Midwest Materials Co. v. Village Development Co.

806 S.W.2d 477, 1991 Mo. App. LEXIS 468, 1991 WL 41775
CourtMissouri Court of Appeals
DecidedMarch 29, 1991
Docket16673
StatusPublished
Cited by43 cases

This text of 806 S.W.2d 477 (Midwest Materials Co. v. Village Development Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Midwest Materials Co. v. Village Development Co., 806 S.W.2d 477, 1991 Mo. App. LEXIS 468, 1991 WL 41775 (Mo. Ct. App. 1991).

Opinion

SHRUM, Judge.

In this breach of contract case, a jury awarded damages of $34,933.50 and interest of $27,972.69 to respondent Midwest Materials Company, the contractor, on its claim under a building construction contract. The jury found against appellant Village Development Company, the owner, on its counterclaim for breach of contract. The trial court entered judgment pursuant to the jury verdict and Village has appealed. We affirm.

FACTUAL AND PROCEDURAL SYNOPSIS

In December 1981, the parties entered a contract under which Midwest, a corporation, would build a condominium apartment complex at the Lake of the Ozarks for Village, a partnership consisting of appellants Theodore Ruppert and R. Michael Webb. Within one year, disputes arose about various matters such as costs incurred, quality of the work, changes in specifications, timeliness of completion, and payment by the owner to the contractor. Midwest ceased work on the project prior to completion of the entire complex.

In early 1984, Midwest filed a petition whereby it sought to enforce a previously filed mechanics lien. In its petition, Midwest also alleged Village had breached the contract in that it “terminated said contract before completion and ceased making the payments required therein to [Midwest].” In its counterclaim, Village alleged that Midwest had breached the contract by failing to substantially complete the first two phases of the project on time, by failing to perform its duties in a “skilled and workmanlike manner,” by completing two phases of the four-phase $776,703.00 project at a cost of $501,000.00, and by charging Village for costs that were not to be reimbursed under the contract. Village sought damages totaling $400,000.00.

In May 1986, the case was transferred to the circuit court’s inactive docket pursuant to local rule. The docket sheet reflects that in May 1987 the case was “closed as per local court rule.” In September 1987, the trial court reinstated the lawsuit to the active docket.

In January 1989 the trial court granted summary judgment to Village on the mechanics lien enforcement claim, and the suit went to trial in October 1989 on the parties’ *482 breach of contract claims. After a four-day trial, the jury returned verdicts for Midwest on its claim and Village’s counterclaim. Following a hearing, the trial court denied Village’s motions for a new trial and judgment notwithstanding the verdict. Village now appeals. We will set out additional facts as necessary in the course of our discussion of Village’s nine points on appeal.

ISSUES ON APPEAL

In summary fashion, this appeal presents the following issues.

1. Whether the trial court erroneously concluded this lawsuit had not been dismissed for lack of prosecution pursuant to a local court rule and whether the trial court exceeded its jurisdiction in reinstating this case from the inactive to the active docket.

2. Whether Midwest made a submissi-ble case on its breach of contract claim.

3. Whether Village was entitled to a judgment on its counterclaim as a matter of law.

4. Whether the trial court committed prejudicial error in overruling Village’s objection to Midwest’s closing argument to the jury.

5. Whether the trial court improperly instructed the jury in submitting the verdict director on Village’s counterclaim.

6. Whether the trial court committed prejudicial error when it permitted introduction of evidence, over objection, that Village owed money to the project architect.

7. Whether the trial court committed prejudicial error when it permitted introduction of evidence pertaining to increases in the cost of the work.

8. Whether the trial court committed prejudicial error when it refused to admit exhibits which Village claimed were probative of damages.

9. Whether Village was entitled to a new trial because a juror, in her juror questionnaire and on voir dire, did not fully disclose her involvement in prior lawsuits.

ISSUE ONE: DISMISSAL UNDER LOCAL RULES

Midwest filed its original petition in January, 1984. The lawsuit proceeded through various stages of pleading and discovery until May 15,1986, when the following docket entry was made. “Case placed on Inactive Docket, Atty’s notified.” The transfer to the inactive docket was based on local Circuit Court Rule 8.2 which states, in part:

The circuit clerk shall maintain two civil dockets for the cases filed with them: (1) ACTIVE and (2) INACTIVE. Upon filing, a case shall be included on the active docket. Cases not disposed of during two (2) years next following their filing shall, on the first day of the term of court next following expiration of said two (2) year period, be deleted from the active docket and placed on the inactive docket. Attorneys of record in cases placed on the inactive docket shall be notified by the circuit clerk of the transfer of cases to the inactive docket within thirty (30) days next follomng such transfer. (Emphasis added.)

Local court Rule 8.2 also provides that if a case is not reinstated to the active docket by court order, upon request by a party, within one year, the case shall then be dismissed, “without prejudice and without further notice to any party thereto, for lack of prosecution.” A related provision, local Rule 37.2 provides, in pertinent part:

Once a case is placed on the inactive docket established by Rule 8.2 hereof, that case may be reinstated to the active docket only in the manner prescribed by Rule 8.2. Once such a case is dismissed for lack of prosecution pursuant to Rule 8.2, that case is not subject to reinstatement absent being refiled as a new case. Rule 8.2 shall be strictly enforced and all counsel are advised to carefully review and consider its content. (Emphasis added.)

In the trial court file is a copy of a form letter dated May 15, 1986, completed so as to state that the case had been placed on the inactive docket “on 5-5-86_” As *483 the trial court later noted in its order reinstating the case, the letter was “not addressed in the manner customary for business correspondence”; rather, at the bottom of the letter, the following appeared:

c.c. Leland C. Bussell, c.c. Sam Weber, c.c. Lewis Z. Bridges, c.c. Charles E. McElyea, c.c. Nicholas J. Lamb, c.c. Marshall K. and Mrs. Shirley J. Fisk.

The next entry on the docket sheet reads: “5/19/87: Case closed as per local Court rule.” On August 21, 1987, Midwest’s attorneys moved to reinstate the case, swearing that they had never received notice from any source that the case had been transferred to the inactive docket. In opposition to Midwest’s motion, Village filed affidavits of Charles McElyea and Lewis Bridges, both attorneys of record in the case, and Marshall Fisk, a named defendant in Midwest’s claim, in which each person swore he had received the May 15, 1986, notice about the case being placed on the inactive docket.

On September 14, 1987, the trial court sustained Midwest’s motion to reinstate the case to the active docket.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DAVID ROMANO v. MIKE R. & CARLA ADAMS
Missouri Court of Appeals, 2024
Shallow v. Follwell
554 S.W.3d 878 (Supreme Court of Missouri, 2018)
Carla Gleason v. Bendix Commercial Vehicle Systems, LLC
452 S.W.3d 158 (Missouri Court of Appeals, 2014)
Baca Chiropractic, P.C. v. Cobb
317 S.W.3d 674 (Missouri Court of Appeals, 2010)
In Re Marriage of Thomas
21 S.W.3d 168 (Missouri Court of Appeals, 2000)
Warren Davis Properties V, L.L.C. v. United Fire & Casualty Co.
4 S.W.3d 167 (Missouri Court of Appeals, 1999)
City of Rolla v. Armaly
985 S.W.2d 419 (Missouri Court of Appeals, 1999)
Simmons v. Lawrence County Jail
948 S.W.2d 242 (Missouri Court of Appeals, 1997)
Kackley v. Burtrum
947 S.W.2d 461 (Missouri Court of Appeals, 1997)
Newcomb v. Humansville R-IV School District
908 S.W.2d 821 (Missouri Court of Appeals, 1995)
Drury v. Missouri Pacific Railroad
905 S.W.2d 138 (Missouri Court of Appeals, 1995)
Hopkins v. American Economy Insurance Co.
896 S.W.2d 933 (Missouri Court of Appeals, 1995)
Hammer v. Waterhouse
895 S.W.2d 95 (Missouri Court of Appeals, 1995)
Pernoud v. Martin
891 S.W.2d 528 (Missouri Court of Appeals, 1995)
Rogers v. Bond
880 S.W.2d 607 (Missouri Court of Appeals, 1994)
Brown v. Van Noy
879 S.W.2d 667 (Missouri Court of Appeals, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
806 S.W.2d 477, 1991 Mo. App. LEXIS 468, 1991 WL 41775, Counsel Stack Legal Research, https://law.counselstack.com/opinion/midwest-materials-co-v-village-development-co-moctapp-1991.