Whitaker Construction Co. v. Benton & Brown, Inc. (In Re Whitaker Construction Co.)

411 F.3d 197, 2005 U.S. App. LEXIS 9751, 2005 WL 1253869
CourtCourt of Appeals for the Fifth Circuit
DecidedMay 27, 2005
Docket04-30344
StatusPublished
Cited by13 cases

This text of 411 F.3d 197 (Whitaker Construction Co. v. Benton & Brown, Inc. (In Re Whitaker Construction Co.)) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Whitaker Construction Co. v. Benton & Brown, Inc. (In Re Whitaker Construction Co.), 411 F.3d 197, 2005 U.S. App. LEXIS 9751, 2005 WL 1253869 (5th Cir. 2005).

Opinion

CARL E. STEWART, Circuit Judge:

Whitaker Construction Company, Inc. (“Whitaker”) appeals from the district court’s judgment affirming the bankruptcy court’s grant of summary judgment for Benton & Brown, Inc., LS Decker, Inc., McNeer Electrical Contracting, Inc., Oak Cliff Mirror & Glass, Inc., Overhead Door Company of Shreveport, Inc., Thompson Drywall & Interiors, Inc. (collectively the *200 “Claimants”). Whitaker argues that the bankruptcy court erred in holding that the Claimants timely filed their claim statements. Whitaker contends that the bankruptcy court’s conclusion was based on an erroneous interpretation of the Louisiana Public Works Act, La. Rev. Stat. 38:2241 et seq. For the following reasons, we reverse the ruling of the district court and render judgment for Whitaker.

FACTUAL AND PROCEDURAL HISTORY

On July 19, 2000, Whitaker and the City of Shreveport (the “City”) entered into a standard construction agreement. This construction agreement called for renovations to Independence Stadium, a sports facility owned and operated by the City. The renovations entailed the construction of a “South End Zone Shell Package,” which consisted of concession areas, bathrooms, and club seating in the south end zone of the stadium. Alliance, Inc. (“Alliance”), a Shreveport architectural firm, was designated the project architect. The agreement was recorded in the Caddo Parish public records on July 26, 2000. Fidelity & Deposit Company of Maryland (“Fidelity”) issued a statutory payment bond on behalf of Whitaker, pursuant to the Louisiana Public Works Act, La. Rev. Stat. 38:2241 et seq., guaranteeing that those supplying labor and materials to the project would be paid.

The project was scheduled to be completed by July 31, 2001. By.December 2001, the project had not been completed, nonetheless, on December 27, 2001, the NCAA’s Independence Bowl football game was played in the stadium.

On January 8, 2002, an Alliance representative issued a certificate of substantial completion for the project; representatives for Whitaker and the City signed the document on that same date. The original date of issuance, January 8, 2002, was changed to read December 22, 2001. On January 10, 2002, the certification of substantial completion was filed in the Caddo Parish public records. The City’s endorsement of the document stated that “[t]he Owner [City] accepts the work or designated portion as substantially complete and will assume full possession at noon, 12:00 p.m. (time) on December 22, 2001 (date).” Whitaker’s endorsement stated that “[t]he Contractor [Whitaker] will complete or correct the Work on the list of items attached hereto within thirty (30) days from the above date of Substantial Completion.” However, work on the project continued for the next several months, until at least April 25, 2002.

The Claimants were subcontractors and suppliers to Whitaker on the Independence Stadium project. On June 21, 2002, the first in a series of claim statements were filed on the project by various claimants, all invoking the Public Works Act. Later that year, Whitaker voluntarily petitioned for bankruptcy. Whitaker sent demand letters to claimants requesting that they cancel their claims because Whitaker argued that the claim statements were all untimely filed. Some claimants complied; the Claimants currently before this court are those who refused to cancel their claims.

Whitaker filed this adversary proceeding in bankruptcy court against the Claimants, requesting a declaratory judgment that the Claimants’ claim statements were untimely because they were not filed in the public records within 45 days of the City’s recorded acceptance of the project on January 10, 2002. Whitaker and the Claimants each filed cross-motions for summary judgment on the timeliness issue; the motions centered on the interpretation of § 2241.1 of the Public Works Act. A hear *201 ing on the issue took place on August 11, 2003.

On October 7, 2003, the bankruptcy court denied Whitaker’s motion and claim for attorney’s fees, and granted summary judgment in favor of the Claimants. The bankruptcy court ruled that the City’s recorded acceptance of the project was nullified because the project was not completed within 30 days after the purported substantial completion. The bankruptcy court interpreted § 2241.1 of the Public Works Act to mean that acceptances cannot be recorded “unless either the job is complete or it is substantially complete and actual completion occurs within 30 days.” The bankruptcy court thereby held that the 45-day claim period under the Public Works Act had never begun to run because of the City’s prematurely recorded acceptance. Whitaker appealed this decision to the Western District of Louisiana. The district court adopted the bankruptcy court’s findings and affirmed the judgment. Whitaker timely appealed, claiming legal error in the bankruptcy court’s and the district court’s interpretation of the Public Works Act.

STANDARD OF REVIEW

Rule 7056 of the Federal Rules of Bankruptcy Procedure governs summary judgment in an adversary proceeding in bankruptcy court. Rule 7056 incorporates Rule 56 of the Federal Rules of Civil Procedure. Fed. R. Bank P. 7056. Under Rule 56(c), summary judgment is appropriate only “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed. R. Civ. P. 56(c).

“Bankruptcy court rulings and decisions are reviewed by a court of appeals under the same standards employed by the district court hearing the appeal from bankruptcy court; conclusions of law are reviewed de novo, findings of fact are reviewed for clear error, and mixed questions of fact and law are reviewed de novo.” In re CPDC, Inc., 337 F.3d 436, 441 (5th Cir.2003).

A district court’s determination of state law is also reviewed de novo. Salve Regina College v. Russell, 499 U.S. 225, 231, 111 S.Ct. 1217, 113 L.Ed.2d 190 (1991). In the absence of a final decision by the state’s highest court on the issue at hand, it is the duty of the federal court to determine, in its best judgment, how the highest court of the state would resolve the issue if presented with the same case. Transcon. Gas Pipe Line Corp. v. Transp. Ins. Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tyler Edmonds v. State of Mississippi
234 So. 3d 286 (Mississippi Supreme Court, 2017)
In re Simbaki, Ltd.
522 B.R. 917 (S.D. Texas, 2014)
Nola Ventures, LLC v. Upshaw Insurance Agency, Inc.
48 F. Supp. 3d 916 (E.D. Louisiana, 2014)
Tajonera v. Black Elk Energy Offshore Operations, L.L.C.
16 F. Supp. 3d 755 (E.D. Louisiana, 2014)
Morton v. Kievit (In Re Vallecito Gas, LLC)
461 B.R. 358 (N.D. Texas, 2011)
In Re Hickman
448 B.R. 769 (C.D. Illinois, 2011)
In Re Sharp
394 B.R. 207 (C.D. Illinois, 2008)
Henry v. Duane Morris LLP
210 F. App'x 356 (Fifth Circuit, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
411 F.3d 197, 2005 U.S. App. LEXIS 9751, 2005 WL 1253869, Counsel Stack Legal Research, https://law.counselstack.com/opinion/whitaker-construction-co-v-benton-brown-inc-in-re-whitaker-ca5-2005.