Metropolitan Erection v. Landis Const.

627 So. 2d 144, 1993 La. LEXIS 3394, 1993 WL 490228
CourtSupreme Court of Louisiana
DecidedNovember 29, 1993
Docket93-C-1017
StatusPublished
Cited by16 cases

This text of 627 So. 2d 144 (Metropolitan Erection v. Landis Const.) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metropolitan Erection v. Landis Const., 627 So. 2d 144, 1993 La. LEXIS 3394, 1993 WL 490228 (La. 1993).

Opinion

627 So.2d 144 (1993)

METROPOLITAN ERECTION COMPANY, INC.
v.
LANDIS CONSTRUCTION COMPANY, INC. et al.

No. 93-C-1017.

Supreme Court of Louisiana.

November 29, 1993.

*145 Lloyd N. Shields, Avis M. Russell, Denise C. Puente, Simon, Peragine, Smith & Redfearn, New Orleans, for applicant.

Harold E. Dearie, II, Dearie & Killian, Metairie, for respondent.

LEMMON, Justice.[*]

This is an action by a subcontractor against the general contractor and its surety to recover the balance due the subcontractor for work performed under a construction contract. The subcontractor did not file the action within the one-year period provided in La.Rev.Stat. 9:4813 for instituting an action asserting its claim against the surety. The issue is whether the general contractor's acknowledgment of the debt extended the period for the filing of the subcontractor's claim against the general contractor's surety.

Landis Construction Company, Inc. entered into a contract with MART-Perez, Inc. to construct an aerial transit crossing the Mississippi River for the 1984 World's Fair. United States Fidelity and Guaranty Company (USF & G) issued a payment bond as surety for the contract. The notice of the contract was duly recorded.

Landis subcontracted with Metropolitan Erection Co., Inc. (MECO) to erect the steel and pre-cast bracings for the aerial crossing. The Landis-MECO subcontract contained the provision that Landis would pay the final payment of the contract price to MECO when Landis received payment from MART-Perez.

MECO performed completely its obligations under the subcontract, and Landis completed the construction of the aerial crossing. Landis and MART-Perez filed a notice of termination of the work on June 20, 1984.[1] The facility was used by MART-Perez *146 during the World's Fair from May through November of 1984. However, MART-Perez failed to pay Landis over $800,000 under the general contract, and there was an unpaid balance of almost $88,000 due by Landis to MECO under the subcontract.[2] According to the stipulation between the parties, Landis continually acknowledged its debt to MECO, but advised it would not pay until MART-Perez paid Landis.

MECO filed the present action against Landis and USF & G on September 13, 1985. Defendants answered and filed a third party demand against MART-Perez.

A 1987 trial date was continued on joint motion, awaiting a decision of this court in Southern States Masonry, Inc. v. J.A. Jones Constr. Co., 507 So.2d 198 (La.1987). In the Southern States87063249 case, this court held that the "pay when paid" provision of a construction contract (similar to the one in the present case) was a term of the contract specifying the time for payment and not a condition of the general contractor's obligation to pay. Therefore, the obligation of the general contractor to pay the balance of the subcontract was not contingent on the general contractor's receipt of payment from the owner on the general contract.

After the Southern States opinion, Landis filed a petition in bankruptcy. The case then proceeded to trial against USF & G, who raised the issue that the claim was prescribed. The parties submitted the matter on the basis of stipulations and briefs.

The trial court rendered judgment in favor of MECO in the amount due under the subcontract, reasoning that it was inequitable to allow Landis to file the certificate of termination of work without notice to MECO and thereby trigger the beginning date of MECO's period for filing suit, while Landis was claiming at the same time that MECO's claim would not mature until the owner paid Landis under the general contract.

The court of appeal affirmed. 613 So.2d 1147. Citing Flowers v. United States Fidelity and Guaranty Co., 381 So.2d 378 (La. 1980), the court held that Landis' repeated acknowledgments of the debt interrupted prescription and that the action was therefore timely.

We granted certiorari to review the decisions of the lower courts. 620 So.2d 821.

Although MECO's claim against Landis is not presently before the court, we note that the MECO-Landis claim was based on a contract, subject to a ten-year prescriptive period. However, there was no contractual relationship between MECO and USF & G, and that claim was based on a special statute.

The Private Works Act, La.Rev.Stat. 9:4801-42, provides the method for contractors, laborers and suppliers of materials to secure and preserve a privilege, according to the circumstances, against the owner, the property and/or the general contractor's surety. As to the time for filing the claim, La.Rev.Stat. 9:4822A provides in part:

A. If a notice of contract is properly and timely filed in the manner provided by R.S. 9:4811, the persons to whom a claim or privilege is granted by R.S. 9:4802 shall within thirty days after the filing of a notice of termination of the work:
(1) File a statement of their claims or privilege.

La.Rev.Stat. 9:4813, providing for the liability of the surety, states in Subsection E:

E. The surety's liability, except as to the owner, is extinguished as to all persons who fail to institute an action asserting their claims or rights against the owner, the contractor, or the surety within one year after the expiration of the time specified in R.S. 9:4822 for claimants to file their statement of claim or privilege.

In the present case, Landis and MART-Perez properly and timely filed the notice of the contract, but MECO did not file an action against the surety within one year of the expiration of the time for filing the statement of claim or privilege.[3]

*147 MECO first contends that the general contractor must notify the subcontractor of the filing of notice of termination of the work in order for Section 4822A's thirty-day period to commence. There is no such requirement in the Act. Moreover, there is no suggestion that the notice was filed prematurely or in bad faith. See La.Rev.Stat. 9:4822E(3)(a). Although a dispute existed between MECO and Landis whether payment on their contract was due at the time of filing, the filing of the notice was appropriate, and nothing prevented MECO from filing its claim and its suit to secure and preserve its privilege.

MECO further contends that Landis' continued acknowledgments of the debt interrupted prescription against both Landis and USF & G.[4] MECO relies on La.Civ.Code art. 3504, as amended effective January 1, 1984, which provides that "[w]hen prescription is interrupted against the principal debtor, the interruption is effective against his surety." MECO cites Dinon Terrazzo & Tile Co. v. Tom Williams Constr. Co., 148 So.2d 329 (La.App. 4th Cir.1963), in which the court applied former La.Civ.Code art. 3553

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Buck Town Contractors & Co. v. K-Belle Consultants, LLC
216 So. 3d 981 (Louisiana Court of Appeal, 2016)
Hawk Field Services, L.L.C. v. Mid America Underground, L.L.C.
94 So. 3d 136 (Louisiana Court of Appeal, 2012)
State Bd. of Ethics v. Ourso
842 So. 2d 346 (Supreme Court of Louisiana, 2003)
C & S Safety Systems, Inc. v. SSEM Corp.
843 So. 2d 447 (Louisiana Court of Appeal, 2003)
Byron Montz, Inc. v. Conco Construction, Inc.
824 So. 2d 498 (Louisiana Court of Appeal, 2002)
Clark Construction Co. v. Warren
774 So. 2d 1091 (Louisiana Court of Appeal, 2000)
Orleans Parish Sch. Bd. v. Scheyd, Inc.
737 So. 2d 954 (Louisiana Court of Appeal, 1999)
Hershell Corp. v. Fireman's Fund Ins. Co.
743 So. 2d 698 (Louisiana Court of Appeal, 1999)
State v. McInnis Bros. Const.
701 So. 2d 937 (Supreme Court of Louisiana, 1997)
State ex rel. Division of Administration v. McInnis Bros. Construction
690 So. 2d 927 (Louisiana Court of Appeal, 1997)
Settoon Marine, Inc. v. Great Lakes Dredge & Dock Co.
657 So. 2d 537 (Louisiana Court of Appeal, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
627 So. 2d 144, 1993 La. LEXIS 3394, 1993 WL 490228, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metropolitan-erection-v-landis-const-la-1993.