This text of 338 A.2d 275 (Mayor of Federalsburg v. Allied Contractors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mayor of Federalsburg v. Allied Contractors, Inc., 338 A.2d 275, 275 Md. 151 (Md. 1975).

Opinion

*153 Digges, J.,

delivered the opinion of the Court.

The appellee, Allied Contractors, Inc., initiated this suit in the Circuit Court for Caroline County against the appellant, the Mayor and Council of Federalsburg, Maryland, a municipal corporation, for moneys Allied claims it is owed by the town under a construction contract. The case was removed to the Circuit Court for Queen Anne’s County where, in a jury trial, the contractor was awarded damages in the amount of $74,022.66. From the judgment which was entered on that verdict, Federalsburg appeals.

The wellspring of this conflict is the contract which was entered into by Federalsburg and Allied on 28 July 1967. Under this agreement, the appellee was to underpin and otherwise reinforce as well as lengthen the piers of a highway bridge and the nearby railroad trestle, both of which span the Marshyhope Creek within the town limits. In addition, as part of the construction project, this creek, which is frequently referred to as the northwest fork of the Nanticoke River, was to be deepened, its channel widened, and its slopes protected so as to prevent erosion in the vicinity of these two parallel bridges. This undertaking, the initial stage of an extensive flood control program being pursued in cooperation with other governmental agencies, 1 began in September of 1967 and was completed to Federalsburg’s satisfaction one year later, on 17 September 1968.

The project contractor in this suit asserts that it is due compensation over and above the base price established in the contract because, while carrying out its obligations to the appellant, Allied provided, at Federalsburg’s request, additional labor and services for the town including more guniting (the pneumatic application of mortar) of the highway bridge’s first pier than was originally contemplated *154 by the agreement. Furthermore, Allied seeks to be reimbursed for its costs which it alleges resulted from the unjustifiable issuance of stop work orders by the town’s contracting officer. In submitting this latter claim, Allied urges that it is entitled to remuneration for two work stoppages, the first in 1967 and the second in 1968, which were directed by Federalsburg’s contracting officer not for Allied’s benefit but to accommodate the town. Following receipt by that contracting officer of these additional compensation demands, considerable correspondence and verbal discussions ensued between the contracting parties but, throughout these communications, the appellant constantly denied having a financial obligation for any of them. 2 Eventually, however, when it became painfully obvious to Allied that continued “negotiations” would not bear fruit, the contractor instituted this suit on 2 March 1972.

Federalsburg responded to Allied’s amended declaration by filing a special plea of limitations along with its pro forma general denial. After testimony was taken at a pre-trial hearing confined to the limitations issue, 3 Judge Turner ruled that the suit was not barred by the statute of limitations.

On appeal, in seeking a reversal of the judgment, the principal contention of Federalsburg, and the only one which we find to have any substance, is that the trial judge erred when he ruled that each of the unpaid claims for additional compensation was not barred by limitations. In addition, the appellant asserts that the trial judge committed prejudicial error when he: (i) made certain comments concerning the evidence in the presence of the jury; (ii) allowed “the jury to speculate and consider all aspects of plaintiffs [(Allied’s)] *155 claim under count number one of said declaration after the evidence clearly established the existence of a written contract as alleged by plaintiff in counts two, three, and four” ; and (iii) concluded that there was “sufficient evidence to uphold a finding of a new benefit to the defendant [(Federalsburg)] in the amount of $74,022.66 as required to be found by the trial court’s instructions to the jury.” We will consider and dispose of each of these arguments seriatim.

Three distinct questions comprise the limitations issue presented by this case. These are: whether the contract was under seal so as to create a specialty and thus make the applicable period of limitations twelve years, under § 5-102 (a) (5) of the Courts and Judicial Proceedings Article of the Maryland Code (1974), rather than the three-year period for simple contracts, under § 5-101 of that Article; on what date did the statutory period, as it pertains to each claimed item of damage, begin to run; and whether, once the period commenced, there were subsequent occurrences which tolled its running?

The only evidence, Allied concedes, to support its assertion that the contract in this case is a specialty is that when the document was signed on behalf of Allied by its vice-president, he also impressed the corporate seal on the instrument. The law in Maryland, as has been recently and fully discussed by this Court in Levin v. Friedman, 271 Md. 438, 317 A. 2d 831 (1974) and Gildenhom v. Columbia R. E. Title, 271 Md. 387, 317 A. 2d 836 (1974), requires more than the mere affixing of the corporate seal to transform a would-be simple contract into one under seal. Indeed, as is made clear by those two cases and General Petroleum Corp. v. Seaboard Terminals Corp., 23 F. Supp. 137 (D. Md. 1938), if a corporate seal is impressed on an agreement it will remain a simple contract unless either the body of the contract itself indicates that the parties intended to establish an agreement under seal, or sufficient extrinsic evidence, in the nature of “how and when and under what circumstances the corporate seal was affixed,” General Petroleum Corp. v. Seaboard Terminals Corp., supra at 139, *156 establishes that the parties desired to create a specialty. In Seaboard Judge Chesnut in discussing the Maryland law applicable to seals stated:

“If the contract is signed by an individual opposite and in obvious relation to a legally sufficient seal, the instrument will be taken as a sealed document, where there is nothing on the face of the paper to indicate the contrary even though there be no reference to the seal in the wording of the paper. ‘A recital of the sealing or of the delivery of a written promise is not essential to its validity as a sealed contract.’.... ‘A promisor who delivers a written promise to which a seal has been previously affixed or impressed with apparent reference to his signature, thereby adopts the seal.’...
“But with. respect to a contract executed by a corporation, the mere presence of its seal on the paper without any other reference therein to the seal, does not necessarily

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hess Construction v. Francis O'Day Co.
Court of Special Appeals of Maryland, 2025
Patriot Construction v. VK Electrical
Court of Special Appeals of Maryland, 2023
Nationwide Mut. Insurance v. Shilling
227 A.3d 171 (Court of Appeals of Maryland, 2020)
Gregory Smith v. Wakefield, LP
202 A.3d 1240 (Court of Appeals of Maryland, 2019)
Dave & Buster's, Inc. v. White Flint Mall, LLLP
616 F. App'x 552 (Fourth Circuit, 2015)
Tucker v. Specialized Loan Servicing, LLC
83 F. Supp. 3d 635 (D. Maryland, 2015)
Shailendra Kumar, P.A. v. Dhanda
43 A.3d 1029 (Court of Appeals of Maryland, 2012)
Columbia Ass'n v. Poteet
23 A.3d 308 (Court of Special Appeals of Maryland, 2011)
Ely v. Science Applications International Corp.
716 F. Supp. 2d 403 (D. Maryland, 2010)
Master Financial, Inc. v. Crowder
972 A.2d 864 (Court of Appeals of Maryland, 2009)
Crowder v. Master Financial, Inc.
933 A.2d 905 (Court of Special Appeals of Maryland, 2007)
Goodman v. Praxair, Inc.
494 F.3d 458 (Fourth Circuit, 2007)
McGinty v. Player
396 F. Supp. 2d 593 (D. Maryland, 2005)
Butler v. VisionAIR, Inc.
385 F. Supp. 2d 549 (D. Maryland, 2005)
Tipton v. Partner's Management Co.
773 A.2d 488 (Court of Appeals of Maryland, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
338 A.2d 275, 275 Md. 151, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mayor-of-federalsburg-v-allied-contractors-inc-md-1975.