Myrex Industries, Inc. v. Ortolon

126 S.W.3d 548, 2003 WL 22707422
CourtCourt of Appeals of Texas
DecidedFebruary 26, 2004
Docket14-02-01129-CV
StatusPublished
Cited by26 cases

This text of 126 S.W.3d 548 (Myrex Industries, Inc. v. Ortolon) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Myrex Industries, Inc. v. Ortolon, 126 S.W.3d 548, 2003 WL 22707422 (Tex. Ct. App. 2004).

Opinion

OPINION

CHARLES W. SEYMORE, Justice.

Appellant, Myrex Industries, Inc., appeals a judgment in favor of appellee, David Ortolon, on his quantum meruit claim to recover commissions allegedly earned while employed by Myrex. Myrex contends that Ortolon (1) is precluded from presenting a quantum meruit claim; (2) failed to prove all elements of his claim; (3) used an incorrect measure of damages; and (4) the damages awarded are excessive. We reverse and render.

I. BACKGROUND

Myrex is a steel fabricator for various industries. Myrex hired Ortolon as an estimator in November 1998. Ortolon’s duties included selling projects by estimating the costs involved and preparing bid proposals for customers. He also had duties after he sold a project including managing the project, interacting with the customer, writing purchase orders, and addressing change orders. Ortolon was paid a salary, plus commissions under Myrex’s “incentive bonus plan.” Under this plan, an estimator is paid a commission of five percent of the net profit on the projects he sells. However, an estimator is not paid the commission until a project closes. A project closes when Myrex collects final payment from the customer and makes adjustments for job costs. Further, if an estimator’s projects that close within a quarter maintain a certain profit margin, he is paid an additional five percent.

Ortolon resigned from Myrex in March 2001. At that time, he had been paid commissions for his projects that had closed. However, there were certain projects he had sold that had not yet closed. Despite his demand, Myrex refused to pay him commissions on these projects. My-rex asserted it does not pay commissions on projects that close after an estimator leaves the company.

Ortolon sued Myrex for breach of contract and, alternatively, quantum meruit. The jury found in Myrex’s favor on the breach of contract claim because it found no agreement that Myrex would pay Orto-lon commissions for projects that closed after his resignation. 1 However, the jury returned a verdict for Ortolon on his quantum meruit claim and awarded him $64,631.93. The trial court entered judgment for Ortolon in the amount of $64,631.93 plus prejudgment interest, court costs, and postjudgment interest. This appeal followed.

II. Analysis

Myrex presents three issues for review. In subpart (c) of its first issue, Myrex contends Ortolon is not entitled to recover in quantum meruit because he failed to prove all elements of a quantum meruit claim. We will address this contention first because it is dispositive of this appeal. 2

*550 Quantum meruit is an equitable remedy based upon an implied promise to pay for benefits received. Heldenfels Bros., Inc. v. City of Corpus Christi, 832 S.W.2d 39, 41 (Tex.1992). To recover in quantum meruit, a claimant must prove (1) valuable services were rendered or materials furnished; (2) for the person sought to be charged; (3) which services and materials were accepted by the person sought to be charged; (4) under such circumstances as reasonably notified the person sought to be charged that the plaintiff in performing such services was expecting to be paid by the person sought to be charged. Id.

Myrex contends Ortolon’s work on the disputed projects was not accepted by Myrex under such circumstances that reasonably notified Myrex that Ortolon was expecting to be paid commissions. Specifically, Myrex attacks the legal and factual sufficiency of the evidence supporting the jury’s “yes” answer to the following question:

Question 11
Did Ortolon perform compensable work for Myrex for which Ortolon was not paid?
You are instructed when answering this question that — •
One party performs compensable work if valuable services are rendered or materials furnished for another party who knowingly accepts and uses them and if the party accepting them should know that the performing party expects to be paid for the work. 3

When a party challenges the legal sufficiency of the evidence supporting an adverse finding on an issue on which it does not have the burden of proof, that party must demonstrate on appeal that there is no evidence to support the adverse finding. Price Pfister, Inc. v. Moore & Kimmey, Inc., 48 S.W.3d 341, 347 (Tex.App.-Houston [14th Dist.] 2001, pet. denied) (citing Croucher v. Croucher, 660 S.W.2d 55, 58 (Tex.1983)). We consider all the evidence in the light most favorable to the jury’s verdict, indulging every reasonable inference in favor of the prevailing party. Id. (citing Associated Indem. Corp. v. CAT Contracting, Inc., 964 S.W.2d 276, 285-86 (Tex.1998)). We will sustain a legal insufficiency point when (a) there is a complete absence of evidence of a vital fact; (b) the court is barred by rules of law or of evidence from giving weight to the only evidence offered to prove a vital fact; (c) the evidence offered to prove a vital fact is no more than a mere scintilla; or (d) the evidence conclusively establishes *551 the opposite of a vital fact. Id. (citing Merrell Dow Pharms., Inc. v. Havner, 953 S.W.2d 706, 711 (Tex.1997)).

When Ortolon tendered his resignation, he told his supervisor, Kelli Boze, he expected to be paid commissions for his projects that had not yet closed. Ortolon later sent a letter to Jim Moffa, Myrex’s president, demanding payment for these projects. Ortolon concedes these demands are the only evidence that Myrex knew Ortolon expected to be paid commissions for the disputed projects. However, demands at the time of, and after, his resignation do not satisfy the “notice” element of quantum meruit.

The “notice” element focuses on what the recipient of the services knew or should have known at the time the services were accepted. The claimant must prove the services “were accepted by the person sought to be charged ... under such circumstances as reasonably notified the person ... that the plaintiff in performing such services was expecting to be paid.” Heldenfels, 832 S.W.2d at 41 (emphasis added). 4 Our review of the record reveals a complete absence of evidence that Myrex knew or should have known at the time Ortolon sold the disputed projects that he expected to be paid commissions even if the projects closed after his employment ended.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kevin Ellis v. Reliant Energy Retail Services, LLC
418 S.W.3d 235 (Court of Appeals of Texas, 2013)
General Capital Group Beteligungsberatung GMBH v. AT & T
407 S.W.3d 507 (Court of Appeals of Texas, 2013)
Aneita J. Weaver v. John Jamar
383 S.W.3d 805 (Court of Appeals of Texas, 2012)
M & a Technology, Inc. v. iValue Group, Inc.
295 S.W.3d 356 (Court of Appeals of Texas, 2009)
Collins & Aikman Floorcoverings, Inc. v. Thomason
256 S.W.3d 402 (Court of Appeals of Texas, 2008)
Tricon Tool & Supply, Inc. v. Thumann
226 S.W.3d 494 (Court of Appeals of Texas, 2006)
Tricon Tool & Supply, Inc. v. Bruce E. Thumann
Court of Appeals of Texas, 2006

Cite This Page — Counsel Stack

Bluebook (online)
126 S.W.3d 548, 2003 WL 22707422, Counsel Stack Legal Research, https://law.counselstack.com/opinion/myrex-industries-inc-v-ortolon-texapp-2004.