Gilbane Federal v. United States

CourtUnited States Court of Federal Claims
DecidedJune 17, 2026
Docket25-1265
StatusPublished

This text of Gilbane Federal v. United States (Gilbane Federal v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gilbane Federal v. United States, (uscfc 2026).

Opinion

In the United States Court of Federal Claims GILBANE FEDERAL,

Plaintiff, No. 25-1265 v. Filed: June 17, 2026 THE UNITED STATES,

Defendant.

Michael A. Branca of Peckar & Abramson, P.C., Washington, D.C., argued for Plaintiff.

Ioana C. Meyer of the United States Department of Justice, Civil Division, Washington, D.C., argued for Defendant. With her on the briefs were Brett A. Shumate, Patricia M. McCarthy, and Steven Michael Mager, of the United States Department of Justice, Civil Division, Washington, D.C.

MEMORANDUM AND ORDER

In June of 2020, only a few months after the President of the United States had declared

the COVID-19 pandemic an emergency, Plaintiff Gilbane Federal (Gilbane or Plaintiff) entered

into Contract No. W912HN-20-C-3006 (Contract) with the Army Corps of Engineers (Corps) for

the construction of a government facility located at Fort Gordon, Georgia. When disputes arose

under this Contract, and after the Corps denied two of its certified claims, Gilbane appealed to

separate venues: one appeal to this Court, and one appeal to the Armed Services Board of Contract

Appeals (ASBCA).

The first dispute arose when Gilbane submitted a certified claim to the contracting officer

(CO) on May 26, 2022, requesting compensation and a schedule extension. The claim was

partially settled, but the CO denied certain contract modification preparation costs, which Gilbane appealed to the ASBCA on September 19, 2023. The second dispute arose after Gilbane

encountered delays allegedly caused by labor shortages, worker illnesses, and similar labor

difficulties due to the COVID-19 pandemic. On June 7, 2024, Gilbane submitted a second certified

claim to the CO seeking 61 days of excusable, non-compensable delay to the Contract completion

date, in addition to contract preparation costs. The CO denied Gilbane’s second certified claim on

August 6, 2024, and on July 31, 2025, Gilbane filed suit in this Court under the Contract Disputes

Act (CDA) to appeal the second denial. Gilbane seeks two forms of relief in this Court: (1) sixty-

one days of excusable, non-compensable delay and (2) the reimbursement of $30,537.67 in

administrative costs related to proposal preparation and modification and claim preparation.

On January 9, 2026, Defendant the United States filed a Motion to Transfer and Stay

Proceedings, seeking to transfer this action to the ASBCA pursuant to 41 U.S.C. § 7107(d), which

permits the Court of Federal Claims to transfer cases to agency boards. Defendant contends that

this Court should transfer the present action because, among other reasons, the proceedings at the

ASBCA arose out of the same Contract and concern an overlapping issue. Plaintiff opposes the

Motion to Transfer.

As articulated below, this Court has broad discretion when considering a Motion to

Transfer under 41 U.S.C. § 7107(d). In examining the present case, all of the factors favor transfer

of the action to the ASBCA. Accordingly, this Court GRANTS Defendant’s Motion to Transfer

and Stay Proceedings (ECF No. 12).

2 STATEMENT OF FACTS 1

I. The Contract

On May 31, 2019, the Corps issued Solicitation No. W912HN-19-R-3004 for the

construction of a new “Cyber Instructional Facility and Network Center” at Fort Gordon, Georgia.

ECF No. 1 (Complaint) ¶ 5. Plaintiff, a “full-service general contractor,” submitted its final

proposal for the facility on September 13, 2019. Id. ¶¶ 2, 7. On March 13, 2020, the President of

the United States declared a national emergency related to the COVID-19 pandemic. Id. ¶ 9. On

June 19, 2020 (280 days after Gilbane submitted its final proposal), the Corps awarded Gilbane

firm-fixed-price Contract No. W912HN-20-C-3006 that covered construction of the facility in

exchange for $96,903,333. Id. ¶ 8.

Plaintiff claims that the COVID-19 emergency negatively “impacted” its work and the

work of its subcontractors. Id. ¶ 13. The impacts included an “[o]verall lack of labor resources,”

a concrete subcontractor’s “inability to find qualified manpower in the local area,” a “[s]maller

pool of crew and supervision that were qualified to access Fort Gordon,” and “[i]ndividual worker

illnesses caused by COVID-19.” Id.

On October 15, 2021, Plaintiff indicated in a monthly schedule update that the project had

fallen 31 days behind schedule. Id. ¶ 15. On October 25, 2021, the Corps issued a Letter of

Concern regarding schedule delays. Id. ¶ 16. Plaintiff and its subcontractors took several measures

to address the delays, including overtime work, higher wages, and “out of area recruitment.” Id.

¶ 18. On January 12, 2022, the Corps issued Request for Proposal (RFP) 0027, which addressed

1 The Court accepts the facts in the Complaint as true for the purpose of resolving the Motion. See Rockwell Automation, Inc. v. United States, 70 Fed. Cl. 114, 116 n.2 (2006); see also ECF No. 12 (Motion to Transfer or Mot.) at 5 n.2 (“For this statement of facts, we rely on the allegations in Gilbane’s complaint, [and] exhibits to its complaint . . . . We respectfully reserve the right to challenge any of the facts alleged by Gilbane in the future, should this motion be denied.”). 3 project delays due to COVID-19, and subsequently agreed to extend the completion period to

January 20, 2022. Id. ¶ 20.

Despite mitigation efforts that Plaintiff allegedly undertook, delays mounted, and Plaintiff

requested 69 days of excusable, non-compensable delay on February 14, 2022. Id. ¶ 21. Plaintiff

also requested $21,645.00 “for proposal preparation costs, which included time incurred by

Gilbane’s Project Executive and Project Controls-Scheduler.” Id. The Corps denied that request

as lacking merit on February 22, 2022; Plaintiff then provided supplemental material to support its

submission. Id. ¶¶ 22, 23. On April 27, 2022, the Corps issued Unilateral Modification

A000018/R00021, which granted Gilbane eight days of excusable, non-compensable delay for

delays that accrued through January 20, 2022. Id. ¶ 26.

In response, Plaintiff indicated that it intended to submit a Request for Equitable

Adjustment (REA). Id. ¶ 27. Plaintiff submitted its REA on March 11, 2024, seeking 61 days of

excusable non-compensable delay. Id. ¶ 29. Plaintiff calculated the 61-day figure by subtracting

the eight days granted by the Government from the 69 days that Plaintiff had earlier requested. Id.

¶ 29. The Corps denied the REA on March 29, 2024. Id. ¶ 30.

II. Plaintiff’s Court of Federal Claims Suit

On June 7, 2024, Plaintiff filed a Certified Claim with the CO that sought relief on the same

grounds as the denied REA. Id. ¶ 31; see ECF No. 1-2 (Certified Claim) at 2. In its Certified

Claim, Plaintiff sought 61 “calendar days of excusable, non-compensable extension” and

$30,537.67 for REA preparation costs. Certified Claim at 2. On August 6, 2024, the CO denied

Plaintiff’s Certified Claim, finding “no merit” in either the sixty-one-day schedule extension or

the claim for $30,537.67 in costs. ECF 12-1 (Defendant’s Appendix or Appendix) at 2 (emphasis

in original). With respect to the claim for 61 days of excusable, non-compensable delay, the CO

4 found that Plaintiff “did not show that the days it request[ed] were excusable and attributable to

COVID-19.” App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Utah Construction & Mining Co.
384 U.S. 394 (Supreme Court, 1966)
Crowley v. United States
398 F.3d 1329 (Federal Circuit, 2005)
Larry E. Graybill v. United States Postal Service
782 F.2d 1567 (Federal Circuit, 1986)
John R. Glenn v. The United States
858 F.2d 1577 (Federal Circuit, 1988)
Nova group/tutor-saliba v. United States
127 Fed. Cl. 591 (Federal Claims, 2016)
Avant Assessment, LLC v. United States
134 Fed. Cl. 323 (Federal Claims, 2017)
E.D.S. Federal Corp. v. United States
30 Cont. Cas. Fed. 70,659 (Court of Claims, 1983)
Precision Pine & Timber, Inc. v. United States
45 Fed. Cl. 134 (Federal Claims, 1999)
Morse Diesel International, Inc. v. United States
66 Fed. Cl. 801 (Federal Claims, 2005)
Rockwell Automation, Inc. v. United States
70 Fed. Cl. 114 (Federal Claims, 2006)
Northrop Grumman Corp. v. United States
70 Fed. Cl. 230 (Federal Claims, 2006)
Ch2m Hill Hanford Group, Inc. v. United States
82 Fed. Cl. 139 (Federal Claims, 2008)
Multi-Roof Systems Co. v. United States
32 Cont. Cas. Fed. 72,530 (Court of Claims, 1984)
Giuliani Contracting Co. v. United States
36 Cont. Cas. Fed. 75,882 (Court of Claims, 1990)
Kroy Ip Holdings, LLC v. Groupon, Inc.
127 F.4th 1376 (Federal Circuit, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
Gilbane Federal v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gilbane-federal-v-united-states-uscfc-2026.