Manno v. United States

48 Fed. Cl. 587, 2001 U.S. Claims LEXIS 7, 2001 WL 95735
CourtUnited States Court of Federal Claims
DecidedJanuary 30, 2001
DocketNo. 99-285C
StatusPublished
Cited by24 cases

This text of 48 Fed. Cl. 587 (Manno v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Manno v. United States, 48 Fed. Cl. 587, 2001 U.S. Claims LEXIS 7, 2001 WL 95735 (uscfc 2001).

Opinion

ORDER

MILLER, Judge.

This case is before the court on plaintiffs Application for Attorneys’ Fees after trial and entry of judgment in plaintiffs favor. Plaintiff argues that the position of the United States Department of Agriculture, by the Natural Resources Conservation Service Agency (the “NRCS” or the “agency”), both before and during litigation was not “substantially justified” within the meaning of the Equal Access to Justice Act, 28 U.S.C.A. § 2412 (West 1994 & Supp.1999) (the “EAJA”). Argument is deemed unnecessary.

FACTS

The NRCS awarded James J. Manno, Sr., d/b/a James J. Manno Construction Co. (“plaintiff’), Contract No. 50-5E34-7-78 for the construction of 1,805 linear feet of El-piling wall and related work along Churn Creek Road in Jefferson Township, Adams County, Ohio (the “Project”). At the conclusion of the project, plaintiff, acting pro se, submitted a claim dated February 11, 1998, to the contracting officer for an equitable adjustment. In a letter dated May 4, 1999, the contracting officer denied plaintiffs claim in its entirety.

The contracting officer’s denial was based, in part, on his review of the Job Diaries maintained by the Government’s engineer during the Project. Plaintiff appealed the denial to the cognizant board of contract appeals. When the Government moved to dismiss plaintiffs appeal as untimely, plaintiff requested that its appeal be withdrawn without prejudice in order to file in the United States Court of Federal Claims. That request was granted on November 18, 1998.

On August 28, 1998, plaintiff submitted a request for the Job Diaries under the Freedom of Information Act, 5 U.S.C.A. § 552 (West 1994 & Supp.1999) (the “FOIA”). Citing the “deliberative process privilege (pre-decisional)” the agency denied the request on September 29, 1998. Plaintiff appealed on October 5, 1998, and the request was again denied on October 22, 1998. Plaintiff, still acting pro se, wrote two other letters, on November 20, 1998, and January 15, 1999, [589]*589clarifying its FOIA request. The Job Diaries still had not been turned over when plaintiff filed the instant action on May 7, 1999. Beginning on or about that date, plaintiff was represented by counsel.

The case proceeded through cross-motions for summary judgment and to trial commencing on August 21, 2000. Leading up to and during the trial in this case, plaintiff presented a number of bases for recovery. Plaintiff asserted that it was entitled to an equitable adjustment based on defective specifications, bad faith on the part of agency officials, differing site conditions, and unreasonable inspections and tolerances mandated by the NRCS. After ruling on the parties’ cross-motions and a five-day trial, including an indispensable day-long site inspection, the court found that plaintiff was entitled to an award based on the “zealous and enforced inspection” that was suddenly required midway through the project. See Transcript of Trial, No. 99-285C, at 928 (Fed.Cl. Aug. 25, 2000) (“Tr.”). Plaintiffs other theories of recovery, either during briefing or at trial, did not provide a basis for relief. The court directed the parties to file a stipulation as to computation of damages, costs, and interest. On October 5, 2000, the court issued an order entering judgment for plaintiff in the amount of $119,715.51.

At the conclusion of the trial and its bench ruling, on August 25, 2000, the court urged plaintiff to consider carefully a claim for attorneys’ fees. See Tr. at 931. Plaintiff represents that it has done so, see Pl.’s Br. filed Oct. 18, 2000, at 1, and moves now for attorneys’ fees incurred before and during trial.

DISCUSSION

1. The Equal Access to Justice Act

The EAJA sets forth a cause of action for fees and costs: The court “shall award to a prevailing party other than the United States fees and other expenses ... unless the court finds that the position of the United States was substantially justified or that special circumstances make an award unjust.” 28 U.S.C.A. § 2412(d)(1)(A). Defendant concedes that plaintiff is an “eligible”1 “prevailing party”2 within the meaning of the EAJA. See Def.’s Br. filed Dec. 1, 2000, at 7. The remaining issue is whether the Government’s position was “substantially justified.”

The “position” of the Government “means, in addition to the position take by the United States in the civil action, the action or failure to act by the agency upon which the civil action is based ____” 28 U.S.C.A § 2412(d)(2)(D). A position “can be justified even though it is incorrect, and it can be substantially justified if a reasonable person could think it correct.” Doe v. United States, 16 Cl.Ct. 412, 419 (1989). The Government bears the burden of showing that its position was substantially justified. See Helfer v. West, 174 F.3d 1332, 1336 (Fed. Cir.1999).

The phrase “substantially justified” means “‘justified in substance or in the main’ — that is, justified to a degree that could satisfy a reasonable person.” Pierce v. Underwood, 487 U.S. 552, 565, 108 S.Ct. 2541, 101 L.Ed.2d 490 (1988) (citations omitted). Thus, the trial court must “look at the entirety of the government’s conduct and make a judgment call whether the government’s overall position had a reasonable basis in both law and fact.” Chiu v. United States, 948 F.2d 711, 715 (Fed.Cir.1991) (footnote omitted); see TGS Intern., Inc. v. United States, 983 F.2d 229, 229-30 (Fed.Cir.1993). “[T]he entirety of the conduct of the [G]overnment,” includes “the action or inaction by the agency prior to litigation.” Chiu, 948 F.2d at 715. “As the Supreme Court has emphasized, whether the Government’s position lacks substantial justification is a “single finding” that operates as a one-time threshold for fee eligibility.” Commissioner Immi-[590]*590grat. & Nat. Servs. v. Jean, 496 U.S. 154, 160, 110 S.Ct. 2316, 110 L.Ed.2d 134 (1990).

When evaluating whether the Government has met its burden, the court therefore examines the entirety of the Government’s conduct and makes a single finding as to whether the Government’s position was substantially justified. “This ‘quintessentially discretionary’ inquiry ... necessarily involves the determination of facts and the application of the substantially justified standard of the EAJA to those facts.” Stillwell v. Brown, 46 F.3d 1111, 1113 (Fed.Cir.1995) (citations omitted); see also Clemmons v. West, 206 F.3d 1401, 1404 (Fed.Cir.2000) (ruling that Federal Circuit was “precluded” from reviewing challenge to trial court’s factual determination that Government’s position was substantially justified).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yang v. United States
Federal Claims, 2021
Q Integrated Companies, LLC v. United States
133 Fed. Cl. 479 (Federal Claims, 2017)
Shafer v. United States
Federal Claims, 2015
Wollman v. United States
Federal Claims, 2015
Park Properties Associates, L.P. v. United States
120 Fed. Cl. 787 (Federal Claims, 2015)
Hyperion, Inc. v. United States
118 Fed. Cl. 540 (Federal Claims, 2014)
Bcpeabody Construction Services, Inc. v. United States
117 Fed. Cl. 408 (Federal Claims, 2014)
Kwv, Incorporated v. United States
113 Fed. Cl. 534 (Federal Claims, 2013)
Miles Construction, LLC v. United States
113 Fed. Cl. 174 (Federal Claims, 2013)
Standard Communications, Inc. v. United States
106 Fed. Cl. 165 (Federal Claims, 2012)
Greenhill v. United States
96 Fed. Cl. 771 (Federal Claims, 2011)
United Partition Systems, Inc. v. United States
95 Fed. Cl. 42 (Federal Claims, 2010)
Dalles Irrigation District v. United States
91 Fed. Cl. 689 (Federal Claims, 2010)
Precision Pine & Timber, Inc. v. United States
83 Fed. Cl. 544 (Federal Claims, 2008)
JGB Enterprises, Inc. v. United States
83 Fed. Cl. 20 (Federal Claims, 2008)
ACE Constructors, Inc. v. United States
81 Fed. Cl. 161 (Federal Claims, 2008)
CEMS, Inc. v. United States
65 Fed. Cl. 473 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
48 Fed. Cl. 587, 2001 U.S. Claims LEXIS 7, 2001 WL 95735, Counsel Stack Legal Research, https://law.counselstack.com/opinion/manno-v-united-states-uscfc-2001.