Miller-Davis Co. v. Ahrens Construction Inc.

802 N.W.2d 33, 489 Mich. 355
CourtMichigan Supreme Court
DecidedJuly 11, 2011
DocketDocket 139666
StatusPublished
Cited by31 cases

This text of 802 N.W.2d 33 (Miller-Davis Co. v. Ahrens Construction Inc.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller-Davis Co. v. Ahrens Construction Inc., 802 N.W.2d 33, 489 Mich. 355 (Mich. 2011).

Opinion

Marilyn Kelly, J.

This case involves a dispute over a construction contract. At issue is whether the limitations period in MCL 600.5839(1) applies to an action for breach of contract. The Court of Appeals held that it does and that the statute’s six-year limitations period expired before plaintiff filed its complaint, barring the suit. Accordingly, the Court of Appeals reversed the judgment of the trial court, which had awarded plaintiff damages for breach of contract, and remanded the case for entry of a judgment in favor of defendant. 1

Plaintiff alleges that the general statute of limitations for breach of contract actions, MCL 600.5807(8), controls its action and that it filed suit within six years of the date its action accrued. Defendant alleges that *358 the contractor statute of repose, MCL 600.5839(1), controls plaintiffs action and that plaintiff filed it more than six years after the occupancy, use, or acceptance of the roof defendant built. 2 If defendant is correct, the suit is time-barred; if plaintiff is correct, the suit may not be time-barred.

We agree with plaintiff that MCL 600.5839(1) does not apply to actions for breach of contract. MCL 600.5807(8) is the applicable statute. The limitations period in both statutes is six years. But unlike the period in MCL 600.5839(1), which runs from “the time of occupancy of the completed improvement, use, or acceptance of the improvement,” the limitations period in MCL 600.5807(8) runs from the date the “claim first accrued . . . .”

Accordingly, we reverse the judgment of the Court of Appeals. Because there is a question about the date plaintiffs action accrued, we remand the case to the Court of Appeals to resolve this issue, as well as other issues not yet considered.

THE FACTUAL BACKGROUND AND PROCEDURAL HISTORY

Plaintiff, Miller-Davis Company, was the general contractor hired to improve and construct various buildings for the YMCA Camping and Retreat Services of Battle Creek and Kalamazoo. The project included construction of a natatorium. Plaintiff contracted with defendant Ahrens Construction, Inc., to install the natatorium’s roof.

A temporary certificate of occupancy was issued for the entire project on June 11, 1999. The roof was *359 installed before that date. Soon after its installation, the YMCA noticed excessive condensation in the natatorium, so severe at times that it appeared to be “raining” in the pool area. The parties refer to this condition as the “natatorium moisture problem” (NMP).

The temperature and air pressure in the pool were adjusted. Also, defendant performed corrective work on the roof. But the NMP continued into 2003, when plaintiffs architect recommended removing the roof as the only means to determine whether defendant’s improper installation caused the NMP The architect, who eventually testified as plaintiffs expert witness, opined that rips in and missing sections of the vapor barrier and improper installation of the insulation had caused the NMP

Defendant insisted that the NMP was the result of design defects rather than poor workmanship. After all defendant’s efforts to correct the problem were unsuccessful, plaintiff declared a default. Plaintiff eventually performed the corrective work itself in the fall of 2003.

In May 2005, plaintiff sued defendant, alleging that it had breached its contract by installing a roof that did not conform to the plan’s specifications. Plaintiff sought indemnification for the necessary corrective work. Its complaint did not allege that defendant’s work created a defective and unsafe condition, that defendant caused the NMI] or that plaintiffs damages arose from a defective and unsafe condition. Nor did it refer to defendant’s express one-year guarantee or allege a breach of warranty.

Defendant sought summary disposition under MCR 2.116(C)(7), claiming that plaintiff had filed suit after expiration of the six-year period specified in the statute of repose contained in MCL 600.5839(1). The trial court *360 denied defendant’s motion without addressing the applicability of MCL 600.5839(1). 3

The case proceeded to a bench trial. Plaintiffs theory was that defendant had constructed a defective roof and that the nature of the defect became apparent only when the roof was removed. It asserted that the NMP did not reappear after the roof was reconstructed. Defendant’s defense was that design defects caused the NMP For example, defendant claimed that the NMP arose because the roofs design allowed the vapor barrier to come into contact with cold outside air. Defendant’s expert testified that once the defectively designed roof had been removed, the NMP was corrected because trapped moisture was allowed to escape. Alternatively, defendant argued that the alleged defects in the roof were caused when plaintiff removed it. In closing argument, defendant again raised the statute of repose.

The trial court ruled in favor of plaintiff. It determined that defendant was in material breach of its contract for having performed nonconforming and defective work on the roof, which required corrective measures. This resulted in damages of $348,851.50. On the indemnity claim, the court ruled in favor of defendant because no suits had been filed against plaintiff. Hence, no indemnification was required. The court did not address the statute of repose issue.

Defendant appealed as of right, raising the statute of repose, among other defenses. Plaintiff cross-appealed the denial of its indemnity claim. The Court of Appeals agreed with defendant on the statute-of-repose issue, *361 and reversed the judgment of the trial court. 4 Because that resolution rendered moot the other issues, including the cross-appeal, the Court of Appeals declined to consider them and remanded the case for entry of a judgment for defendant. 5

We granted plaintiffs application for leave to appeal. 6

THE STATUTES INVOLVED

The issue in this case is whether the statute of repose contained in MCL 600.5839(1) or the statute of limitations contained in MCL 600.5807(8) applies to plaintiffs civil action. This case also involves the interpretation and application of MCL 600.5805. The issue presents a question of law that we review de novo. 7

MCL 600.5805 sets forth various periods of limitations for civil actions. It provides, in pertinent part:

(1) A person shall not bring or maintain an action to recover damages for injuries to persons or property unless, after the claim first accrued to the plaintiff or someone through whom the plaintiff claims, the action is commenced within the periods of time prescribed by this section.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnny Zaitona v. John Leonowicz
Michigan Court of Appeals, 2026
Krist Oil Company v. Semco Energy Inc
Michigan Court of Appeals, 2025
Tameka McCree v. Continental Management LLC
Michigan Court of Appeals, 2021
Steven Hinderer v. Marcus Snyder
Michigan Court of Appeals, 2019
Rose Sfraga v. Sanctuary at Fraser Villa
Michigan Court of Appeals, 2018
Deborah Fuqua v. David Goldstein
Michigan Court of Appeals, 2018
People of Michigan v. Juan Vincent Buber
Michigan Court of Appeals, 2017
Frank v. Linkner
871 N.W.2d 363 (Michigan Court of Appeals, 2015)
Miller-Davis Co. v. Ahrens Construction, Inc.
848 N.W.2d 95 (Michigan Supreme Court, 2014)
Book-Gilbert v. Greenleaf
840 N.W.2d 743 (Michigan Court of Appeals, 2013)
Lela Tompkins v. Crown Corr, Inc.
726 F.3d 830 (Sixth Circuit, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
802 N.W.2d 33, 489 Mich. 355, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-davis-co-v-ahrens-construction-inc-mich-2011.