Brosius Development Corp. v. City of Hagerstown

206 A.2d 571, 237 Md. 374, 1965 Md. LEXIS 732
CourtCourt of Appeals of Maryland
DecidedFebruary 3, 1965
Docket[No. 139, September Term, 1964.]
StatusPublished
Cited by10 cases

This text of 206 A.2d 571 (Brosius Development Corp. v. City of Hagerstown) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brosius Development Corp. v. City of Hagerstown, 206 A.2d 571, 237 Md. 374, 1965 Md. LEXIS 732 (Md. 1965).

Opinion

Barnes, J.,

delivered the opinion of the Court.

The appellants, (who were the defendants below), Brosius Development Corporation and Brosius Homes of Hagerstown, Inc. (closely affiliated corporations, hereinafter referred to as “Brosius”) were the owners and developers of a subdivision known as Greystone Manor in the north central part of the City of Hagerstown, (“the City”), the appellee. The City and Brosius agreed that the City would install the sewers in Greystone Manor, toward the expense of which Brosius paid the City $12,000. The agreement provided that “Rough grading shall be accomplished by and paid for by the property owner or developer.”

Brosius had Morton Thomas & Associates, its engineering consultant, prepare profile and street layout drawings for certain streets in Greystone Manor. One of these streets was Outer Drive. In 1958, Brosius graded the streets in the development, including Outer Drive. Brosius furnished the Thomas plans for the installation of sewers in the development. The sewer contract had been awarded by the City to Hetzer, Inc., the low bidder and the sewer work was commenced in the Spring of 1959.

On July 28, 1959, Hetzer, Inc. submitted a bill to the City for work performed under its contract which showed extra excavation of 989 cubic yards of dirt from Outer Drive. The unit price in the Hetzer contract for excavation of this type was $4.80 per cubic yard, so that this extra amounted to $4,747.20. The City paid the Hetzer bill and, on July 30, 1959, submitted a bill to Brosius for $4,747.20 covering this extra excavation.

Brosius, having indicated some objections to this charge in *377 a letter of August 3, 1959 to the City Engineer, had meetings with its representatives and the City representatives and in August, 1959 employed J. Harold Seibert, Engineer and County Surveyor, to check the area, and the computations of the City in regard to the excavation, as well as to determine the amount of dirt excavated. Mr. Seibert, by a letter dated September 23, 1959, (with a copy to the City Engineer) reported to Brosius that on August 19, 1959 he had checked the elevations and stated in detail the man hole number, the actual elevation, the grade and the difference between the actual elevation and the grade. His conclusions were as follows:

“From the above results, I am sure that the City Engineers Office used the same datum used by your Engineer when the original profiles were run and that the difference between the estimated quantity of excavation according to your profiles and the actual excavation according to profiles run by the City cannot be blamed on the use of different bench marks.
“I then spot checked the computations through several sections and found the method used to be correct, and the actual computations were likewise correct.
“Based on my review of the methods used, and an actual inspection of the ground, I am of the opinion that the profiles furnished by the City represent a reasonable picture of the actual conditions found, and that their estimate of extra excavation between the established street sub-grade and the actual ground line is reasonably correct.”

Relying on the Seibert Report, the President of Brosius went to see Mr. Hetzer, President of Hetzer, Inc., the Sewer Contractor, and asked him to accept less than $4.80 per cubic yard for the excavation, but Mr. Hetzer refused to do this.

The City pressed for payment of the $4,747.20 and on November 17, 1959, Brosius wrote the City Engineer as follows:

“Mr. Reynolds told me of your conversation with him of yesterday, inquiring as to when we would pay *378 the extra charge made us by your department for additional depth in the sewer ditch.
“As we have discussed with you on several occasions in the past, this was totally unexpected expense to us. As far as we were concerned, the streets had been graded to the required profile. So far as we can determine, no responsible person in our organization was notified that the street grades were higher than planned, except in the Haven Road area where we promptly corrected the grade before the sewer ditching was done. Had we been properly notified through Mr. Davis or Mr. Reynolds, or myself, the grading would have been completed for an expense of $500.00 or $600.00.
“The money involved in land development is substantial, as you are aware. This being the case, we must plan well in advance for our budgeted expenses.
We must also make provision for all expense in the sale price of our lots. Since we had no advance notice nor expectation of this cost, it was not budgeted and no plans were made for it in our capital program. We must, therefore, meet it as an unplanned expense.
“On this basis, we hope to be able to take care of the bill, at least to a substantial degree, by the end of this year.”

In his testimony, the President of Brosius stated that he wrote the letter of November 17, 1959 because Brosius “had a continuing relationship with the City which we had to maintain and * * * you don’t fight City Hall.” In response to a question by the trial court, he stated: “Yes sir, once I said, yes, we had to pay it, and I was explaining why we couldn’t pay it that day or that month, but would pay it some months later.” He also admitted that after writing the letter of November 17th, he had “a change of heart because many things have developed since then.”

The City did not institute its action to recover the $4,747.20 until July 23, 1962. Brosius pleaded the general issue pleas and a plea of the three year Statute of Limitations. It also filed a *379 “Plea of Recoupment” in two counts. In Count I, Brosius alleged defective work in installing the sewer line, resulting in damage to the plumbing work installed by Brosius, inconvenience to purchasers of homes in the development and injury to the reputation and good will of Brosius. In Count II, Brosius alleged that after having commenced preparations for paving Outer Drive, it discovered certain alleged errors in the grade elevations shown in the drawings, so that it had to place dirt in areas in which it had previously removed it, causing it loss and damage.

The case was tried in the lower court before Judge McLaughlin, sitting without a jury. He filed a Memorandum Opinion finding the principal facts in favor of the City and entered judgment for the City for $4,747.20. He allowed Brosius two items of $116.76 and $21.60 for sewer errors, entered judgment for Brosius on its counter-claim, for $138.36 and required Brosius to pay all the costs. He did not allow the items of $443.20 paid by Brosius to Bester and Long, the paving contractor, for adding fill on Outer Drive in 1962, and $168.00 for the value of the use of the equipment of Brosius in this filling operation.

The principal issue in this case is whether the City’s claim is barred by the Statute of Limitations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Westminster Management
Court of Special Appeals of Maryland, 2023
Jenkins v. Karlton
620 A.2d 894 (Court of Appeals of Maryland, 1993)
Potterton v. Ryland Group, Inc.
424 A.2d 761 (Court of Appeals of Maryland, 1981)
Mayor of Federalsburg v. Allied Contractors, Inc.
338 A.2d 275 (Court of Appeals of Maryland, 1975)
Glassman Const. Co., Inc. v. Maryland City Plaza, Inc.
371 F. Supp. 1154 (D. Maryland, 1974)
James v. Thurn
290 A.2d 490 (Court of Appeals of Maryland, 1972)
Operations Research, Inc. v. Davidson & Talbird, Inc.
217 A.2d 375 (Court of Appeals of Maryland, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
206 A.2d 571, 237 Md. 374, 1965 Md. LEXIS 732, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brosius-development-corp-v-city-of-hagerstown-md-1965.