Maryland Casualty Co. v. West Construction Co.

114 A. 890, 139 Md. 171, 1921 Md. LEXIS 145
CourtCourt of Appeals of Maryland
DecidedJune 28, 1921
StatusPublished
Cited by1 cases

This text of 114 A. 890 (Maryland Casualty Co. v. West Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maryland Casualty Co. v. West Construction Co., 114 A. 890, 139 Md. 171, 1921 Md. LEXIS 145 (Md. 1921).

Opinion

Boyd, C. J.,

delivered the opinion of the Court.

The appellant was surety on the bond of Carl T. Opperman for the completion of certain construction work under a contract between him and the City of Harrisburg. Ho having made default in the performance of the contract, the appellee and the appellant entered into an agreement on the 27th day of September, 1913, by which the appellee agreed to perform any and all work remaining unfinished under the contract between Opperman and the said city. Suit was brought by the appellee against the appellant, for the recovery of $3,-485.88 withheld by the city as the retained percentage upon the work theretofore performed by Opperman. The lower court refused to grant a prayer recognizing the right of the plaintiff to recover that sum, and we concurred in its action. In. the course of the trial, which was before the court without a jury, two errors were discovered, one for $750 and another for $407.50, which were admitted by the casualty company and, although the court did not allow recovery for what was sued for — the retained percentage — a judgment was rendered in favor of the’ plaintiff for $1,307.25, being the sum of the two items above mentioned, together with interest on them.

The appellee (then plaintiff), not being satisfied with the amount of recovery, took an appeal to this Court, it being amongst the unreported cases in 132 Maryland, 699. The opinion in that case concluded by saying: “The judgment will be affirmed, no reversible error having occurred in any of the rulings at- the trial, but the affirmance will be without prejudice to any'claim which the plaintiff may 'be entitled to assert for work done under its agreement with the de1fendant on account of the deficiencies or imperfections in the *173 prior work on the same project.” When the mandate was issued to the lower court it only recited that the judgment was affirmed with costs. A petition was then filed by the construction company, asking this Court to amend or modify its mandate so as to read: “Judgment affirmed, with costs, but without prejudice,” etc. — following' the language of the opinion we have just quoted. That was granted and the mandate was amended accordingly. A new suit was then brought —resulting’ in a judgment for $«,655.63, from which this appeal was taken.

The basis of this suit was the work of making good the deficiencies and imperfections in the prior work of Opperraan under his contract. The plaintiff filed six common counts and two special counts. The defendant filed the two general issue pleas, a plea of limitations and its fourth and fifth pleas, setting up the former judgment as a bar to this suit, and alleging that by virtue of an order of the Superior Court it had paid into court the sum of $1,284.23 in full satisfaction, release and discharge1 of said judgment, interest and costs. The plaintiff joined issue on the first and second' pleas, reversed the third (of limitations) and demurred to. the fourth and fifth. The demurrers to those two pleas were sustained, and afterwards an amended fifth plea was filed and a demurrer to it was sustained. Fourteen bills of exceptions to the rulings on evidence are in the record and the-fifteenth embraces the rulings in rejecting1 its nine prayers.

The appellant very earnestly contends that this Court had no power to authorize another suit to he brought on the contract, and that the judgment of affirmance was a bar to this-, suit, notwithstanding what was said in the opinion and the* modification made to the mandate. As that is the most important question involved in the appeal, not only as affecting this particular case, but the practice in this Court, we will first consider it. "We can have no doubt about the correctness of tlie general principles as announced in the many antherities cited by the appellant as to what constitutes res *174 (idjudicata, that a party cannot generally split his cause of action, etc. For the most part they may be conceded, but do they reach the real point in this case.

It will be well for us to quote from the former opinion at ■ some length, especially as it was not reported. Judge ITrwer, in speaking for the Court, said:

“It is said that the appellant was required to remedy defects in portions of the work which the first contractor performed-, - and that this duty was assumed by the appellant under its agreement, and furnishes adequate support- for its theory that it is entitled, and was intended, to receive the amount of the retained percentage, of the cost of the previously finished work over and above the price agneed upon for the work then remaining uncompleted. In reference to ■this suggestion it is to be observed that the agreement- between the appellant and the casualty company provided specifically for payment on the unit price basis therein designated for fti-h of the work for which ■ the appellant contracted, and upon .¡that: ¡basis alone, therefore, must its compensation be ascertained. The appellant’s undertaking was to perform the work leftumeompleted by Oppennan in accordance with the specifications of the contract he had executed. That description of - the work yet to be done clearly included sucli operations as might be necessary to supply deficiencies-in the construction-previously attempted and to complete it as required by the specifications. The work defectively done hv the preceding contractor1 was unfinished work within the terms of the -appellant’s agreement. For such work the appellant was undoubtedly entitled to be paid, but only at the unit price rate of ■ compensation, which the contract defines as applicable to every feature of the work for which it makes provision.

“The evidence in the record docs not show the items or contract value of the labor and materials furnished by the appellant- in supplying deficiencies in the prior construction. It is stated generally in the testimony that the appellant was required to do such supplemental work and thereby incurred *175 considerable expense. No allowance for work of that nature appears to have been made in the accounting' between the casualty company and the appellant, their settlement, however, being expressly without prejudice to the rights of the parties to assert their respective theories in reference to the question now under consideration. The contention- of the casualty company, in substance, is that, under the agreement, all the work required to complete the project according to specifications, including the correction of defects in the preceding work, was to be done by the appellant for the amount which the casualty company was to receive from the city, plus the difference between that amount and the price,-on the new contractual basis, of the work which the first contractor had left wholly unperformed. Neither this view, nor that of the appellant, already indicated, is in accord with our interpretation of the contract bv which the rights of the parties are to be determined. In our opinion the correct meaning of the agreement is that the appellant should' be paid at the specified unit prices for all work required to complete the project conformably to- the specifications of the original contract, both as to the portion of the construction not previously begun and as to that which had been undertaken but left in an imperfect condition.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mayor of Federalsburg v. Allied Contractors, Inc.
338 A.2d 275 (Court of Appeals of Maryland, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
114 A. 890, 139 Md. 171, 1921 Md. LEXIS 145, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maryland-casualty-co-v-west-construction-co-md-1921.