Spring Harbor Club Condominium Association v. Greg Wright

CourtMichigan Court of Appeals
DecidedJune 23, 2015
Docket321507
StatusUnpublished

This text of Spring Harbor Club Condominium Association v. Greg Wright (Spring Harbor Club Condominium Association v. Greg Wright) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spring Harbor Club Condominium Association v. Greg Wright, (Mich. Ct. App. 2015).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS

SPRING HARBOR CLUB CONDOMINIUM UNPUBLISHED ASSOCIATION, DON L. KESKEY, the ESTATE June 23, 2015 OF PETER DONLIN, and BRUCE TRAVERSE d/b/a KESTRADON ENTERPRISES,

Plaintiffs-Appellants,

v No. 321507 Charlevoix Circuit Court GREG WRIGHT d/b/a WRIGHT ENTERPRISE LC No. 13-061924-CK INC a/k/a BUILT WRIGHT CONSTRUCTION a/k/a BUILT WRIGHT CONTRACTORS a/k/a BUILT WRIGHT CORP, H. JACK BEGROW PC, HAROLD JACK BEGROW, and UNKNOWN SUBCONTRACTORS,

Defendants-Appellees.

Before: RONAYNE KRAUSE, P.J., and MURPHY and SERVITTO, JJ.

PER CURIAM.

Plaintiffs appeal by right the trial court’s grant of summary disposition in favor of defendants on the grounds that plaintiffs’ claims are time-barred. Plaintiffs are, in broad strokes, the owners of certain condominiums designed or constructed by defendants between 1991 and 1994. In 2013, plaintiffs discovered significant problems with the structure, and upon further inspection they determined that the problems were due to defective construction or construction management. Furthermore, plaintiffs contend that the defective workmanship was totally undiscoverable in the interim. Defendants successfully argued that plaintiffs’ claims are time- barred by applicable statutes of limitation, statutes of repose, or a limitations period specified in the parties’ contracts. The issue before this Court is not the substantive merits of plaintiffs’ claims, but rather solely whether those claims are indeed time-barred. We affirm in part, reverse in part, and remand.

I. INTRODUCTION

A grant or denial of summary disposition is reviewed de novo on the basis of the entire record to determine if the moving party is entitled to judgment as a matter of law. Maiden v Rozwood, 461 Mich 109, 118; 597 NW2d 817 (1999). A motion brought under MCR

-1- 2.116(C)(8) should be granted only where the complaint is so legally deficient that recovery would be impossible even if all well-pleaded facts were true and construed in the light most favorable to the non-moving party. Id. at 119. Only the pleadings may be considered when deciding a motion under MCR 2.116(C)(8). Id. at 119-120. Under MCR 2.116(C)(7), where the claim is allegedly barred, the trial court must accept as true the contents of the complaint, unless they are contradicted by documentary evidence submitted by the moving party. Id. at 119. For the purposes of the instant appeal, we presume the truth of the assertions in plaintiffs’ complaint.

Plaintiffs’ Second Amended Complaint alleges one count each of breach of contract against defendant Greg Wright and defendant Jack Begrow, and counts of malpractice, breach of implied warranties, gross negligence, and negligence against both. Plaintiffs allege that they retained Wright and his associated business entities (collectively “Wright”), a licensed residential contractor, as general contractor to build the condominium project, and they retained Begrow, a licensed architect, to design the project and supervise its construction. “Greg Wright and Jack Begrow ignored critical design specifications, industry standards and applicable building codes during the construction of Spring Harbor Club thereby creating defective and unsafe conditions.” This alleged malfeasance caused considerable damage that was not discovered until 2013 because of the hidden nature of the defects. Plaintiffs have promptly performed remediation at their expense but believe more damage remains to be discovered. For convenience, we will address the individual counts asserted by plaintiffs in sequence.

II.(A) BREACH OF CONTRACT

Plaintiffs assert that their breach of contract claims are not subject to any limitations period because they articulate indemnity claims, or because they contend they should be granted leave to amend their complaint to articulate indemnity claims. Our Supreme Court has explained that the contractor’s statute of repose, MCL 600.5839, only applies to tort claims, so a contractual claim against a contractor would instead be subject to the general 6-year limitations period for contract claims set forth in MCL 600.5807(8). See Miller-Davis Co v Ahrens Constr Inc (Miller-Davis II), 495 Mich 161, 169-170; 848 NW2d 95 (2014). Our Supreme Court further explained that in a claim for indemnification, a party breaches an indemnity clause in a contract when the party refuses a demand to indemnify, which is independent of the date when the party allegedly breached any other obligations it might have had under the contract. Id. at 180-182. Importantly, Miller-Davis II relied on the fact that the parties in that case had a broad and unambiguous indemnity clause in their contract. Miller-Davis II, 495 Mich at 174-175. Plaintiffs are correct in stating that if they could arguably show that defendants breached an indemnity clause in their contract, they should indeed have an opportunity to prove it.

However, the indemnification clauses in the parties’ contracts are not as inclusive as the one at issue in Miller-Davis II. The indemnification clause in the contract with Wright states:

To the fullest extent permitted by law, the Contractor shall indemnify and hold harmless the Owner and the Architect and their agents and employees from and against all claims, damages, losses and expenses, including but not limited to attorneys’ fees, arising out of or resulting from the performance of the Work, provided that any such claim, damage, loss or expense (1) is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible

-2- property (other than the Work itself) including the loss of use resulting therefrom, and (2) is caused in whole or in part by any negligent act or omission of the Contractor, any Subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, regardless of whether or not it is caused in part by a party indemnified hereunder.

Parsing the above provision, the first requirement for an indemnification claim explicitly excludes claims arising from Wright’s performance to the extent any such claim arises out of harm to the work performed itself. Reading plaintiffs’ complaint as a whole, the entirety of plaintiffs’ action is based on damage to the condominium structure and other construction work allegedly performed by Wright. The indemnity clause in Miller-Davis II contained no such exclusion. Furthermore, plaintiffs have not articulated any document purporting to be a contractual indemnity provision between themselves and defendant Begrow. We are not persuaded that it is possible for plaintiffs to articulate an indemnity claim.

II.(B) MALPRACTICE

Plaintiffs correctly state that, unlike many of the other claims at issue, a claim for malpractice enjoys a “discovery rule” that tolls the applicable limitations period to a certain extent. Other than medical or legal malpractice claims, the general rule is that a claim for malpractice “accrues” when a licensed professional discontinues professionally serving a plaintiff, MCL 600.5838(1), but, with exceptions not relevant here, an action may be commenced “within 6 months after the plaintiff discovers or should have discovered the existence of the claim.” MCL 600.5838(2). Actions against architects or contractors for damages to property “arising out of the defective or unsafe condition of an improvement to real property” are, however, subject to a statute of repose, establishing a maximum limit of ten years after the improvement is occupied or accepted. MCL 600.5839(1)(b). A superficial reading of the latter statute leads to the conclusion that plaintiffs’ claims expired in 2004 at the latest.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miller-Davis Co. v. Ahrens Construction Inc.
802 N.W.2d 33 (Michigan Supreme Court, 2011)
Rory v. Continental Insurance
703 N.W.2d 23 (Michigan Supreme Court, 2005)
Cree Coaches, Inc. v. Panel Suppliers, Inc.
186 N.W.2d 335 (Michigan Supreme Court, 1971)
Etefia v. Credit Technologies, Inc
628 N.W.2d 577 (Michigan Court of Appeals, 2001)
Maiden v. Rozwood
597 N.W.2d 817 (Michigan Supreme Court, 1999)
Weeks v. Slavik Builders, Inc.
180 N.W.2d 503 (Michigan Court of Appeals, 1970)
Smith v. Foerster-Bolser Construction, Inc
711 N.W.2d 421 (Michigan Court of Appeals, 2006)
City of Marysville v. Pate, Hirn & Bogue, Inc
397 N.W.2d 859 (Michigan Court of Appeals, 1986)
Ostroth v. Warren Regency, GP, LLC
687 N.W.2d 309 (Michigan Court of Appeals, 2004)
Miller-Davis Co. v. Ahrens Construction, Inc.
848 N.W.2d 95 (Michigan Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Spring Harbor Club Condominium Association v. Greg Wright, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spring-harbor-club-condominium-association-v-greg-wright-michctapp-2015.