Urban Industries of Ohio, Inc. v. Tectum, Inc.

612 N.E.2d 382, 81 Ohio App. 3d 768, 20 U.C.C. Rep. Serv. 2d (West) 1193, 1992 Ohio App. LEXIS 3744
CourtOhio Court of Appeals
DecidedJuly 14, 1992
DocketNo. 3-91-41.
StatusPublished
Cited by7 cases

This text of 612 N.E.2d 382 (Urban Industries of Ohio, Inc. v. Tectum, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Urban Industries of Ohio, Inc. v. Tectum, Inc., 612 N.E.2d 382, 81 Ohio App. 3d 768, 20 U.C.C. Rep. Serv. 2d (West) 1193, 1992 Ohio App. LEXIS 3744 (Ohio Ct. App. 1992).

Opinion

Hadley, Presiding Judge.

Defendant-appellant, Tectum, Inc. (“Tectum”), appeals from a judgment entry in the Crawford County Court of Common Pleas, granting a directed verdict in favor of plaintiff-appellee, Urban Industries of Ohio, Inc. (“Urban”).

This action was commenced on February 1, 1990, by the filing of appellee’s complaint, whereby it sought payment for lamination services performed for appellant. Appellant counterclaimed, seeking damages for two separate claims. The first claim related to a project Tectum contracted to perform in Hamden, Connecticut called the Church Street School Project (“CSS Project”). *770 The causes of action relating to the CSS Project included breach of warranty and negligence, based upon the doctrine of res ipsa loquitur, for work that Urban performed for Tectum. The second claim involved three other construction projects that Tectum subcontracted to Urban to perform.

Urban agreed to perform certain work for Tectum for the CSS project in June 1989, including producing roof-deck panels. This product consists of three materials, waferboard, styrofoam, and tectum substrate, laminated in a sandwich fashion. Tectum supplied the materials for the roof-deck panels to Urban. It was also noted by the trial court during his ruling from the bench that the instructions and guidelines for applying the adhesive and compressing the materials were given by Tectum and Morton-Thiokol, the supplier of the glue.

During the lamination process, adhesive was applied to both sides of the styrofoam, the two outer products were placed on each side of the styrofoam, and then all three products were vacuum-pressed together by Urban. Tectum specified to Urban the thickness of the adhesive to the applied, the pressure of the vacuum, and that only one of two types of adhesive could be applied. Further, Urban was not to exceed the recommendation of Morton-Thiokol for “open time.” 1 After the application of the vacuum pressure, Urban trimmed the roof deck panels to ensure that they were in proper alignment. 2

During Tectum and Urban’s business relationship, which began in 1988, Urban intermittently reported a quality-control problem to Tectum concerning some tectum panels supplied by Tectum. As late as April 1989, Urban complained to Tectum during a meeting of the two companies that there were problems with the surface of the tectum boards supplied to Urban for lamination. Urban stated that some of the tectum surfaces were uneven and/or concave. There was an implication at trial that this problem with the tectum surface may have resulted in problems for Urban during lamination. However, it was also stated by a Tectum representative that even if the tectum board had been uneven or warped in some manner, vacuum pressing would still have compressed the tectum into the adhesive. 3

In June 1989, Urban received the order and materials to do the CSS project for Tectum. Within a few days, the order was completed and Urban shipped *771 the completed roof-deck panels directly to the CSS project job site. In early February 1990, it was discovered that several of the panels had delaminated, causing a critical problem because these panels were designed to be supporting structures. Tectum made an initial inspection of the roof at the CSS project on February 20, 1990. Pursuant to this inspection, Tectum notified Urban that Urban could inspect the job site and that in the opinion of Tectum’s vice-president, the delamination problem had occurred as a result of excessive open time. Tectum also informed Urban that the architect and engineer on the CSS project were demanding replacement of the delaminated panels or testing of the panels that had not failed. The evidence indicates that Urban did not make an inspection of the CSS project job site.

There was testimony at the trial that Tectum’s vice-president, John Carlson, sent a letter dated May 4, 1990, to Anthony Garcia of R.V. Civitello, the general contractor for the CSS project, stating that it was Tectum’s position that the delamination had occurred possibly because of improper handling of the panels during storage or moving or improper nailing during installation. There was no mention that the delamination could have resulted from excessive open time.

Due to the failure of some of the panels, the entire roof of the school had to be replaced. Urban denied liability for the delamination of the panels and, therefore, Tectum hired a subcontractor to perform the replacement work. As in its arrangement with Urban, Tectum supplied the panels to the replacement subcontractor to be laminated. There is no evidence that any of these panels supplied by the subsequent subcontractor delaminated.

The three other construction projects, which compose appellant's second claim for relief, occurred after the CSS project. These projects were the Woodland School project, the Holy Rosary School project, and the York College of Pennsylvania project. Evidence at trial indicated that Urban performed work, lamination and/or alignment, for these projects and that problems occurred with each of these three projects. However, Tectum did not notify Urban until after replacement work had been completed that there was a problem possibly relating to the work that Urban had done and that replacement had been necessary to conform the work to the contractor’s requirements.

Upon completion of appellant’s case in chief, appellee moved for a directed verdict against both of appellant’s claims for relief. At this time during the jury trial, the trial judge concluded that he would grant the directed verdict only as to the CSS project. During appellee’s case in chief, the trial judge granted a directed verdict against appellant on its second claim for relief. The October 7,1991 judgment entry of the trial court reflected that a directed *772 verdict had been directed in favor of Urban. It is from this judgment entry that appellant appeals, asserting two assignments of error.

Assignment of Error No. 1

“The trial judge erred in directing a verdict on Tectum’s counterclaim for damages caused by the delamination of Tectum III roof-deck panels on the Church Street School project.”

This assignment of error addresses the directed verdict motion as to the CSS project. Significant to this assignment of error is appellant’s argument that this claim for relief is based upon res ipsa loquitur. This doctrine of negligence has been defined as:

“ * * * a rule of evidence which permits the jury to draw an inference of negligence where the instrumentality causing the injury is under the exclusive management and control of the defendant and the accident occurs under such circumstances that in the ordinary course of events it would not occur if ordinary care were observed.” (Citations omitted.) 70 Ohio Jurisprudence 3d (1986) 295-296, Negligence, Section 157.

Although appellant did not specifically state in its counterclaim that the doctrine of res ipsa loquitur

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alcala v. Verbruggen Palletizing Solutions, Inc.
531 P.3d 1085 (Idaho Supreme Court, 2023)
H & C Ag Servs., L.L.C. v. Ohio Fresh Eggs, L.L.C.
2015 Ohio 3714 (Ohio Court of Appeals, 2015)
Mueller v. All-Temp Refrig., Inc.
2014 Ohio 2718 (Ohio Court of Appeals, 2014)
State v. Johnson, Unpublished Decision (8-11-2004)
2004 Ohio 4295 (Ohio Court of Appeals, 2004)
Mécanique C.N.C., Inc. v. Durr Environmental, Inc.
304 F. Supp. 2d 971 (S.D. Ohio, 2004)
C.J. Mahan Construction Co. v. Valspar Corp.
30 F. App'x 381 (Sixth Circuit, 2002)
Ankle & Foot Care Centers v. Infocure Systems, Inc.
164 F. Supp. 2d 953 (N.D. Ohio, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
612 N.E.2d 382, 81 Ohio App. 3d 768, 20 U.C.C. Rep. Serv. 2d (West) 1193, 1992 Ohio App. LEXIS 3744, Counsel Stack Legal Research, https://law.counselstack.com/opinion/urban-industries-of-ohio-inc-v-tectum-inc-ohioctapp-1992.