Fidelity & Deposit Co. v. FitzGerald Contractors, Inc.

439 F.3d 212
CourtCourt of Appeals for the Fifth Circuit
DecidedFebruary 1, 2006
Docket04-30598, 05-30074
StatusPublished
Cited by10 cases

This text of 439 F.3d 212 (Fidelity & Deposit Co. v. FitzGerald Contractors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fidelity & Deposit Co. v. FitzGerald Contractors, Inc., 439 F.3d 212 (5th Cir. 2006).

Opinion

PRADO, Circuit Judge:

This appeal is the consolidation of two actions, both of which involve FitzGerald Contractors, Inc. (“FitzGerald”), a subcontractor, seeking compensation under Louisiana’s Private Works Act, La.Rev,Stat. Ann. §§ 9:4801-55 (West 1991 & Supp. 2005) (“PWA”), from Fidelity & Deposit Company of Maryland, Inc. (“F&D”), a surety, for work performed on construction projects in Louisiana. F&D seeks to avoid liability by asserting the defense of peremption under subsection 9:4813(E) of the PWA. Two questions are presented on appeal: (1) whether FitzGerald’s filing of an involuntary bankruptcy petition against the general contractor constituted an “assertion of] claims or rights” under subsection 9:4813(E); and (2) whether the peremption period defined in section 9:4822 is triggered when notice of the construction contract is filed but notice of termination is not. Answering both questions in the negative, the district court found for F&D in the Biomedical Project matter and FitzGerald in the Lifeshare Project matter. For the reasons below, we AFFIRM.

I. Background

Whitaker Construction Company, Inc. (“Whitaker”), as contractor, entered into a standard-form construction contract with the Biomedical Research Foundation of Northern Louisiana, as owner, to build a biotechnology manufacturing facility in Shreveport, Louisiana (“Biomedical Project”). The contract was entered into the Caddo Parish, Louisiana mortgage books on April 28, 2000. It required Whitaker to furnish surety bonds guaranteeing payment to subcontractors. F&D, as surety, issued bonds with a penal sum of $9,755,904.00 on April 25, 2000.

Whitaker, as contractor, also entered into a contract with Blood Center Properties, Inc., as owner, to build a facility for Lifeshare Blood Centers in Shreveport, Louisiana (“Lifeshare Project”). This contract was entered into the Caddo Parish mortgage books on July 27, 2000. It also required Whitaker to furnish a surety bond. F&D, again as surety, issued a bond in the amount of $3,541,953.00 on July 26, 2000. For both the Biomedical and Lifeshare projects, the contracts were recorded and the bonds issued pursuant to the PWA.

Effective August 24, 2000, Whitaker and FitzGerald executed two subcontracts, one relating to the Biomedical Project and one to the Lifeshare Project, in each of which FitzGerald agreed to perform work on the facility.

For the Biomedical Project, a Certificate of Substantial Completion was recorded on September 17, 2001 in the mortgage records for Caddo Parrish. For the Lifes-hare Project, no official filing was made regarding completion, though other events occurred that suggest the project was completed: on June 29, 2001, the Estopinal Group, architect for the project, compiled a punchlist; minutes of the Lifeshare Project progress meetings indicate the facility was ready to be occupied between July 23 and 26; and, on July 25, the City of Shreveport issued a certificate of occupancy.

II. Procedural History

On August 9, 2002, FitzGerald and two other creditors filed an involuntary bankruptcy petition against Whitaker in bankruptcy court in the Western District of Louisiana. The standard Form B5 filing had the following information: (1) Whitaker’s identity as debtor; (2) the nature of Whitaker’s business as general contractor; *215 (3) the amount FitzGerald was owed, $586,258.17, including liened amounts of $418,596.58 and un-liened amounts of $167,661.59; (4) that the petition was being filed under Chapter 7 of the Bankruptcy Code; and (5) an assertion of petitioners’ eligibility to file under 11 U.S.C. § 303(b). It did not invoke the PWA nor mention specifically amounts owed under it. 1

On August 19, 2002, F&D filed a notice of appearance in the Whitaker bankruptcy proceeding. On September 6, Whitaker filed an answer to the involuntary petition and a Motion to Convert Case to Chapter 11 Proceeding with a corresponding memorandum in support. On September 12, the bankruptcy court granted the Order of Relief for the involuntary petition and converted the matter to a voluntary Chapter 11 case. On January 9, 2003, FitzGerald filed its proof, of claim for all of its claims, liened and un-liened, in the Chapter 11 bankruptcy proceeding.

Regarding the Biomedical Project, Fitz-Gerald filed an adversary complaint in the bankruptcy court on April 16, 2003, naming F&D as defendant. In its complaint, FitzGerald alleged that F&D was liable as surety for payment of $82,473.89 plus interest for amounts Whitaker failed to pay FitzGerald for work it completed on the Biomedical Project. On May 16, F&D answered the complaint, denying FitzGer-ald’s allegations and asserting the defense of peremption. On June 19, F&D moved for summary judgment; FitzGerald made a cross-motion for summary judgment or, alternatively, partial summary judgment. After hearing argument, the bankruptcy court granted FitzGerald’s motion for summary judgment in part, and denied F&D’s motion. It determined that the involuntary bankruptcy petition was a timely assertion of rights within the meaning of § 9:4813(E) and that the bankruptcy filing did not stay FitzGerald’s rights under the PWA. The bankruptcy court entered judgment on September 2.

F&D appealed to the district court on September 3, 2003. The district court determined that the involuntary bankruptcy petition was not an assertion of rights for purposes of subsection 9:4813(E). It reversed the bankruptcy court’s judgment with respect to this issue and affirmed its judgment with respect to finding that the bankruptcy filing did not stay FitzGerald’s rights. The district court issued its final judgment on May 26, 2004. FitzGerald appealed on June 17, 2004, challenging the district court’s determination regarding the involuntary bankruptcy petition in the Biomedical matter.

Regarding the Lifeshare Project, Fitz-Gerald filed an adversary complaint in the bankruptcy court on July 16, 2003, naming F&D as defendant. In it, FitzGerald alleged that F&D was liable as surety for payment of $81,689.00 plus interest for amounts Whitaker failed to pay FitzGerald for work it completed on the Lifeshare Project. On August 6, F&D answered the complaint, denying FitzGerald’s allegations and asserting the defense of peremption. On October 2, FitzGerald moved for summary judgment or, alternatively, partial summary judgment. On January 9, 2004, F&D filed a cross-motion for summary judgment. After hearing argument, the bankruptcy court granted FitzGerald’s motion for summary judgment in part, and denied F&D’s motion. As in the Biomedical matter, it determined that the involuntary bankruptcy petition was a timely assertion of rights within the meaning of the *216 PWA. The bankruptcy court also held that, because no certificate of substantial completion was filed for the Lifeshare Project, subsection 9:4822(0) applied, establishing a peremption period of one year and sixty days. The bankruptcy court entered judgment on March 26.

F&D appealed to the district court, the same court as in the Biomedical matter, on March 29, 2003.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
439 F.3d 212, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fidelity-deposit-co-v-fitzgerald-contractors-inc-ca5-2006.