Martin v. Hodel

692 F. Supp. 637, 1988 U.S. Dist. LEXIS 8972, 1988 WL 85256
CourtDistrict Court, W.D. Virginia
DecidedAugust 11, 1988
DocketCiv. A. No. 88-0133-B
StatusPublished
Cited by1 cases

This text of 692 F. Supp. 637 (Martin v. Hodel) is published on Counsel Stack Legal Research, covering District Court, W.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martin v. Hodel, 692 F. Supp. 637, 1988 U.S. Dist. LEXIS 8972, 1988 WL 85256 (W.D. Va. 1988).

Opinion

MEMORANDUM OPINION

GLEN M. WILLIAMS, District Judge.

This is a suit to enjoin the federal defendants from prosecuting the plaintiff for violating the Surface Mining Control and Reclamation Act of 1977, 30 U.S.C.A. §§ 1201-1328 (West 1986 & Supp.1988) (The Act). Initially, this court has jurisdiction to determine its jurisdiction, an issue raised by the defendant. Texas & Pacific Ry. v. Gulf, Colorado & Santa Fe Ry., 270 U.S. 266, 274, 46 S.Ct. 263, 265, 70 L.Ed. 578 (1927) cited in McGowen v. Harris, 666 F.2d 60, 66 (4th Cir.1981).

FINDINGS OF FACT

W.D. Martin, the plaintiff, operated a small coal mine in Dickenson County, Virginia for a period of approximately three weeks in 1981. At some point, a citizen complained, resulting in an inspection of the mine by the Office of Surface Mining, Bureau of the Mines, United States Department of Interior (OSM). The OSM inspector concluded that the mine had not been [638]*638restored to its approximate original contour as required by the Act because there was no sedimentation structure on the site, the highwall had not been covered, and no other reclamation work had been done. The OSM inspector, as required by 30 U.S.C.A. § 1271, issued a Notice of Violation (NOV), # 81-1-47-33, and a proposed civil penalty of $1,100.00 for (1) failing to pass all surface drainage through a sedimentation pond, 30 C.F.R. 715.17(a), and (2) failing to compact and regrade spoil material in order to eliminate the highwall, 30 C.F.R. 715.14.

Martin filed for a review of the NOV charged by OSM pursuant to 30 U.S.C.A. § 1275(a)(1). His defense was that 30 U.S. C.A. § 1278(3) (West Supp.1988) exempts him from reclamation because the area disturbed by his mining operations was less than two acres (two acre exemption). The Administrative Law Judge (AU) agreed, holding that the evidence “clearly showed that W.D. Martin and his coal surface mining operation at the site in question is exempt from the act.” Martin v. Office of Surface Mining Reclamation and Enforcement, (CH# 2-29-R) at 2 (Office of Hearings and Appeals of the Dept. of Interior, March 11, 1982) (unpublished). The AU vacated the NOV for “lack of jurisdiction on the part of OSM to have issued the same.” Id. at 3. OSM did not seek review of the decision.

Seven years later, OSM again inspected the site and issued another NOV, #88-132-423-006. Through this NOV, OSM cites Martin for failure to transport, backfill and grade all spoil material, and to eliminate highwalls, spoil sites and depressions, in order to achieve the approximate original contour at the site Martin mined in 1981.

In response, Martin filed this suit to enjoin the federal defendants from prosecuting the 1988 NOV on the legal ground of res judicata. He argued that, since the AU found Martin’s Dickenson County mining operation within the Act’s two acre exemption in 1981, OSM is barred from further action for the same violation at the identical site when Martin has engaged in no further mining at the site. Furthermore, it is futile to pursue administrative remedies as OSM ignores unfavorable administrative results. He contends only an injunction from this court shall give Martin the relief he seeks. Of course, OSM disagrees, arguing Martin must make these legal arguments through the administrative process and this court is without jurisdiction to hear this case.

Martin testified at the hearing on the Preliminary Injunction. He stated that Martin Coal Co. was not incorporated and that he was using that name for fictitious trading purposes. He had retired in 1979 and ceased mining, except for two small mines. The first mine, near Colfax brancht was abandoned in February. The second, near Trammel branch, was operated for only three weeks in June and July of 1981. The Trammel mine was the subject of the first NOV. He testified that, at the original administrative hearing, he had indeed stated that he had done no other mining since his retirement but that he was wrong since he had forgotten about the first mine he had operated for only a week in February. When asked by the court whether these operations were simultaneous, Martin answered no. He further testified that he had not done any mining since the Trammel operation in the summer of 1981 and that the cost of reclaiming the 1981 site was beyond his means. Martin concluded by stating he was now fully retired from the coal business but that he did some farming.

The Government called Doyle Boothroy as a witness, who is a reclamation specialist with the Office of Surface Mining. He stated that the 1988 NOV is a result of the “two acre task force.” This group resulted from a settlement the government made with an environmental group which had sued over the government’s enforcement policies for small mines. Although OSM was aware of the 1981 administrative opinion, it nevertheless issued the 1988 NOV because it was not aware of Martin’s February operation at Colfax in 1981. When the affected areas of these two mines are combined, the sum is greater than two acres. Boothroy testified that OSM relatedness criteria provide that two mines should be combined for purposes of apply[639]*639ing the two acre exemption when (1) they are in the same watershed (they do not have to be physically connected); (2) involve the same mining company; and, (3) were operated within twelve months of each other. Boothroy confirmed Martin’s testimony that there was no evidence of any further mining of the site since 1981. He also stated that no environmental harm had occurred at the Trammel site as a result of Martin’s 1981 operation.

The Government contends that the court does not have jurisdiction of this suit because Martin has failed to exhaust his administrative remedies. The Act sets forth a complex scheme for review of the Secretary’s actions. Thirty days after the Secretary issues a NOV, a coal operator must first apply to the Secretary for temporary relief. See 30 U.S.C.A. § 1276(c). If such relief is denied, the operator may seek judicial review in U.S. District Court where the mine is located. Id. § 1276(a)(2). Until that process is exhausted, the government contends a district court cannot assert jurisdiction. Mullins Coal Co. v. Clark, 759 F.2d 1142, 1144-46 (4th Cir.1985) reversing 600 F.Supp. 645 (W.D.Va.1984) (exercise of jurisdiction by this court enjoining Secretary from issuing NOV). When a statute provides for judicial review, review of agency action under that statute must be exclusively pursuant to those special review provisions. 5 U.S.C.A. § 703 (West 1977); Whitney Bank v. New Orleans Bank, 379 U.S. 411, 420, 85 S.Ct. 551, 557, 13 L.Ed.2d 386 (1965). Martin may only proceed to this court if he is dissatisfied with the ALJ’s decision.

CONCLUSIONS OF LAW

The court agrees with the government’s argument as far as it goes. However, it assumes the Secretary is acting lawfully.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pierce v. Securities & Exchange Commission
737 F. Supp. 2d 1068 (N.D. California, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
692 F. Supp. 637, 1988 U.S. Dist. LEXIS 8972, 1988 WL 85256, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martin-v-hodel-vawd-1988.