Metropolitan Erection Co. v. Landis Construction Co.

613 So. 2d 1147, 1993 La. App. LEXIS 690, 1993 WL 41161
CourtLouisiana Court of Appeal
DecidedFebruary 10, 1993
DocketNo. 92-CA-795
StatusPublished
Cited by3 cases

This text of 613 So. 2d 1147 (Metropolitan Erection Co. v. Landis Construction Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metropolitan Erection Co. v. Landis Construction Co., 613 So. 2d 1147, 1993 La. App. LEXIS 690, 1993 WL 41161 (La. Ct. App. 1993).

Opinion

GOTHARD, Judge.

Defendant, United States Fidelity and Guaranty Company (USF & G) appeals an adverse decision on a motion for summary judgment. We affirm.

This matter arises out of a suit for breach of contract ^filed on September 13, 1986 by Metropolitan Erection Company, Inc. (Metro), a subcontractor, against Lan-dis Construction Company, Inc. (Landis), a general contractor, and its surety, (USF & G). The contract at issue is one for construction of a gondola for the Mississippi Aerial River Transit Facility (Mart) on the site of the 1984 Louisiana World’s Fair in New Orleans.

In the petition Metro asserts a claim for $87,785.50 plus interest and cost due and owing for labor performed and materials furnished as per the terms of its subcontract with Landis. Landis answered the suit admitting the funds were due to Metro but maintaining as a defense a “pay when paid” clause in the subcontract. Landis asserts that, since it has not been paid by the owner (Mart) on the prime contract, Metro is not yet entitled to payment on the subcontract. Landis also made a third party demand against Mart for payment on the prime contract.

A trial on the merits was continued indefinitely by a joint motion of the parties on March 30, 1987 pending the outcome of two consolidated cases before the Louisiana Supreme Court interpreting the “pay when paid” clause in subcontracts.1 In that motion the following statement was made;

... undersigned counsel thinks that the decisions of our La. Supreme Court in these cases will probably be binding precedents that will be dispositive of the issues involved in this action that should obviate trial of this case and result in an agreement for a consent judgment herein
[[Image here]]

On May 18, 1987 a decision rendered by the Supreme Court in those consolidated [1149]*1149cases2 held that “pay when paid” clauses provide a method of and not a condition precedent to payment; thus, subcontractors were given a right to collect monies owed pursuant to a subcontract even if the general contractor has not been paid on the prime contract.

The parties filed stipulations which resolved all factual issues as follows:

1. On September 28, 1983, Landis, as general contractor, entered into a written prime contract with third party defendant MART/Perez, Inc., as owner, for construction of the Mississippi Aerial River Transit [“Mart”] on the site of the 1984 Louisiana World’s Fair in New Orleans, Louisiana.
2. The notice of this construction contract was recorded at MOB 2430, folio 347 in the office of the Orleans Parish Recorder of Mortgages, in compliance with the Louisiana Private Works Statute (La.R.S. 9:4801-4842, as amended).
3. Defendant, USF & G, issued a written bond as Surety for Landis, as general contractor, on the September 29, 1983 MART/Perez, Inc. — Landis Prime Contract in compliance with Louisiana Private Works Statute (La.R.S. 9:4801-4842). Due to the bankruptcy proceedings of Landis, referred to below, USF & G remains the only defendant as to Metro.
Landis is now the debtor in a petition for relief under Chapter 11 of Title 11 of the United States Bankruptcy Code pending in the United States Bankruptcy Court for the Eastern District of Louisiana and bearing case number 87-05424-BCK-THK.
4. On January 23, 1984, Landis entered into a written Subcontract Agreement with Metro for the completion of the erection of all fabricated steel and pre-cast x-bracing required for the Mississippi Aerial River Transit facility on the site of the 1984 Louisiana World Exposition in New Orleans, Louisiana. The base contract price was $79,062.00. Lan-dis issued to Metro three change orders totaling $94,075.00 thereby increasing the adjusted contract price to $173,-137.00.
5. Metro satisfactorily performed and completed all of the work of the Subcontract as amended.
6. Landis satisfactorily performed and completed all work required by the Prime Contract with MART, and in May, 1984, MART assumed occupancy, possession, control and use of the structures and improvements, and used these facilities continuously during the six month period of the World’s Fair, from May 12, 1984, to November 11, 1984.
7. Landis, in its third party demand herein, alleges that MART has failed to pay it $868,099.00 of the earned Prime Contract funds.
8. Landis and USF & G admit that the unpaid balance on Metro’s subcontract is $87,785.50 for which Metro filed this lawsuit on September 13, 1985.
9. Landis and MART/Perez filed a Certificate of Substantial Completion on June 20, 1984, and said notice is recorded as instrument number 555091 of the Notarial Archives of the Parish of Orleans and recorded in MOB 2452, folio 517.
The notice of this acceptance was published in the New Orleans Daily Journal of Commerce on July 11, 1984. However, this publication is available to individuals, corporations, etc. by subscription only.
10. Landis admits that it never advised Metro of the filing of this Notice of Substantial Completion and that it repeatedly acknowledged its debt to Metro, and adyised that it was owed $868,099.00 by MART, and advised that it would pay Metro upon receipt of the money owed it by MART, relying on the “Pay When Paid” provisions of Landis’ January 23, 1984 contract with Metro.
Landis, in its third party demand against MART/Perez, alleges a violation and breach of essential terms and conditions of the September 29, 1983 Prime Contract, and admits that such a breach existed when it signed a Certificate of [1150]*1150Substantial Completion filed on June 20, 1984 (recorded as noted above).
11. The parties agree that this case was set for trial on the merits in this Court on March 23, 1987, and the record will reflect that the parties, through their then respective counsel, filed a Joint Motion to continue the Trial. In this Joint Motion to Continue, the parties agreed, through their respective counsel, to the issues to be litigated before this Court.
The reason for the continuance was that similar issues were pending before the Louisiana Supreme Court in two consolidated cases titled “Southern States Masonry, Inc. v. J.A. Jones Company and Fidelity and Deposit Company of Maryland” #86-0-2443 (498 So.2d 151 La.App. 5th Cir.), and “Dorman Stra-han d/b/a Strahan Painting Company v. Landis Construction Company and United States Fidelity & Guaranty Company ” # 86-0-2544 (499 So.2d 417 La.App. 4th Cir.).
12. The parties agree that the above cited cases were heard by the Supreme Court, and that a decision rendered May 18, 1987 and reported at (507 So.2d 198 Sup.Ct.1987) held that the “Pay When Paid” clauses were a method of payment and not a condition precedent, and therefore, that the subcontractors had a right to be paid even if the owner had not paid the general contractor. A motion for a re-hearing in these consolidated cases was denied on June 18, 1987.
13.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
613 So. 2d 1147, 1993 La. App. LEXIS 690, 1993 WL 41161, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metropolitan-erection-co-v-landis-construction-co-lactapp-1993.