Mécanique C.N.C., Inc. v. Durr Environmental, Inc.

304 F. Supp. 2d 971, 52 U.C.C. Rep. Serv. 2d (West) 832, 2004 U.S. Dist. LEXIS 1664, 2004 WL 232764
CourtDistrict Court, S.D. Ohio
DecidedFebruary 9, 2004
Docket2:01-cv-01216
StatusPublished
Cited by27 cases

This text of 304 F. Supp. 2d 971 (Mécanique C.N.C., Inc. v. Durr Environmental, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mécanique C.N.C., Inc. v. Durr Environmental, Inc., 304 F. Supp. 2d 971, 52 U.C.C. Rep. Serv. 2d (West) 832, 2004 U.S. Dist. LEXIS 1664, 2004 WL 232764 (S.D. Ohio 2004).

Opinion

OPINION AND ORDER

MARBLEY, District Judge.

I. INTRODUCTION

This matter is before the Court on the Motion for Partial Summary Judgment filed by Defendants Durr Environmental, Inc. (“Durr”), and Liberty Mutual Insurance Company (“Liberty Mutual”). 1 Jurisdiction is proper pursuant to 28 U.S.C. *973 § 1332. For the following reasons, the Court GRANTS Defendants’ Motion.

II. BACKGROUND

Durr entered into a contract with Defendant GE Quartz, Inc. (“GE”), to engineer, design, construct, manufacture, assemble, install, start up, and test a Selective Catalytic Reduction (“SCR”) System at GE’s plant in Hebron, Ohio (the “Job Site”). The SCR System is used to control the emission of nitrogen oxides into the atmosphere, subject to certain permits and state and federal environmental regulations.

Plaintiff, Mécanique C.N.C., Inc. (“CNC”), was one of Durr’s subcontractors on the project. Negotiations for CNC to fabricate and install ductwork and related equipment for the SCR System began in July 2000. The negotiations occurred via telephone, facsimile, and email between Durr’s offices in Wixom, Michigan, and CNC’s offices in Varennes, Quebec, Canada. The work was to consist of the fabrication, coating, insulation, and installation of metal and stainless steel in connection with the SCR System.

Pursuant to CNC’s version of the contract formation, on August 3, 2000, CNC submitted a bid to Durr outlining the work and price (the “August 3, 2000, Letter”). 2 Durr then submitted to CNC an executed proposed subcontract agreement (the “Subcontract”), labeled “Subcontract No. 82410.22336.SC” and, dated August 2, 2000. 3 The Subcontract referenced certain “Contract Documents,” but the documents were not attached. Thereafter, CNC added three handwritten notes to the Subcontract, signed it, and forwarded it to Durr. The first handwritten note attempted to add to the “Contract Documents” section of the Subcontract the August 3, 2000, Letter. The second handwritten addition attempted to shift the obligation to supply tools from CNC to Durr. The third addition attempted to change the “Payment Terms” from “Subcontractor to Invoice monthly based on percentage of material delivered and installed at jobsite” to “Subcontractor to Invoice monthly based on material purchased and received in our shop.”

Following receipt of the executed Subcontract with the handwritten additions, Rob Cox, an employee of Durr, sent CNC a revised Subcontract on both August 4, 2000, and August 9, 2000. This revised Subcontract included the substance of CNC’s additions regarding invoicing but did not include the other two proposed changes. CNC never executed either copy of the revised Subcontract. In a letter dated October 30, 2000, Cox informed CNC that the “alterations” made the Subcontract “null and void.” 4

Both parties commenced and continued performance without regard to the dispute over the contract. CNC began fabrication in August 2000 at its facilities in Montreal. CNC also coated some of the fabricated work in Montreal. CNC acknowledges that this work was performed in accordance with directions from Durr and GE. While the work was being performed, two “kick off’ meetings occurred. One occurred at Durr’s facility in Wixom, Michigan, and the other at the Job Site. Subse *974 quently, representatives of both Durr and GE traveled to Montreal to inspect the fabrication and coating work being performed by CNC. During this time period, CNC corresponded with Durr, obtained surety bonds, and requested and received payment, all referencing the Subcontract and/or the Subcontract number. In a letter from CNC to Durr dated March 9, 2001, CNC also apparently referenced the Subcontract. 5

In approximately September 2000, CNC commenced delivery of the fabrication work to the Job Site. CNC also began assembly of the fabricated steel, which was inspected at the Job Site by representatives of both Durr and GE. Localized problems with certain coating were then ascertained at the Job Site. CNC received new procedures from Durr at that time, and CNC commenced refinishing certain fabrication on site in Hebron. This re-work conducted at the Job Site caused certain delays and substantial additional costs to CNC. The parties have both factual and legal disputes relating to the re-work and to subsequent actions taken by the parties, as well as justifications for those actions. According to CNC, Durr later unilaterally amended the work schedule and imposed an arbitrary deadline on CNC. Notwithstanding, CNC was on schedule to complete the work within the given time. Pri- or to the deadline, however, in March 2001 CNC was terminated. Durr claimed to be unhappy with the progress of the work; however, CNC believes it was terminated because it had demanded compensation for its damages resulting from, among other things, the re-work. After CNC’s termination, Durr directly contracted with one of CNC’s subcontractors to complete the work.

On December 7, 2001, CNC brought suit against Durr, Liberty Mutual, 6 and GE. In its Complaint, CNC alleges the following causes of action against Durr: (1) breach of contract; (2) delay, inefficiency, and increased overhead damages; (3) violation of section 4113.61 of the Ohio Revised Code; (4) quantum meruit and unjust enrichment; (5) wrongful termination and nonperformance; (6) cardinal change and contract modification; and (7) breach of duty of good faith and fair dealing. CNC seeks to recover from Liberty Mutual based on breach of payment bond. CNC alleges a cause of action against GE for quantum meruit and unjust enrichment. In an additional Count of its Complaint, CNC seeks foreclosure of a mechanics’ lien.

This matter is before the Court on Defendants Durr and Liberty Mutual’s Motion for Partial Summary Judgment. Pursuant to Rule 56 of the Federal Rules of Civil Procedure, Defendants ask this Court to hold that the governing contract between Durr and CNC was the Subcontract, rather than, as Plaintiff contends, the August 3, 2000, Letter.

III. STANDARD OF REVIEW

Summary judgment is appropriate “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(c). The movant has the *975 burden of establishing that there are no genuine issues of material fact, which may be accomplished by demonstrating that the non-moving party lacks evidence to support an essential element of its case. Celotex Corp. v. Catrett,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
304 F. Supp. 2d 971, 52 U.C.C. Rep. Serv. 2d (West) 832, 2004 U.S. Dist. LEXIS 1664, 2004 WL 232764, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mecanique-cnc-inc-v-durr-environmental-inc-ohsd-2004.