Louisiana Nat. Bank v. Triple R Contractors, Inc.
This text of 345 So. 2d 7 (Louisiana Nat. Bank v. Triple R Contractors, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
LOUISIANA NATIONAL BANK OF BATON ROUGE
v.
TRIPLE R. CONTRACTORS, INC., et al.
Supreme Court of Louisiana.
Robert M. Day, Day & Grand, Baton Rouge, for plaintiff-applicant.
Charles W. Borde, Jr., Durbin, Durbin, Borde & Fogg, Denham Springs, Charles O. Simmons, Jr., E. Drew McKinnis, McKinnis & Juban, Baton Rouge, for defendants-respondents.
Prentice L. G. Smith, Jr., Smith & Smith, Baker, for intervenor-respondent.
*8 DENNIS, Justice.
We are called upon to decide whether the developer of an apartment complex who divides its construction into two segments, by having the construction performed on separate but adjacent lots under two separate construction contracts, may give his lender a mortgage superior to materialmen's liens on the second segment although work commences on the first segment before the mortgage is filed. The case ultimately hinges upon whether the segments constitute two different "phases" of subdivision development under the Private Works Act, La. R.S. 9:4801, et seq.
On October 17, 1972, Triple R Contractors mortgaged to Louisiana National Bank (LNB) 4.89 acres of its 6.6 acre tract on Essen Lane in East Baton Rouge Parish to secure a loan for the construction of a 94-unit apartment complex on the mortgaged property. LNB provided 10% of the funds for the project and Colwell Mortgage Trust supplied the remaining 90%; at the completion of construction, the mortgage and the note it secured were to be assigned to Colwell which would reimburse to LNB its 10% investment. The act of mortgage was recorded on the same day it was executed, together with a building contract between Triple R and Riddle Masonry Company, Inc., and an affidavit by a licensed civil engineer certifying that no work had begun and no materials had been placed on the building site. Construction began shortly thereafter.
On March 1, 1973, Triple R purchased an additional 2.58 acres adjacent to its 6.6 acre tract, and on March 29, 1973, mortgaged the entire 9.18 acre tract to LNB, under the same arrangement with Colwell Mortgage Trust as the 1972 mortgage. This mortgage was given to secure a second loan to be used in the construction of a 97-unit apartment complex, specifically described and referred to as "Phase II" in the mortgage, on the 4.29 acres of the property not already devoted to the construction of Phase I. Recorded with the mortgage and a building contract for the Phase II construction, was a civil engineer's no-work affidavit relating only to the 4.29 acres comprising Phase II. At this time work on Phase I was well under way.
Phase I was accepted as completed on January 2, 1974, and a clear lien certificate was issued by the Clerk of Court on February 4, 1974. The mortgage on Phase I was then assigned to Colwell Mortgage Trust.
Prior to the completion of Phase II, Triple R defaulted under the terms of both the Phase I and Phase II mortgages and notes. As a result Colwell Mortgage Trust instituted foreclosure proceedings against the Phase I complex and LNB instituted foreclosure proceedings against the Phase II complex.
A number of interventions claiming materialman's liens were filed against the Phase II property by persons who had furnished supplies and materials to that project. On February 12, 1975 the property was adjudicated to LNB by Sheriff's sale subject to any liens and encumbrances which primed the mortgage in favor of LNB. LNB then brought this rule to have its mortgage recognized as superior to the claims and liens of the intervenors and to have LNB declared to be entitled to the said property free and clear of all liens and other encumbrances.
After a hearing on the rule, the trial judge concluded that the apartment complex was built as one project, albeit in "two interconnected phases," and that LNB's rights under the Phase II mortgage could not prime those of the lienholding materialmen because the mortgage was not recorded before work had begun on the project, which in his opinion included Phase I. The First Circuit Court of Appeal affirmed the judgment of the trial court.
LNB argues that the lower courts erred in failing to recognize the Phase II job site as distinct from the Phase I construction; under this view, the Phase II mortgage would have a superior rank if recorded before work had begun or materials were supplied to the Phase II job site.
La. R.S. 9:4801 grants a privilege upon immovables to persons furnishing materials *9 for use in construction or improvement of the property with the consent or at the request of the owner. Materialmen's liens, secured in compliance with the provisions of La. R.S. 9:4801, et seq., are superior to the claims of mortgagees unless the mortgages "exist and have been recorded before the work or labor has begun or any material has been furnished." La. R.S. 9:4801(B). The phrase, "before the work or labor is begun or any material [has been] furnished," is defined by La. R.S. 9:4819 (A)(1) and (3) as follows:
"(1) In the event that the work or construction is new, then `work or labor is begun or material is furnished' is defined as having begun when either excavation has been started so that it can be observed on inspection, or material has been furnished and delivered to the job site which is visible upon inspection and which material when delivered had a value in excess of one hundred dollars provided, however, that test piling shall be excluded from this definition.
"* * *
"(3) In any event, if an affidavit, duly signed by an architect, a licensed civil engineer or registered land surveyor, before a notary public, has been filed in the office of the clerk and recorder of the parish in which the property is located or in the case of Orleans Parish, in the mortgage office thereof, which affidavit certifies that he has inspected the job site on a certain date and at a certain time and that no work has begun or material furnished to the building site, either on new construction or on the improvement, repair or reconstruction of existing construction; and such affidavit is filed immediately prior to the filing of a bona fide mortgage or bona fide vendor's lien, or within two business days thereafter, then any lender, including banks, savings and loan associations, life insurance companies, credit unions or other institutional lenders, and other interested parties may rely on the facts recited in said affidavit and shall maintain any and all privileges to and priority over other liens and claims as conferred by Title 9, and particularly, 9:4801, 9:4812, and 9:4813. The filing of such an affidavit will in no wise prejudice the rights of the furnishers of labor or material to file and perfect liens to which they may be entitled, but if materials have been furnished after the affidavit of the engineer, architect or surveyor has been filed, then a materialmen's lien is subordinated to the bona fide mortgage or vendor's lien.
The statute speaks of visible work or material on the "job site" but offers no guidance in delimiting the job site. The engineer's affidavit of March 29, 1973, certified that no work had begun and no materials had been furnished to the 4.29 acre tract which LNB envisioned as the building site. Great pains were taken by the owner and the mortgagee to create two job sites by expressly stating in the mortgage that it was confected solely for the purpose of construction on Phase II, identified as 4.29 acres and depicted by a plat delineating the two-phase division of the mortgaged property.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
345 So. 2d 7, 1977 La. LEXIS 5433, Counsel Stack Legal Research, https://law.counselstack.com/opinion/louisiana-nat-bank-v-triple-r-contractors-inc-la-1977.