Mullins Coal Company v. William P. Clark, Secretary, Department of Interior

759 F.2d 1142, 15 Envtl. L. Rep. (Envtl. Law Inst.) 20661, 1985 U.S. App. LEXIS 30356
CourtCourt of Appeals for the Fourth Circuit
DecidedMarch 28, 1985
Docket85-1042
StatusPublished
Cited by14 cases

This text of 759 F.2d 1142 (Mullins Coal Company v. William P. Clark, Secretary, Department of Interior) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mullins Coal Company v. William P. Clark, Secretary, Department of Interior, 759 F.2d 1142, 15 Envtl. L. Rep. (Envtl. Law Inst.) 20661, 1985 U.S. App. LEXIS 30356 (4th Cir. 1985).

Opinion

HARRISON L. WINTER, Chief Judge:

The Secretary of the Interior appeals from an order of the district court preliminarily enjoining him from enforcing against Mullins Coal Company (Mullins) a cessation order issued pursuant to 30 U.S.C. § 1271(a)(3). 600 F.Supp. 645. Because Mullins failed to exhaust available administrative remedies, as contemplated by the Surface Mining Control and Reclamation Act of 1977, 30 U.S.C. § 1201 et seq., before obtaining relief from the district court, we vacate the district court’s preliminary injunction.

I.

Mullins operates a mine in Buchanan County, Virginia. It is the holder of a permit from the Virginia Division of Mined Land Reclamation (DMLR), and within the permit area is a haul road leading from the mine. On July 26, 1984, while conducting an oversight inspection, federal reclamation specialist David Beam noticed a landslide in the fill bank of the haul road that extended beyond the permit area. Because the Commonwealth of Virginia has elected to assume exclusive jurisdiction over the regulation of surface coal mining and reclamation under a federally approved state program as permitted under 30 U.S.C. § 1253, Mr. Beam first contacted the DMLR as required by 30 U.S.C. § 1271(a)(1). When the DMLR did not act on the ten-day notice *1144 filed by Beam, he reinspected the site, concluded that the landslide was unstable, and issued a notice of violation (NOV) on October 5, 1984.

Under the Act, if an inspector finds a violation of the Act which poses no “imminent danger to health, safety or the environment” he must issue an NOV that fixes “a reasonable time but not more than ninety days for the abatement of the violation.” 30 U.S.C. § 1271(a)(3). The October 5,1984 NOV gave Mullins thirty days in which to abate the violation. If after the time fixed for abatement the violation remains, the Secretary or his representative must issue a cessation order halting those mining op: erations relevant to the violation. 30 U.S.C. § 1271(a)(3). On December 4, 1984, Beam again inspected the site, found that Mullins had done nothing to correct the violation, and issued a cessation order requiring Mullins to cease hauling coal over the haul road.

The Act entitles a coal company to administrative review both of NOV’s and of cessation orders. Under 30 U.S.C. § 1275(b), a company issued a cessation order is entitled to a written decision from the Secretary within thirty days of receipt of its application for review. During that time, however, the cessation order remains in effect. However, the company may seek temporary relief from an NOV or cessation order, and the Secretary must act on an application for temporary relief from a cessation order within five days of the application’s receipt. 30 U.S.C. § 1275(c).

If the Secretary denies temporary relief, the company may seek immediate review in the United States District Court for the district in which the mine is located. 30 U.S.C. § 1276(c). By seeking immediate judicial review of the Secretary’s decision, the company also bypasses appeal to the Board of Land Appeals. 43 C.F.R. § 4.1267 (1984). The district court may grant temporary relief under section 1276(c) pending completion of the administrative process. Section 1276(a)(2) provides, inter alia, for judicial review of any order or decision of the Secretary issued in any proceeding “required to be conducted pursuant to section 554 of Title 5.”

On November 8, 1984, Mullins sought administrative review of the NOV pursuant to section 1275. In response to the Secretary’s cessation order, however, it did not first obtain a decision from the Secretary. Instead, on December 11, 1984, it simultaneously filed a complaint in the district court seeking a temporary restraining order and a preliminary injunction and mailed an application for temporary relief, which the Office of Hearings and Appeals did not receive until December 17, 1984. According to the Secretary, the application for temporary administrative relief waived the five-day requirement by failure to comply with the regulations set out at 43 C.F.R. §§ 4.1260-.1266 (1984). On December 31, 1984, however, the Office of Hearings and Appeals did receive a request by Mullins for consolidation of its administrative appeals and for expedited review. The district court granted Mullins’ requested TRO on December 11, 1984, and subsequently granted ten-day extensions of the TRO on December 20 and December 30, 1984.

On January 4, 1985, the district court enjoined the Secretary from enforcing the cessation order until it had acted upon the permanent injunction. The district court excused the exhaustion requirement on the ground that pursuit of administrative remedies in this case “would be a futile gesture.” On that same day, the Administrative Law Judge denied Mullins’, application for temporary relief from the cessation order. 1

II.

Mullins contends that the Act does not require it to exhaust administrative *1145 remedies before pursuing a judicial one. We agree with the Sixth Circuit that it does. See Shawnee Coal Co. v. Andrus, 661 F.2d 1083 (6 Cir.1981).

As Mullins readily concedes, the district court’s jurisdiction to grant relief in this case must derive from § 1276(a)(2). That section states in pertinent part:

Any order or decision issued by the Secretary in a civil penalty proceeding required to be conducted pursuant to section 554 of Title 5 shall be subject to judicial review on or before 30 days from the date of such order or decision in accordance with subsection (b) of this section in the United States District Court for the district in which the surface coal mining operation is located.

Notably, section 1276(a)(2) conditions judicial review on compliance with subsection (b).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Living Lands, LLC v. Cline
S.D. West Virginia, 2022
Dine Citizens Against Ruining Our Environment v. Klein
676 F. Supp. 2d 1198 (D. Colorado, 2009)
DINE CITIZENS AGAINST RUINING OUR ENV. v. Klein
676 F. Supp. 2d 1198 (D. Colorado, 2009)
OHIO VALLEY ENVIRONMENTAL COALITION, INC. v. Apogee Coal Co.
531 F. Supp. 2d 747 (S.D. West Virginia, 2008)
Libutti v. United States
914 F. Supp. 804 (N.D. New York, 1995)
In Re Grewe
4 F.3d 299 (Fourth Circuit, 1993)
Kenlin Industries, Incorporated v. United States
927 F.2d 782 (Fourth Circuit, 1991)
United States v. Hubler
117 B.R. 160 (W.D. Pennsylvania, 1990)
Plowman v. Cheney
714 F. Supp. 196 (E.D. Virginia, 1989)
Martin v. Hodel
692 F. Supp. 637 (W.D. Virginia, 1988)
Diaz v. Pueblo International, Inc.
23 V.I. 346 (Supreme Court of The Virgin Islands, 1988)
St. Francis Hospital v. Bowen
802 F.2d 697 (Fourth Circuit, 1986)
St. Francis Hospital v. Owen
802 F.2d 697 (Fourth Circuit, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
759 F.2d 1142, 15 Envtl. L. Rep. (Envtl. Law Inst.) 20661, 1985 U.S. App. LEXIS 30356, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mullins-coal-company-v-william-p-clark-secretary-department-of-interior-ca4-1985.