Michael B. Huss v. The King Company, Inc. Lake Michigan Contractors, Inc.

338 F.3d 647, 2003 A.M.C. 2167, 2003 U.S. App. LEXIS 15604, 2003 WL 21792510
CourtCourt of Appeals for the Sixth Circuit
DecidedAugust 5, 2003
Docket02-1010
StatusPublished
Cited by16 cases

This text of 338 F.3d 647 (Michael B. Huss v. The King Company, Inc. Lake Michigan Contractors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michael B. Huss v. The King Company, Inc. Lake Michigan Contractors, Inc., 338 F.3d 647, 2003 A.M.C. 2167, 2003 U.S. App. LEXIS 15604, 2003 WL 21792510 (6th Cir. 2003).

Opinion

OPINION

WILLIAM W SCHWARZER, Senior District Judge.

This is an appeal from an adverse judgment after trial in an action brought by Michael Huss for injuries sustained while employed by defendant King Company, Inc. (King). On May 3, 1995, Huss, together with three other King employees, attempted to retrieve a work boat from the yard of codefendant Lake Michigan Contractors (LMC). As the boat was being hoisted by a crane off its cradle, Huss crawled underneath the boat to remove a scrap of rope from the propeller shaft. While he was attempting to remove the rope, one of the lines securing the boat to the crane came loose, causing it to fall on Huss. He sustained a compression fracture of the fifth lumbar vertebra and a posteri- or left rib fracture. After spending one night in the hospital, he was released to home. He returned to work approximately one month after the accident, performing duties that did not require heavy lifting, until August 1997. At that time, he ceased reporting to work, and in December 1997, he terminated his employment with King. In May 1998, Huss filed this action alleging claims against King under the Jones Act, 46 U.S.C. § 688 et seq., and for unseaworthiness, and against LMC for unseaworthiness and negligence. In January 2000, he filed another action against King alone to recover maintenance and cure. The two actions were consolidated. Following a bench trial, the court awarded Huss damages of $30,234.73; after reducing this amount by sixty percent for Huss’s comparative fault and crediting King with overpayment of maintenance and cure, it entered a take-nothing judgment. This appeal followed. The district court had jurisdiction under 28 U.S.C. § 1333, and we have jurisdiction under 28 U.S.C. § 1291. Because the rulings of the district court were not clearly erroneous and did not abuse its discretion, we affirm the judgment.

DISCUSSION

I. THE CLAIM AGAINST KING

A The Maintenance and Cure Issue

In July 2000, Huss moved for partial summary judgment on his claim for maintenance and cure. 1 The court found *650 that King had discontinued payment of maintenance and cure on January 1, 1998. It held that because Huss had presented evidence that he had not reached maximum cure and King had failed to raise a triable issue, Huss was entitled to summary judgment on liability, leaving the amount due, if any, to be determined. A pretrial order entered in May 2001 stated the amount of maintenance and cure due to be a disputed issue.

In July and August 2001 the case went to trial before the district judge. At the conclusion of the trial, the court delivered oral findings stating, among other things, that new evidence had come to light leading the court to determine that maximum cure had been reached prior to January 1998. 2 In subsequent written findings, the court stated that the prior entry of summary judgment for Huss on the issue of maintenance and cure was “essentially meaningless if by the time of the ruling King had already paid all of the maintenance and cure to which [Huss] was entitled.” It held that because Huss reached maximum cure sometime between September and December 1997, King properly discontinued maintenance and cure payments as of January 1998. King had, however, as the court noted, made additional payments following the court’s earlier ruling for the years 1998, 1999, and 2000. The court found that King was entitled to credit for those sums toward any judgment on the unseaworthiness and Jones Act claims. 3 Huss then filed a post-trial brief, much of it devoted to the maintenance and cure issue. In November 2000 the court issued its Supplemental Order Regarding Maintenance and Cure addressing the evidence adduced at trial and not previously presented that led the court to find that maximum cure had been reached before January 1998, as well as the arguments on the issue advanced by Huss.

Huss’s principal argument on appeal is that the court erred in revoking its partial summary judgment determining that maintenance and cure had not been reached by September 2000. Rule 56(d) authorizes the entry of partial summary judgment. Fed.R.Civ.P. 56(d). It states that if summary judgment is rendered on less than an entire case and a trial on the remaining claims is necessary, the court

shall if practicable ascertain what material facts exist without substantial controversy and what material facts are actually and in good faith controverted. It shall thereupon make an order specifying the facts that appear without substantial controversy, including the extent to which the amount of damages or other relief is not in controversy, and directing such further proceedings in the action as are just. Upon the trial of the action the facts so specified shall be deemed established, and the trial shall be conducted accordingly.

*651 We agree with Judge Newman’s analysis of Rule 56(d) in Leddy v. Standard Drywall, Inc., 875 F.2d 888 (2d Cir.1989), in which he stated:

Once a district judge issues a partial summary judgment order removing certain claims from a case, the parties have a right to rely on the ruling by forbearing from introducing any evidence or cross-examining witnesses in regard to those claims. If, as allowed by Rule 54(b), 4 the judge subsequently changes the initial ruling and broadens the scope of the trial, the judge must inform the parties and give them an opportunity to present evidence relating to the newly revived issue. Failure to do so might in some circumstances cause substantial prejudice.

875 F.2d at 386.

Here, the district judge informed Huss of the change of his initial ruling and gave him an opportunity in post-trial briefing to argue that he was entitled to continued payment of maintenance and cure after January 1998. Although the court’s change of its ruling did not occur until after trial, it was based on the damage evidence relevant to maintenance and cure presented at trial. Counsel on brief made no attempt to show that the post-trial change of the ruling prejudiced his trial presentation. At oral argument he conceded that all of the evidence relevant to maintenance and cure had been presented in support of Huss’s damage claim and that he knew of no questions he would have asked witnesses had he known of the court’s revised ruling. We conclude that the district court did not commit error and that its action did not prejudice Huss.

B. Allocation of Comparative Negligence

Huss contends that the district court’s allocation to him of sixty percent comparative negligence was clearly erroneous. Our review of allocation of fault is for clear error. Phillips Petroleum Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ordos City Hawtai Autobody Co. v. Dimond Rigging Co.
695 F. App'x 864 (Sixth Circuit, 2017)
Ronald Stolle v. Kent State University
610 F. App'x 476 (Sixth Circuit, 2015)
Randall Waldman v. Ronald Stone
599 F. App'x 569 (Sixth Circuit, 2015)
David Hayduk v. City of Johnstown
386 F. App'x 55 (Third Circuit, 2010)
Dillon v. Cobra Power Corp
Sixth Circuit, 2009
Royal Caribbean Cruises, Ltd. v. Cox
974 So. 2d 462 (District Court of Appeal of Florida, 2008)
Venture Industries Corp. v. Autoliv ASP, Inc.
196 F. App'x 894 (Federal Circuit, 2006)
In re: John R. Homes v.
Sixth Circuit, 2006
Dean v. Byerley
Sixth Circuit, 2005
Brege v. Lakes Shipping Co.
225 F.R.D. 546 (E.D. Michigan, 2004)
Huss v. King Co., Inc.
541 U.S. 1015 (Supreme Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
338 F.3d 647, 2003 A.M.C. 2167, 2003 U.S. App. LEXIS 15604, 2003 WL 21792510, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michael-b-huss-v-the-king-company-inc-lake-michigan-contractors-inc-ca6-2003.