Lummus Global Amazonas, S.A. v. Aguaytia Energy Del Peru, S.R. Ltda.

256 F. Supp. 2d 594, 2002 WL 31401996
CourtDistrict Court, S.D. Texas
DecidedJune 14, 2002
DocketCIV.A.H-01-495
StatusPublished
Cited by26 cases

This text of 256 F. Supp. 2d 594 (Lummus Global Amazonas, S.A. v. Aguaytia Energy Del Peru, S.R. Ltda.) is published on Counsel Stack Legal Research, covering District Court, S.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lummus Global Amazonas, S.A. v. Aguaytia Energy Del Peru, S.R. Ltda., 256 F. Supp. 2d 594, 2002 WL 31401996 (S.D. Tex. 2002).

Opinion

MEMORANDUM AND ORDER

ROSENTHAL, District Judge.

Lummus Global Amazonas, S.A. (“LGA”) designed and built natural gas pipeline, gathering, and processing facilities in Peru for the project owner, Aguay-tia Energy Del Peru S.R. Ltda. (“Aguay-tia”). The contract between LGA and Aguaytia contained a broad arbitration provision, providing for “final and binding arbitration” under the Rules of Arbitration of the International Chamber of Commerce. In September 1998, the parties began arbitration proceedings to resolve a number of claims and counterclaims under the contract. The proceedings, conducted in two phases, ended in June 2001. The arbitration panel issued three detailed written decisions and an addendum, resolving LGA’s claims for unpaid bonuses, change orders, and contract price adjustments, and Aguaytia’s counterclaims for liquidated damages for delays, the cost of remedying alleged defects in the construction, payment for pipe paid for but not purchased or installed, and a number of other disputed items. The panel concluded that LGA was required to pay Aguaytia a net amount of $13.4 million, exclusive of interest.

*600 In this lawsuit, LGA moves to vacate, modify, or amend the final and interim arbitration awards, asserting a number of defects in the arbitration process and result. Aguaytia asks this court to confirm and enforce the award, but to enter judgment that reduces the award by an offset of approximately $5.2 million that the parties have stipulated is owed to LGA.

The parties have presented starkly different characterizations of the claims and of the arbitration itself. LGA asserts that it delivered “a working, viable and commercially profitable facility” by the agreed-upon date, that has exceeded the parties’ projections of profit. Aguaytia contends that “LGA failed to complete, test and deliver the facilities at the times specified in the Agreement” and delivered the facilities months late, with material defects. LGA asserts that the arbitration represents a “mockery of justice,” in which the three-member panel, dominated by one arbitrator LGA challenges as biased, acted in “manifest disregard” of the governing law. Aguaytia asserts that the panel of recognized experts in construction law assembled and painstakingly analyzed a thorough and exhaustive record involving a number of very technical issues; correctly stated and applied the law; and based the specific findings that LGA challenges on the detailed technical facts disclosed in the record and the parties’ contract provisions. Aguaytia denies any arbitrator bias and emphasizes that LGA did not raise this claim until after the panel issued its award in favor of Aguaytia.

This court applies the standard for reviewing arbitration awards under the Federal Arbitration Act, 9 U.S.C. §§ 10, 11, and 12, to the extensive record, the arbitration panel’s detailed findings, and the parties’ contentions. LGA also invokes the Inter-American Convention on International Commercial Arbitration (the “Inter-American Convention”), 9 U.S.C. § 301 et seq., and the Convention on the Recognition and Enforcement of Foreign Arbitral Awards (the “New York Convention”), 9 U.S.C. §§ 201 et seq.

Most of the arguments LGA makes for vacating or modifying the awards challenge specific aspects of the awards. Two arguments, arbitrator bias and the panel’s refusal to grant the parties’ joint request to incorporate the stipulation as to credits and payments owing to LGA, are alleged as a basis for vacating the entire award. Each of the grounds LGA asserts, with Aguaytia’s response, raises the same set of issues: does LGA assert a sufficient basis to permit this court, under the narrow and deferential standard of review mandated by statute, to vacate the results of the already prolonged process that the parties agreed would be final and binding upon them?

Based on the pleadings, the motions and responses, the evidence, the arguments of counsel, and the applicable law, this court concludes that LGA has met the burden that the law imposes to vacate the results of contractually binding arbitration only as to two discrete aspects of the award. One is the award for certain IGV, or Peruvian value-added, taxes. This court vacates the portion of the award addressing LGA’s liability for certain IGV taxes and remands that issue to arbitration for a determination as to the amount of taxes owed. The second aspect is the status of the joint stipulation of certain payments and credits owed to LGA. The narrow scope of review does not permit this court to include the stipulation in the final judgment. This court remands the narrow issue of the effect of the stipulation as to payments and credits on the arbitration award to be resolved in arbitration. This court confirms all other aspects of the arbitration award. Specifically, this court DENIES LGA’s motion for discovery on the issue of evi *601 dent partiality or bias; DENIES LGA’s motions to vacate the award in its entirety; GRANTS, in part, and DENIES, in part, LGA’s motion to vacate specific aspects of the award; DENIES LGA’s supplemental petition and motion to vacate the award; GRANTS, in part, and DENIES, in part, Aguaytia’s motion to confirm and enforce the arbitration award; DENIES, without prejudice, Aguaytia’s motion for final judgment; and DENIES Aguaytia’s request for bond. This court also ORDERS the parties to appear for a status conference on April 12, 2002, at 9:00 a.m., to discuss the most efficient method of proceeding.

The reasons for these rulings are set out below.

I. Background

Aguaytia is organized and has its principal place of business in Peru. (Docket Entry No. 9). LGA is a Peruvian corporation with its principal place of business in Houston, Texas. (Docket Entry No. 1). LGA is a subsidiary of ABB Lummus Global, Inc., a Delaware corporation with its principal place of business in Houston, Texas. (Id.).

In February 1995, Aguaytia issued an invitation to bid for the design and construction of natural gas and natural gas liquid gathering, processing, and pipeline facilities in what the parties both describe as a “jungle” area in Peru. LGA submitted its bid in May 1995. Effective May 31, 1996, Aguaytia and LGA entered into an Agreement to design and construct a gas processing facility, a fractionation facility, and pipelines from wellheads to the gas plant and from the gas plant to other facilities. The pipelines connected the fractionation facility and a newly constructed power plant that was not part of the Agreement.

Clause 24.02(a) of the Agreement required the parties to submit “all disputes arising in connection with or relating to this Agreement” to “final and binding arbitration,” “pursuant to the rules of Arbitration of the International Chamber of Commerce.” (Docket Entry No. 9, Ex. 7). The Agreement provided that “[t]he substantive law applied in such arbitration shall be the law of New York.” (Id.).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Affordable Care, LLC v. McIntyre
S.D. Mississippi, 2022
Load Trail, LLC v. Joseph Julian
Court of Appeals of Texas, 2021
Vantage Deepwater Company v. Petrobras Amer
966 F.3d 361 (Fifth Circuit, 2020)
Delek Refining, Limited v. Local 202, Untd Steel
891 F.3d 566 (Fifth Circuit, 2018)
Salus Capital Partners, LLC v. Moser
289 F. Supp. 3d 468 (S.D. Illinois, 2018)
Jody James Farms, JV v. Altman Group, Inc.
506 S.W.3d 595 (Court of Appeals of Texas, 2016)
Timegate Studios, Inc. v. Southpeak Interactive, LLC
860 F. Supp. 2d 350 (S.D. Texas, 2012)
Dealer Computer Services, Inc. v. Michael Motor Co.
761 F. Supp. 2d 459 (S.D. Texas, 2010)
Townes Telecommunications, Inc. v. Travis, Wolff & Co.
291 S.W.3d 490 (Court of Appeals of Texas, 2009)
Fogal v. Stature Construction, Inc.
294 S.W.3d 708 (Court of Appeals of Texas, 2009)
Weber v. Merrill Lynch Pierce Fenner & Smith, Inc.
455 F. Supp. 2d 545 (N.D. Texas, 2006)
Adam Silva v. State
Court of Appeals of Texas, 2006

Cite This Page — Counsel Stack

Bluebook (online)
256 F. Supp. 2d 594, 2002 WL 31401996, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lummus-global-amazonas-sa-v-aguaytia-energy-del-peru-sr-ltda-txsd-2002.