Maryland Steel Co. v. United States

48 Ct. Cl. 50, 1912 U.S. Ct. Cl. LEXIS 8, 1912 WL 1168
CourtUnited States Court of Claims
DecidedDecember 2, 1912
DocketNo. 31281
StatusPublished
Cited by1 cases

This text of 48 Ct. Cl. 50 (Maryland Steel Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maryland Steel Co. v. United States, 48 Ct. Cl. 50, 1912 U.S. Ct. Cl. LEXIS 8, 1912 WL 1168 (cc 1912).

Opinion

Peelle, Ch. J.,

delivered the opinion of the court:

The claimant seeks recovery for a balance claimed to be due on a contract which was performed according to its terms and full payment therefor made except as to the sum of $4,750, which the Government by its set-off in the nature of a cross petition alleges should have been deducted as liquidated damages under a prior contract for the failure of the claimant to complete the work thereunder within the contract time, notwithstanding the time limit had been waived and the claimant permitted to proceed with the work to completion and full payment therefor was made.

The claimant for replication admits that there was such a contract, but says that before the expiration of the time fixed therein for the completion of the work the Quartermaster General waived the time limit.

No reference is made in the petition to this prior contract, but the Government by its cross petition alleges that the amount deducted under the contract sued on was inadvertently and contrary to law paid to the claimant under said prior contract.

Said first contract provided for the construction, equipment, and delivery in New York to the Government of a single-screw steamer for harbor purposes, article 2 of which provided as follows:

“Article 2. That the Maryland Steel Company shall complete the construction and equipment of the said steamer and deliver same to the party of the first part in New York Harbor, or as directed by him, in one hundred forty (140) days, exclusive of Sundays and legal holidays, from the date of this contract. And it is hereby agreed that in case the party of the second part fails to complete in all respects and deliver the said steamer within the time herein specified, the loss re-[56]*56suiting to the United States from such failure is hereby fixed at the rate of fifty ($50) dollars per day for each and every day, exclusive of Sundays and legal holidays, completion and delivery of the vessel is delayed beyond the period hereinbefore specified, and it is hereby stipulated that the party of the first part may withhold such amount as liquidated damages from any money due and payable to the party of the second part by the United States for work done under this contract. In the event of the act of God, war, fire, or strikes and lockouts of workmen affecting the working of this contract, the date of completion of the steamer may be extended for such period as may be deemed just and reasonable by the party of the first part, to cover the time lost from any of the above-mentioned causes.”

It will be noted that time was of the essence of the contract and a breach thereof would have given the opposite party the option of treating the contract as discharged. Slater v. Emerson, 19 How., 224. On the other hand, had the contractor failed to perform within the specified time, the Government’s permission for it to continue performance would have operated as a waiver of the breach. Jeffrey Mfg. Co. v. Iron Co., 93 Fed. R,., 408; Davis v. Roberts, 89 Ala., 402; Barnard v. McLeod, 114 Mich., 73.

In the present case the time limit within which to complete the work was orally waived by the Quartermaster General before the expiration of the time fixed in the contract therefor, and accordingly the claimant proceeded therewith and thereafter on April 1, 1904, completed the work. On the day succeeding the completion of the work, to wit, April 2, 1904, the Quartermaster General, United States Army, in writing, confirmed the waiver of the time limit as aforesaid, following which, by order of said Quartermaster General, the depot quartermaster at New York made final payment to the claimant for the steamer so completed under said first contract, less 10 per cent retained by way of indemnity for any defects that might appear in either the material or workmanship.

Thereafter, July 13, 1904, the percentage so retained was paid over to the claimant company. Thus the transaction under the first contract, it would seem, was closed.

[57]*57Nearly four years thereafter, to wit, February 24,1908, the claimant entered into a written contract, made part of the petition herein, whereby the claimant, for the consideration of $357,500, agreed to furnish all the necessary labor and material therefor and to build one steel hull twin-screw suction dredge, and to furnish and install therein the propelling and necessary machinery, electric-light plant, etc., and to deliver the work at Sparrows Point, in the State of Maryland, which work was completed on January 6, 1909, and the claimant was fully paid therefor, less $4,750, which was withheld as due under the first contract as liquidated damages for the 95 days’ delay of the claimant in the completion of the steamer thereunder, notwithstanding the waiver of the time limit by the Quartermaster General and payment of said amount as aforesaid.

The verbal waiver of the stipulated time within which to perform work under a contract notwithstanding the act of 1862, 12 Stat., 411, requiring contracts to be in writing, finds support in the case of Salomon v. United States, 19 Wall., 17, 19; 7 C. Cls., 482, wherein Justice Miller, reversing this court, said:

“ Whether we regard the delivery made in October as made under a verbal extension of the time stipulated in the original contract, or consider it as a new transaction in which the Government received and took possession of the com and used part of it and permitted the remainder to be injured in its hands, we think the claimant is equally entitled to be paid for it.
“ The act of 1862, requiring contracts for military supplies to be in writing, is not infringed by the proper officer having charge of such matter accepting delivery of such supplies after the day stipulated, nor is a verbal agreement to extend the time of performance invalid.
“ And if this were not so, when the quartermaster in charge receives of a person corn for the Government, gives a receipt and voucher for the amount and the price, and the Government uses such part of it as it wants and suffers the remainder to decay by exposure and neglect, there is an implied contract to pay the value of such corn, which value may, in the absence of other testimony, be presumed to be the price fixed in the voucher by the quartermaster.”

In the case of District of Columbia v. Camden Iron Works, 181 U. S., 453, 461, involving the construction of a similar [58]*58statute, requiring contracts made by the Board of Public Works of the District to be in writing and signed by the parties, the court held in substance that the delivery of the material contracted for after the time specified in the contract did not constitute a new contract. See also Williams v. Bank, 2 Pet., 96, therein cited, and Phillips Construction Company v. Seymour, 91 U. S., 646.

But we do not understand the Government to seriously controvert the waiver of the time limit. It does, however, vigorously contend that, notwithstanding the waiver, the liquidated-damage clause of the contract continued in force. The waiver of the time limit was before the expiration of the time agreed upon for the completion of the work, -and therefore no liquidated damages had then accrued. Guyer v. Warren, 175 Ill., 328; Vandergrift v. Engineering Co., 161 N. Y., 435.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Camden Iron Works v. United States
50 Ct. Cl. 191 (Court of Claims, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
48 Ct. Cl. 50, 1912 U.S. Ct. Cl. LEXIS 8, 1912 WL 1168, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maryland-steel-co-v-united-states-cc-1912.