Conco, Inc. v. Napco Precast, LLC

CourtDistrict Court, D. Kansas
DecidedJanuary 30, 2026
Docket6:24-cv-01078
StatusUnknown

This text of Conco, Inc. v. Napco Precast, LLC (Conco, Inc. v. Napco Precast, LLC) is published on Counsel Stack Legal Research, covering District Court, D. Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Conco, Inc. v. Napco Precast, LLC, (D. Kan. 2026).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF KANSAS

CONCO, INC.,

Plaintiff,

v. Case No. 24-01078-JWB

NAPCO PRECAST, LLC,

Defendant.

MEMORANDUM AND ORDER

This matter is before the court on cross motions for summary judgment. (Docs. 83, 85.) The motions are fully briefed and ripe for decision. (Docs. 84, 86, 87, 88, 90, 97, 98.) Plaintiff’s motion for summary judgment is DENIED and Defendant’s motion for summary judgment is GRANTED for the reasons stated herein. I. Facts

This case belongs in a first-year law student’s contracts textbook. The parties before the court quarrel over the proper application of some of the most foundational principles of contract law. Plaintiff Conco, Inc. (hereinafter “Conco” or “Plaintiff”) is a general contractor based in Wichita, Kansas. (Doc. 81 at 2.)1 In 2021, Conco was selected to be the prime contractor on the construction of the Lumen apartment complex in Bentonville, Arkansas. (Id. at 4, 2.) As part of its bid on the apartment complex, Conco entered negotiations with Defendant NAPCO Precast, LLC (hereinafter “NAPCO” or “Defendant”) for a subcontract under which NAPCO would construct a parking garage. (Id. at 2-3.) NAPCO is based in San Antonio, Texas. (Id. at 2.)

1 The court notes that all page number citations to the record reference the ECF-assigned pagination at the top of each page of documents filed with the court. The parties’ interactions began when Conco decided that, as part of its design for the garage, it would use precast concrete slabs instead of post-tensioned concrete. (Id.) This was done as a cost saving measure. (Id.) Precast concrete involves the fabrication of “component pieces specific to the requirements of a particular [p]roject” through “forms or molds” with “reinforcement . . . placed within.” (Id.) After the slabs are “cur[ed]” each slab is transported to

the job side and “erect[ed].” (Id.) This stands in contrast to post-tensioned concrete, which is poured around steel wires. (Id.) The steel wires are “tensioned” after the concrete has “gained sufficient strength.” (Id.) Defendant NAPCO Precast, hence the name, produces precast concrete structures. (Id.) On February 2, 2021, Conco contacted Mark Carr, a NAPCO employee, to begin discussing a possible NAPCO bid for the precast work. (Id.) In the ensuing spring and summer, Conco and NAPCO exchanged information to begin crafting “estimates and proposals” for the project. (Id.) On June 9, 2021, Carr sent Conco its first proposal for the parking garage. (Id. at 3.) The total value of the proposal was for $1,984,500.00. (Id.) Carr submitted a revised proposal

for $1,667,000.00 on June 24, 2021. (Id.) NAPCO was the only precast contractor to submit a bid on the project at this stage. (Id.) Still, in August 2021, Conco did receive an estimate from another contractor, Coreslab, to enable Conco to cost check NAPCO’s proposal. (Id.) Finally, on September 9, 2021, Mark Carr submitted another proposal to Conco totaling $1,698,260.00. (Id.) The proposal included an option for an additional $227,570.00 for NAPCO to build a “precast ramp” into the parking garage. (Id.) The proposal contained “information regarding the scope of work, terms, conditions, and details as set forth in the document itself, including but not limited to the express term that the [] proposal was ‘valid for 60 days.’” (Id.) In theory, this would mean that the last day Conco could accept would be November 8, 2021. See (id.) Conco, relying upon NAPCO’s proposal, submitted a bid for the prime contract at the apartment complex that included a $1,698,260.00 cost item for the parking garage. (Id.) From this time through November 2021, Conco negotiated with the apartment complex’s project owner. (Id.) Multiple proposals were “revis[ed] and resubmit[ed]” by Conco to the owner during this period. (Id.) Those prime contract proposals relied upon NAPCO’s September 9, 2021,

subcontract proposal. (Id. at 3-4.) On “November 9, 2021, the 60-day period stated in the [September 9, 2021, NAPCO subcontract] proposal as to how long the proposal was valid expired without any communication from Conco to Carr accepting the proposal.” (Id. at 4.) On that day, Carr followed up with Conco. (Id.) No response was received until November 18, 2021. (Id.) Conco replied that it was still “working through contract negotiations with the owner” and was “[h]oping to have [its] contract executed in the next couple weeks.” (Id.) Conco also advised that at that point it would “get the schedule dialed in and start working on our subcontractor/vendor commitments.” (Id.) Carr replied to Conco asking if NAPCO could receive something in writing, like a letter of

intent, to indicate that Conco was committing to NAPCO as its subcontractor for the parking garage. (Id.) Carr specifically indicated that he needed this “by or before the end of December” to “hold pricing.” (Id.) “Conco did not respond in writing to this email or [NAPCO’s] proposal until January 2022.” (Id.) Conco was eventually awarded the apartment complex’s prime contract on December 2, 2021. (Id.) The prime contract included a cost line item for “Parking Garage Precast” valued at $1,698,260.00. (Id.) The apartment complex was scheduled to be completed by November 12, 2023. (Id.) Conco did not inform NAPCO that it had been awarded the prime contract until over a month had passed. (Id.) On January 4, 2022, NAPCO’s Mark Carr wrote to Conco asking for an update. (Id.) It was then that Conco’s project manager Robert Davis, wrote back saying that Conco had “a signed contract with the owner.” (Id.) Davis told Carr that Conco was awaiting the release of funding, at which point a letter of intent would be issued while the parties finalized a subcontract. (Id.) Carr replied ebulliently. (Id. at 4-5.) Later, a design change required that NAPCO update its price. (Id. at 5.) On January 17,

2022, Conco told Carr that the funding had been received and asked NAPCO to “accept this email as our letter of intent to award this project to you.” (Id.) Conco also asked NAPCO to “please begin [the detailed] design process ASAP.” (Id.) Conco further asked NAPCO to “[p]lease clean up your number to eliminate the exterior ramp and place it internal[]”, and told NAPCO that as soon as he received NAPCO’s updated price he would issue the subcontract. (Doc 84-11 at 2.) On February 2, 2022, NAPCO sent Conco a new proposal totaling $1,860,118.00 plus an optional addition of $136,776.79 for a mechanical room. (Doc. 81 at 5.) On the same day, Davis responded2 saying “[f]rankly, the $160k add to the main garage is a problem.” (Id.) Conco’s budget anticipated that the aforementioned design changes would “reduce” the price. (Id.) On

February 15, 2022, Conco followed up with NAPCO, asking “[w]here do we stand on improving the number here.” (Id.) On March 15, 2022, NAPCO sent Conco a “Notice to Proceed” for the design work for “Drafting and Calculation work necessary to provide Gravity Loads.” (Id.) On March 21, 2022, Davis signed this notice on behalf of Conco and returned it to NAPCO and noted “subcontract coming this week.” (Id.) On April 5, 2022, NAPCO sent Conco various submissions as part of their design work. (Id.) On May 16, 2022, NAPCO sent Conco links to NAPCO’s “calculations, drawings, and sections for review and approval.” (Id.) NAPCO then invoiced Conco $50,877.67

2 The stipulated fact in the pretrial order says “Carr responded” but that would make no sense given the context, so the court assumes that the parties meant Davis, Conco’s project manager. for engineering services. (Id. at 6.) Conco paid NAPCO $46,377.67 for those services. (Id.) NAPCO sent a receipt on June 24, 2022, for this payment. (Id.) On June 16, 2022, NAPCO sent Conco a change order that increased the price of its proposal for the parking garage to $2,703,210.00.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Lifewise Master Funding v. Telebank
374 F.3d 917 (Tenth Circuit, 2004)
Coleman v. Blue Cross Blue Shield of Kansas, Inc.
287 F. App'x 631 (Tenth Circuit, 2008)
Mohr v. State Bank of Stanley
770 P.2d 466 (Supreme Court of Kansas, 1989)
Weil & Associates v. Urban Renewal Agency
479 P.2d 875 (Supreme Court of Kansas, 1971)
Steele v. Harrison
552 P.2d 957 (Supreme Court of Kansas, 1976)
Drennan v. Star Paving Co.
333 P.2d 757 (California Supreme Court, 1958)
Care Display, Inc. v. Didde-Glaser, Inc.
589 P.2d 599 (Supreme Court of Kansas, 1979)
Berryman v. Kmoch
559 P.2d 790 (Supreme Court of Kansas, 1977)
Belmont Industries, Inc. v. Bechtel Corp.
425 F. Supp. 524 (E.D. Pennsylvania, 1976)
US Fid. & Guar. Co. v. N. Am. Steel Corp.
335 So. 2d 18 (District Court of Appeal of Florida, 1976)
Standard Structural Steel Co. v. Debron Corp.
515 F. Supp. 803 (D. Connecticut, 1980)
Nicholson v. Hartnett
277 P.3d 1193 (Court of Appeals of Kansas, 2012)
Levinson Steel Co. v. SCHIAVONE CONST. CO., INC.
637 F. Supp. 164 (S.D. New York, 1986)
Golden v. Den-Mat Corp.
276 P.3d 773 (Court of Appeals of Kansas, 2012)
M West, Inc. v. Oak Park Mall, L.L.C.
234 P.3d 833 (Court of Appeals of Kansas, 2010)
Mécanique C.N.C., Inc. v. Durr Environmental, Inc.
304 F. Supp. 2d 971 (S.D. Ohio, 2004)
Wachter Management Co. v. Dexter & Chaney, Inc.
144 P.3d 747 (Supreme Court of Kansas, 2006)
Short v. Sunflower Plastic Pipe, Inc.
500 P.2d 39 (Supreme Court of Kansas, 1972)
Bouton v. Byers
321 P.3d 780 (Court of Appeals of Kansas, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Conco, Inc. v. Napco Precast, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/conco-inc-v-napco-precast-llc-ksd-2026.