Belmont Industries, Inc. v. Bechtel Corp.

425 F. Supp. 524, 20 U.C.C. Rep. Serv. (West) 1196, 1976 U.S. Dist. LEXIS 11909
CourtDistrict Court, E.D. Pennsylvania
DecidedDecember 10, 1976
DocketCiv. A. 75-1743
StatusPublished
Cited by17 cases

This text of 425 F. Supp. 524 (Belmont Industries, Inc. v. Bechtel Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Belmont Industries, Inc. v. Bechtel Corp., 425 F. Supp. 524, 20 U.C.C. Rep. Serv. (West) 1196, 1976 U.S. Dist. LEXIS 11909 (E.D. Pa. 1976).

Opinion

MEMORANDUM AND ORDER

BECHTLE, District Judge.

Presently before the Court is defendants’ motion for summary judgment, pursuant to Fed.R.Civ.P. 56, in this diversity action. Defendants’ primary contention is that this is an action for breach of a contract for sale within the meaning of the Uniform Commercial Code, as enacted in Pennsylvania, and that, accordingly, the suit is time-barred by the applicable four-year statute of limitations found at 12A P.S. § 2-725 (1970). For the reasons stated below, the Court agrees with defendants an} will grant their motion.

The material facts relevant to this motion, undisputed except as to their legal significance, are as follows: In early 1969, Bechtel Corporation (“Bechtel”), through Bechtel Constructors, Inc. (“Bechtel Constructors”), was engaged by Union Carbide Corporation (“Union Carbide”) as general contractor for the construction of a petrochemical complex near Ponce, Puerto Rico. On June 9, 1969, Bechtel Constructors issued an invitation for bids to furnish and install, on a “turnkey” basis, the container handling system at the Union Carbide complex’s marine facility. Badrena & Perez, Inc. (“B&P”), submitted its bid on August 15, 1969. That bid anticipated the erection of a large steel structure, to be used in loading and unloading ships, composed of a crane runway, over which would run a crane assembly, and a movable apron extending over the water. Belmont Iron Works (“Belmont”), a division of plaintiff Belmont Industries, Inc., was to design the structure, fabricate the steel for it and deliver the steel to B&P in Puerto Rico. Other subcontractors to B&P were to erect the structure, supply the crane assembly, supply the controls system, sandblast and paint the steel, as well as provide additional work and materials.

At a “pre-award” meeting on January 22, 1970, the proposed contract between Bechtel Constructors and B&P was discussed in detail and B&P was advised shortly thereafter that it was the successful bidder. A subcontract was sent by Bechtel Constructors to B&P on March 23; 1970. On April 16, 1970, B&P sent a proposed sub-subcontract to Belmont. That document provided that Belmont would “supply all steel structures at job site . . . ” 1 for a lump-sum price of $338,420. [Ex. D-78.] Although several letters were subsequently exchanged between B&P and Belmont regarding its terms, Belmont never returned the executed sub-subcontract to B&P. Nevertheless, on the assumption that there • was some kind of agreement with B&P, Belmont continued to take actions apparently directed towards fulfillment of that-agreement concerning the container handling facility. 1

In early July, 1970, Belmont advised representatives of B&P, Bechtel and Union Carbide that, due to disagreement over the employment of a consulting engineer, it could not continue to accept design responsibility for the structure. Belmont would thereafter act only as a material supplier, fabricating in accordance' with plans and specifications submitted by others. On July 22, 1970, Belmont sent B&P a proposed sub-subcontract pursuant to which Belmont would be obligated “solely to [sic ] the prep *526 aration of shop detail drawings from plans and specifications submitted by others and the fabrications [sic] and delivery of structural steel based thereon.” [Ex. D-34.] Belmont’s compensation was still to be a lump-sum payment of $338,420. 2 The proposed sub-subcontract was apparently never signed. However, despite the absence of a written contract, Belmont was doing work as a supplier for the project as late as October 26, 1970.

In mid-October, 1970, B&P encountered financial difficulties and asked to be allowed to withdraw from its subcontract with Bechtel. The Bechtel-B&P subcontract was formally terminated on October 24, 1970.

On November 9, 1970, Bechtel sent a letter to Belmont asking Belmont to enter into a contract directly with Bechtel, on a purchase order basis, for the fabrication and delivery of the steel for the container handling facility. The price terms of the proposed contract would be the same as had been agreed between Belmont and B&P. On November 10, 1970, Bechtel informed Belmont by letter that if it would not agree to transfer its original obligation, on the same terms, from B&P to Bechtel, it would be free to make a new proposal pursuant to the open bid request which had been sent to other steel fabricators the previous day. Bechtel and Belmont were unable to reach agreement on a price for the transfer contract. On November 24, 1970, Bechtel entered into an agreement with Owen Steel Company (“Owen”) pursuant to which Owen would provide the steel for the container handling facility. Belmont was aware of Bechtel’s agreement with Owen by early December, 1970.

Based upon this series of events, Belmont filed a three-count complaint on June 18, 1975. The first count sets forth a claim for breach of contract and requests both compensatory and punitive damages. The second count sets forth a claim for a quantum meruit recovery based on the same agreement alleged in Count I. 3 The third count of the complaint, which seeks compensatory and punitive damages, alleges that defendants “wilfully and maliciously concealed from the fabricator they selected to replace Belmont, knowledge of Belmont’s procurement of the specially manufactured materials. This act of concealment was committed with the intent to, and with the effect of, denying Belmont the opportunity to sell said material to that fabricator.”

For purposes of this motion, defendants concede that any contractual obligations which existed ran between Belmont and defendants, rather than Belmont and B&P, and they do not contend at this time that there was no agreement between the parties.

Before addressing the issue of the applicability of the statute of limitations for actions on sales contracts to this case, several preliminary observations should be made. First, the Court agrees with defendants that Count III of the complaint fails to state a claim upon which relief can be granted. Plaintiff has cited no authority, and the Court is unaware of any, which suggests that defendants’ alleged actions constitute an independently recognizable cause of action. Rather, Count III simply alleges that defendants “wilfully and maliciously” prevented plaintiff from mitigating damages which resulted from defendants’ alleged breach of contract. 4 Proof of *527 such a claim would affect the amount of damages recoverable if a breach of contract by defendants is established, but would not entitle plaintiff to a separate award independent of the contract action.

Count II also fails to state a claim upon which relief can be granted. A quantum meruit action is appropriate to recover the value of services performed and accepted on the basis of a contract for those services which left unspecified what the compensation would be. See Lach v. Fleth, 361 Pa.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SnowWolf v. Iacovazzi
M.D. Pennsylvania, 2024
First Mercury Insurance v. Westchester Surplus Lines Ins.
152 F. Supp. 3d 1320 (D. Oregon, 2016)
Feingold v. Win-Vent, Inc.
562 A.2d 830 (Superior Court of Pennsylvania, 1989)
In Re Moore & White Co., Inc.
83 B.R. 277 (E.D. Pennsylvania, 1988)
California & Hawaiian Sugar Co. v. Sun Ship, Inc.
794 F.2d 1433 (Ninth Circuit, 1986)
Barkley v. Lawrence County
35 Pa. D. & C.3d 491 (Lawrence County Court of Common Pleas, 1982)
Lobianco v. Property Protection, Inc.
437 A.2d 417 (Superior Court of Pennsylvania, 1981)
Standard Structural Steel Co. v. Debron Corp.
515 F. Supp. 803 (D. Connecticut, 1980)
Harkins v. Zamichieli
405 A.2d 495 (Superior Court of Pennsylvania, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
425 F. Supp. 524, 20 U.C.C. Rep. Serv. (West) 1196, 1976 U.S. Dist. LEXIS 11909, Counsel Stack Legal Research, https://law.counselstack.com/opinion/belmont-industries-inc-v-bechtel-corp-paed-1976.