government issued Serial No. 0106, dated March 8, 2010 advising of Berger *593 ABAM’s concerns that the final approved design may not be in conformance with the RFP.... The concern that the design was not in conformance with the RFP required all work on Pier B to be stopped until these issues were resolved. This delay impacted all Pier B work for several months and has required NTS to accelerate the falsework operation to mitigate the delay to the construction schedule.

Compl. Ex. 3, at 3.

In REA 9, the subject of the appeal before the ASBCA, Plaintiff raises a differing site condition claim, stating:

REA #9 was assigned to differentiate the pile driving [Differing Site Condition] and related issues between the Mole, REA #5 and Pier B. After completion of the pile driving at the Mole Quay-wall, [American Civil Contractors], our pile driving subcontractor moved to the adjacent Pier B footprint and experienced the same or similar pile related problems at Pier B that it experienced at the Mole structure including inability to drive to design tip elevation and alignment issues, all caused by unknown subsurface conditions. Our design engineer attempted to mitigate the issue by modifying the driving criteria, just as Berger/ABAM did at the Mole. In both cases the criteria did not mitigate the uneven and variable elevations that would typically have been identified by the Indicator Pile Program. The extra scope of work includes the same elements as REA #5 but also includes additional scope including: engineering review and design changes, falsework modifications for bump-outs, reinforcing detailing and material changes, installation of 29 additional piles and CIP crossbeams. This work is ongoing and all associated cost and schedule impacts are being compiled for inclusion into the REA.

Id. at 2. The contracting officer issued a final decision denying REA 14 on September 4, 2014, and a final decision denying REA 9 on August 12, 2015. PL’s Mot. 3-4.

Plaintiff filed its complaint in this Court on August 17, 2015, appealing the contracting officer’s final decision denying REA 14. On October 16, 2015, Defendant filed a motion to dismiss Plaintiffs complaint for failure to state a claim upon which relief could be granted, arguing that Plaintiff failed to give timely written notice of -its claim for constructive changes. The Court denied Defendant’s motion on March 16, 2016, finding that Plaintiffs failure to timely provide written notice did not require dismissal of its complaint, as Plaintiff plausibly alleged that Defendant had actual knowledge of Plaintiffs work stoppage and acceleration. Nova Group, 125 Fed.Cl. at 474, In the meantime, on November 4, 2015, Plaintiff appealed the contracting officer’s denial of REA 9 to the ASBCA.

On April 6, 2016, Defendant filed an unopposed motion to stay this action solely based on Plaintiffs representation that it was considering requesting a transfer to the ASBCA. On April 15, 2016, Plaintiff filed a status report indicating that it was still assessing whether to file a motion to transfer. On May 31, 2016, Plaintiff filed the instant motion to transfer, representing that Defendant did not oppose a transfer.

Discussion

.Plaintiff seeks to transfer the instant case to the ASBCA, or, in the alternative, to transfer.the case currently pending before -the ASBCA to this Court.

Plaintiff avers that because it did not timely file an appeal regarding REA 14 with the Board, the ASBCA would not have jurisdiction over that appeal. 1 Pl.’s Mot. 6-7 (“NTS had the right to but did not timely file a Notice of Appeal with the ASBCA after receiving the CO’s final decision denying NTS’s claim on REA 14. As such, the Board cannot now exercise jurisdiction over a direct appeal *594 since NTS failed to file an appeal within 90 days of the CO’s decision.”) (internal citations omitted). Nonetheless, Plaintiff argues that this Court can bestow “derivative jurisdiction” upon the ASBCA via a transfer, invoking Section 7107(d) of the Contract Disputes Act (“CDA”). That provision states:

If 2 or more actions arising from one contract are filed in the United States Court of Federal Claims and one or more agency boards, for the convenience of the parties or witnesses or in the interest of justice, the United States Court of Federal Claims may order the consolidation of the actions in that court or transfer any actions to or among the agency boards involved.

Free access — add to your briefcase to read the full text and ask questions with AI

Nova group/tutor-saliba v. United States, 127 Fed. Cl. 591, 2016 U.S. Claims LEXIS 1007, 2016 WL 4009886 (uscfc 2016).

127 Fed. Cl. 591 (Nova group/tutor-saliba v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related